Home / Browse projects / Pune, Maharashtra / Kekarav Phase III
Kekarav Phase III
RG-MH-22541 · RERA P52100034729 · Last updated on MahaRERA portal: 3 Jul 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 7 cases
- Completion date moved by 42 months
- 5 extensions taken
Clear
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kekarav Phase III is a Plotted project by SHREM TRADING LLP in Pune, Maharashtra, registered with MahaRERA as P52100034729 on 20 Apr 2022. Possession is promised by 31 Dec 2026. The completion date has moved by 42 months from the original filing. 76 of the 92 units on this registration are recorded sold or booked.
At a glance
Project
- NameKekarav Phase III
- TypePlotted
- Location
- Bavdhan Bk
- Bavadhan BK
- Mulshi
- Pune
- 411021
- Pincode411021
- RERA no.P52100034729
- ReraGenie IDRG-MH-22541
Builder
- NameSHREM TRADING LLP
- Entity typePartnership
- GSTIN27ABYFS9682H1Z0
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersHITESH RAMPRAKSH CHHATWAL, SMITA NITAN CHHATWAL, NITAN RAMPRAKASH CHHATWAL
- Other registrations3 more →
- No longer live1 lapsed, de-registered or revoked
- Declared earlier projects3 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on20 Apr 2022
- Promised completion31 Dec 2026
- Revised completionRevised to 31 Dec 2026 (originally 30 Jun 2023)
- BuildingsNot stated in filing
- Documents filed160 files
Current status
Figures as on 3 Jul 2026, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 3 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities15
As on 3 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 90% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 85% |
| Storm Water Drains | Yes | 75% |
| Landscaping & Tree Planting | Yes | 65% |
| Street Lighting | Yes | 60% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 64.45 cr | Rs 43.71 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VKa Architecture |
| Engineer | Geetanjali Anand Chappar |
| Chartered Accountant | K K S S And Associates |
| Chartered Accountant | MK Doshi and Associates |
| Chartered Accountant | N N Bagwan and Associates |
| Partner | Role in project |
|---|---|
| SHREM TRADING LLP | - |
Extensions applied for5
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterReasons for Delay i. Amenities like club house & Landscaping Work is under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availability of project completion date.
Reason as filed by the promoterThe project situated in hilly area of Bavdhan and due to heavy rains in the said region during monsoon season project development activities on ground cannot be carried out for 4-6 months. The extension is needed as while executing the agreement for sale of unsold plots with registering authority & financing banks of customers need the RERA certificate showing availability of project completion date.
Reason as filed by the promoteri. Our project is located in hilly area, due to monsoon season & heavy rains in the region development activity cannot be carried out extensively for July to October period. Due to rains concrete road casting and other works cannot be done on project site. ii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works cannot be done for extended hours. iii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availabil
Reason as filed by the promoteri. Our project is located in hilly area, due to pre monsoon rain the work progress hampered & further heavy rains in the region development activity cannot be carried out extensively for July to October period. Road concreting along with Services & misc work of 250 Rmt length balance to execute which will be done after rainy season for better quality. ii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works cannot be done for extended hours. iii. This extension is needed as, while executing the agreement of sale of unsold plots with
Reason as filed by the promoterReasons for Delay - i. Supply chain disruptions for materials suited to hilly construction, such as reinforced concrete and drainage systems ii. Challenges in obtaining specialized equipment and skilled labor for slope stabilization and terracing, exacerbated by the site's steep gradients. iii. Project is located near HEMRL land and due to continuous monitoring by HEMRL authority at night development works could not be done for extended hours. iv. Project is near completion stage and nominal works such finishing, landscaping & handing over are in progress. We request an extension of the projec
Litigation declared7
| Case | Court | Status |
|---|---|---|
| 43429/2019 | J M FC COURT PUNE | HEARING |
| 13429/2019 | J M FC COURT PUNE | Closed |
| 13428/2019 | J M FC COURT PUNE | Closed |
| 13427/2019 | J M FC COURT PUNE | Closed |
| 13426/2019 | J M FC COURT PUNE | Closed |
| 13425/2019 | J M FC COURT PUNE | Closed |
| SCC 43429/2019/2019 | Additional Chief Judicial Magistrate, Pune | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Jul 2026 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 29 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 28 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2026
Documents filed160
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 160 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Layout approvalFile: KEKARAV_ANNEXURES_SECTOR 3-compressed.pdf | 3 Jul 2026 |
| Withdrawal Update Form 1File: Form 1 March 26 Sector 3.pdf | 3 Jul 2026 |
| Withdrawal Update Form 2File: Form 2 March 26 Sector 3.pdf | 3 Jul 2026 |
| Withdrawal Update Form 3File: Form 3 March 26 Sector 3.pdf | 3 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf | 3 Jul 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf | 3 Jul 2026 |
| Form 2A (FY 2024-2025)File: Form 2A FY 24-25.pdf | 13 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A FY 25-26.pdf | 13 Apr 2026 |
| Layout approvalFile: 01-07_compressed.pdf | 21 Mar 2026 |
