ReraGenieLog inGet a buyer report

Home / Browse projects / Pune, Maharashtra / Kekarav Phase III

Registered Litigation declared Plotted project

Kekarav Phase III

By SHREM TRADING LLP

RG-MH-22541 · RERA P52100034729 · Last updated on MahaRERA portal: 3 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 7 cases
  • Completion date moved by 42 months
  • 5 extensions taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 42 months from the original
16 of 92Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 160 documents Report an error

Kekarav Phase III is a Plotted project by SHREM TRADING LLP in Pune, Maharashtra, registered with MahaRERA as P52100034729 on 20 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 42 months from the original filing. 76 of the 92 units on this registration are recorded sold or booked.

At a glance

Project

  • NameKekarav Phase III
  • TypePlotted
  • Location
    • Bavdhan Bk
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • RERA no.P52100034729
  • ReraGenie IDRG-MH-22541

Builder

  • NameSHREM TRADING LLP
  • Entity typePartnership
  • GSTIN27ABYFS9682H1Z0
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersHITESH RAMPRAKSH CHHATWAL, SMITA NITAN CHHATWAL, NITAN RAMPRAKASH CHHATWAL
  • Other registrations3 more →
  • No longer live1 lapsed, de-registered or revoked
  • Declared earlier projects3 →

Key dates

this monthRegisteredApr 2022First promiseJun 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Apr 2022
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2023)
  • BuildingsNot stated in filing
  • Documents filed160 files

Current status

83%76 of 92 units booked
67.8%Work done, per cost certificate

Figures as on 3 Jul 2026, this project's latest MahaRERA filing.

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

NA Plot Without Structure:

ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes85%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes65%
Street LightingYes60%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area64,665 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 May 2025

Approvals and building plan

Sanctioning authorityPMRDA
Permissible FSI30047.36
Proposed, not sanctioned30,047 sq m

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchGr Floor, Shri Amba Shanti Chambers, Opp Hotel Leela, Andheri Kurla Road, Andheri E, Mumbai, Maharas
Estimated costRs 64.45 cr
Cost incurredRs 43.71 cr
Work done67.81%
BuildingWingEstimatedIncurred
-NARs 64.45 crRs 43.71 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVKa Architecture
EngineerGeetanjali Anand Chappar
Chartered AccountantK K S S And Associates
Chartered AccountantMK Doshi and Associates
Chartered AccountantN N Bagwan and Associates
PartnerRole in project
SHREM TRADING LLP-

Extensions applied for5

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100024478Jun 2023 → Dec 2024

Reason as filed by the promoterReasons for Delay i. Amenities like club house & Landscaping Work is under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availability of project completion date.

EXT52100015400Jun 2023 → Jun 2024

Reason as filed by the promoterThe project situated in hilly area of Bavdhan and due to heavy rains in the said region during monsoon season project development activities on ground cannot be carried out for 4-6 months. The extension is needed as while executing the agreement for sale of unsold plots with registering authority & financing banks of customers need the RERA certificate showing availability of project completion date.

EXT52100027408Jun 2023 → Jun 2025

Reason as filed by the promoteri. Our project is located in hilly area, due to monsoon season & heavy rains in the region development activity cannot be carried out extensively for July to October period. Due to rains concrete road casting and other works cannot be done on project site. ii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works cannot be done for extended hours. iii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availabil

EA10072502026Jun 2023 → Dec 2025

Reason as filed by the promoteri. Our project is located in hilly area, due to pre monsoon rain the work progress hampered & further heavy rains in the region development activity cannot be carried out extensively for July to October period. Road concreting along with Services & misc work of 250 Rmt length balance to execute which will be done after rainy season for better quality. ii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works cannot be done for extended hours. iii. This extension is needed as, while executing the agreement of sale of unsold plots with

EA21032620324Jun 2023 → Dec 2026

Reason as filed by the promoterReasons for Delay - i. Supply chain disruptions for materials suited to hilly construction, such as reinforced concrete and drainage systems ii. Challenges in obtaining specialized equipment and skilled labor for slope stabilization and terracing, exacerbated by the site's steep gradients. iii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works could not be done for extended hours. iv. Project is near completion stage and nominal works such finishing, landscaping & handing over are in progress. We request an extension of the projec

Litigation declared7

CaseCourtStatus
43429/2019J M FC COURT PUNEHEARING
13429/2019J M FC COURT PUNEClosed
13428/2019J M FC COURT PUNEClosed
13427/2019J M FC COURT PUNEClosed
13426/2019J M FC COURT PUNEClosed
13425/2019J M FC COURT PUNEClosed
SCC 43429/2019/2019Additional Chief Judicial Magistrate, PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 31 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Mar 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed160

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: KEKARAV_ANNEXURES_SECTOR 3-compressed.pdf3 Jul 2026
Withdrawal Update Form 1File: Form 1 March 26 Sector 3.pdf3 Jul 2026
Withdrawal Update Form 2File: Form 2 March 26 Sector 3.pdf3 Jul 2026
Withdrawal Update Form 3File: Form 3 March 26 Sector 3.pdf3 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf3 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf3 Jul 2026
Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf13 Apr 2026
Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf13 Apr 2026
Layout approvalFile: 01-07_compressed.pdf21 Mar 2026
Layout approvalFile: 02-07.pdf21 Mar 2026
Layout approvalFile: 03-07_compressed.pdf21 Mar 2026
Layout approvalFile: 04-07.pdf21 Mar 2026
Layout approvalFile: 05-07.pdf21 Mar 2026
Layout approvalFile: 06-07.pdf21 Mar 2026
Layout approvalFile: 07-07.pdf21 Mar 2026
Form 1File: FORM1-SEC-3 MAR-25.pdf21 Mar 2026
Form 2File: Form 2 (2 March 2025).PDF21 Mar 2026
Form 3File: Form_3 March 25.pdf21 Mar 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold - March 25.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM1-SEC-3 JUN-25.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM1-SEC-3 SEP-25.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM1-SEC-3 DEC-25.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM1-SEC-3 DEC-25.pdf21 Mar 2026
Withdrawal Update Form 2File: Form 2 (2 June 2025).pdf21 Mar 2026
Withdrawal Update Form 2File: Form 2 (2 Sept 2025).pdf21 Mar 2026
Withdrawal Update Form 2File: FORM1-SEC-3 DEC-25.pdf21 Mar 2026
Withdrawal Update Form 2File: Form 2 (2 Dec 2025).pdf21 Mar 2026
Withdrawal Update Form 3File: FORM-3 JUNE 2025.pdf21 Mar 2026
Withdrawal Update Form 3File: FORM-3 Sept 25.pdf21 Mar 2026
Withdrawal Update Form 3File: FORM-3 DEC 2025.pdf21 Mar 2026
Withdrawal Update Form 3File: FORM-3 DEC 2025.pdf21 Mar 2026
Form 1File: 4Form 1_June 23.pdf20 Mar 2026
Form 2File: Form 2 June 23.pdf20 Mar 2026
Form 3File: Form 3 - June 23.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - June 23.pdf20 Mar 2026
Form 1File: Form 1_Dec 22.pdf20 Mar 2026
Form 2File: Form 2 March 23.pdf20 Mar 2026
Form 3File: Form 3 - March 23.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Dec 22.pdf20 Mar 2026
Form 1File: Form 1.pdf20 Mar 2026
Form 2File: Form 2.pdf20 Mar 2026
Form 3File: Form 3.pdf20 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Jun 22.pdf20 Mar 2026
Form 1File: 7Form 1 Q4 FY 23-24 March 24.pdf19 Mar 2026
Form 2File: Form 2 Q4 23-24 March 24.pdf19 Mar 2026
Form 3File: Form 3 - March 24.pdf19 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - March 24.pdf19 Mar 2026
Form 1File: Form 1 Q3 FY 24-25 Dec 24.pdf17 Mar 2026
Form 2File: Form 2 Q3 24-25 Dec 24.pdf17 Mar 2026
Form 3File: Form 3 - Dec 24.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sector III Dec 24.pdf17 Mar 2026
Form 1File: Form 1 Q2 FY 24-25 Sept 24.pdf17 Mar 2026
Form 2File: Form 2 Q2 24-25 Sept 24.pdf17 Mar 2026
Form 3File: Form 3 - Sept 24.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Sector III S.pdf17 Mar 2026
Form 1File: Form 1 Q1 FY 24-25 June 24.pdf17 Mar 2026
Form 2File: Form 2 Q1 24-25 June 24.pdf17 Mar 2026
Form 3File: Form 3 - June 24.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SECTOR III_JUNE24.pdf17 Mar 2026
Form 1File: Form 1 Q3 FY 23-24 Dec 23.pdf17 Mar 2026
Form 2File: Form 2 Q3 23-24 Dec 23.pdf17 Mar 2026
Form 3File: Form 3 - Dec 23.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Dec 23.pdf17 Mar 2026
Form 1File: Form 1_Sept 23.pdf17 Mar 2026
Form 2File: Form 2 Q2 23-24 Sept 23.pdf17 Mar 2026
Form 3File: Form 3 - Sept 23.pdf17 Mar 2026
Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Sept 23.pdf17 Mar 2026
Form 1File: 3Form 1_March 23.pdf16 Mar 2026
Form 2File: 2Form 2 March 23.pdf16 Mar 2026
Form 3File: 2Form 3 - March 23.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure March 23.pdf16 Mar 2026
Form 1File: 1Form 1_Sept 22.pdf16 Mar 2026
Form 2File: 1Form 2_Sept 22.pdf16 Mar 2026
Form 3File: 1Form 3 - Sept 22.pdf16 Mar 2026
Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf16 Mar 2026
Form 5 (FY 2024-2025)File: SIGNED Phase 3_FORM 5 MAHARERA 24-25.pdf16 Mar 2026
Form 5 (FY 2022-2023)File: Form 5 22-23.pdf16 Mar 2026
Form 5 (FY 2023-2024)File: Form 5 23-24.pdf16 Mar 2026
Layout approvalFile: 01-07_compressed.pdf9 May 2025
Layout approvalFile: 02-07.pdf9 May 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Kekarav Phase IP52100025894Bavdhan, Pune86Jul 2020CompletedMar 2024Registered original: Jul 2022Mar 2024
Kekarav Phase IIP52100031548Bavadhan Budruk, Pune17Oct 2021OngoingSep 2022Not delivered

How this compares with Pune

83%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 42 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Kekarav Phase III on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavdhan Bk13,700+ in Pune

Builder: SHREM TRADING LLP

SHREM TRADING LLP has 4 registrations on MahaRERA, including Kekarav Phase I and Kekarav Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Kekarav Phase III is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Kekarav Phase III?

The registered promoter entity is SHREM TRADING LLP, a partnership as per the filing. Its GSTIN 27ABYFS9682H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Kekarav Phase III?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Kekarav Phase III?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Kekarav Phase III?

The professionals named in the filing: Architect: VKa Architecture; Engineer: Geetanjali Anand Chappar; Chartered Accountant: K K S S And Associates; Chartered Accountant: MK Doshi and Associates; Chartered Accountant: N N Bagwan and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Kekarav Phase III?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Kekarav Phase III. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Kekarav Phase III to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.