| Layout approvalFile: 02-07.pdf | 21 Mar 2026 |
| Layout approvalFile: 03-07_compressed.pdf | 21 Mar 2026 |
| Layout approvalFile: 04-07.pdf | 21 Mar 2026 |
| Layout approvalFile: 05-07.pdf | 21 Mar 2026 |
| Layout approvalFile: 06-07.pdf | 21 Mar 2026 |
| Layout approvalFile: 07-07.pdf | 21 Mar 2026 |
| Form 1File: FORM1-SEC-3 MAR-25.pdf | 21 Mar 2026 |
| Form 2File: Form 2 (2 March 2025).PDF | 21 Mar 2026 |
| Form 3File: Form_3 March 25.pdf | 21 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold - March 25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: FORM1-SEC-3 JUN-25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: FORM1-SEC-3 SEP-25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: FORM1-SEC-3 DEC-25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 1File: FORM1-SEC-3 DEC-25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 (2 June 2025).pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 (2 Sept 2025).pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: FORM1-SEC-3 DEC-25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 2File: Form 2 (2 Dec 2025).pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 JUNE 2025.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 Sept 25.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 DEC 2025.pdf | 21 Mar 2026 |
| Withdrawal Update Form 3File: FORM-3 DEC 2025.pdf | 21 Mar 2026 |
| Form 1File: 4Form 1_June 23.pdf | 20 Mar 2026 |
| Form 2File: Form 2 June 23.pdf | 20 Mar 2026 |
| Form 3File: Form 3 - June 23.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - June 23.pdf | 20 Mar 2026 |
| Form 1File: Form 1_Dec 22.pdf | 20 Mar 2026 |
| Form 2File: Form 2 March 23.pdf | 20 Mar 2026 |
| Form 3File: Form 3 - March 23.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Dec 22.pdf | 20 Mar 2026 |
| Form 1File: Form 1.pdf | 20 Mar 2026 |
| Form 2File: Form 2.pdf | 20 Mar 2026 |
| Form 3File: Form 3.pdf | 20 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Jun 22.pdf | 20 Mar 2026 |
| Form 1File: 7Form 1 Q4 FY 23-24 March 24.pdf | 19 Mar 2026 |
| Form 2File: Form 2 Q4 23-24 March 24.pdf | 19 Mar 2026 |
| Form 3File: Form 3 - March 24.pdf | 19 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - March 24.pdf | 19 Mar 2026 |
| Form 1File: Form 1 Q3 FY 24-25 Dec 24.pdf | 17 Mar 2026 |
| Form 2File: Form 2 Q3 24-25 Dec 24.pdf | 17 Mar 2026 |
| Form 3File: Form 3 - Dec 24.pdf | 17 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sector III Dec 24.pdf | 17 Mar 2026 |
| Form 1File: Form 1 Q2 FY 24-25 Sept 24.pdf | 17 Mar 2026 |
| Form 2File: Form 2 Q2 24-25 Sept 24.pdf | 17 Mar 2026 |
| Form 3File: Form 3 - Sept 24.pdf | 17 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sector III S.pdf | 17 Mar 2026 |
| Form 1File: Form 1 Q1 FY 24-25 June 24.pdf | 17 Mar 2026 |
| Form 2File: Form 2 Q1 24-25 June 24.pdf | 17 Mar 2026 |
| Form 3File: Form 3 - June 24.pdf | 17 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: SOLD UNSOLD SECTOR III_JUNE24.pdf | 17 Mar 2026 |
| Form 1File: Form 1 Q3 FY 23-24 Dec 23.pdf | 17 Mar 2026 |
| Form 2File: Form 2 Q3 23-24 Dec 23.pdf | 17 Mar 2026 |
| Form 3File: Form 3 - Dec 23.pdf | 17 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Dec 23.pdf | 17 Mar 2026 |
| Form 1File: Form 1_Sept 23.pdf | 17 Mar 2026 |
| Form 2File: Form 2 Q2 23-24 Sept 23.pdf | 17 Mar 2026 |
| Form 3File: Form 3 - Sept 23.pdf | 17 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: S3-Disclosure of Sold Unsold - Sept 23.pdf | 17 Mar 2026 |
| Form 1File: 3Form 1_March 23.pdf | 16 Mar 2026 |
| Form 2File: 2Form 2 March 23.pdf | 16 Mar 2026 |
| Form 3File: 2Form 3 - March 23.pdf | 16 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure March 23.pdf | 16 Mar 2026 |
| Form 1File: 1Form 1_Sept 22.pdf | 16 Mar 2026 |
| Form 2File: 1Form 2_Sept 22.pdf | 16 Mar 2026 |
| Form 3File: 1Form 3 - Sept 22.pdf | 16 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Disclosure.pdf | 16 Mar 2026 |
| Form 5 (FY 2024-2025)File: SIGNED Phase 3_FORM 5 MAHARERA 24-25.pdf | 16 Mar 2026 |
| Form 5 (FY 2022-2023)File: Form 5 22-23.pdf | 16 Mar 2026 |
| Form 5 (FY 2023-2024)File: Form 5 23-24.pdf | 16 Mar 2026 |
| Layout approvalFile: 01-07_compressed.pdf | 9 May 2025 |
| Layout approvalFile: 02-07.pdf | 9 May 2025 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kekarav Phase IP52100025894 | Bavdhan, Pune | 86 | Jul 2020 | Completed | Mar 2024Registered original: Jul 2022 | Mar 2024 |
| Kekarav Phase IIP52100031548 | Bavadhan Budruk, Pune | 17 | Oct 2021 | Ongoing | Sep 2022 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 3 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations, which the RERA portal never shows together
- All 160 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Kekarav Phase III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bavdhan Bk13,700+ in Pune
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: SHREM TRADING LLP
SHREM TRADING LLP has 4 registrations on MahaRERA, including Kekarav Phase I and Kekarav Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if Kekarav Phase III is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kekarav Phase III?
The registered promoter entity is SHREM TRADING LLP, a partnership as per the filing. Its GSTIN 27ABYFS9682H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kekarav Phase III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kekarav Phase III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kekarav Phase III?
The professionals named in the filing: Architect: VKa Architecture; Engineer: Geetanjali Anand Chappar; Chartered Accountant: K K S S And Associates; Chartered Accountant: MK Doshi and Associates; Chartered Accountant: N N Bagwan and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kekarav Phase III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback