Kekarav Phase I
RG-MH-16436 · RERA P52100025894 · Last updated on MahaRERA portal: 23 Dec 2024
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 31 months past the filed date
- Completion date moved by 20 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Kekarav Phase I is a Plotted project by SHREM TRADING LLP in Pune, Maharashtra, registered with MahaRERA as P52100025894 on 27 Jul 2020. Possession was promised by 31 Mar 2024 and is now 31 months past that date. The completion date has moved by 20 months from the original filing. 84 of the 86 units on this registration are recorded sold or booked.
At a glance
Project
- NameKekarav Phase I
- TypePlotted
- Location
- Bavdhan Road
- Bavdhan
- Bavadhan BK
- Mulshi
- Pune
- 411021
- Pincode411021
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100025894
- ReraGenie IDRG-MH-16436
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on27 Jul 2020
- Promised completion31 Mar 2024
- Revised completionRevised to 31 Mar 2024 (originally 31 Jul 2022)
- BuildingsNot stated in filing
- Documents filed57 files
Current status
Figures as on 23 Dec 2024, this project's latest MahaRERA filing.
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 23 Dec 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
NA Plot Without Structure:
| Activity | Progress |
|---|---|
| Excavation | Not applicable |
| Basement (if any) | Not applicable |
| Podiums (if any) | Not applicable |
| Plinth | Not applicable |
| Stilt Floor | Not applicable |
| Slabs of Super Structure | Not applicable |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | Not applicable |
| Sanitary Fittings within the flats / premises | Not applicable |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | Not applicable |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | Not applicable |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | Not applicable |
Progress on shared amenities21
As on 23 Dec 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 80% |
| Water Supply | Yes | 80% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 80% |
| Storm Water Drains | Yes | 80% |
| Landscaping & Tree Planting | Yes | 60% |
| Street Lighting | Yes | 80% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 80% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | No | Not applicable |
| Electrical meter room, sub-station, receiving station | Yes | 75% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
| Access Road Development | Yes | 80% |
| Electrical Lines and feeder Pillars | Yes | 80% |
| Internal Road development with necessary retaining wall | Yes | 80% |
| Plot Fencing | Yes | 80% |
| Project Plot Compound Wall | Yes | 85% |
| Solar Panels for common area lighting | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners3
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | VKu Urban |
| Engineer | Geetanjali Chappar |
| Chartered Accountant | K K S S & Associates |
| Partner | Role in project |
|---|---|
| SHREM TRADING LLP | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterAll the project facilities are ready only landscape & amenities are under construction which requires additional time. In addition to this, the project situated in hilly area of Bavdhan and due to heavy rains in the said region during monsoon season project developments activities on ground cannot be carried out for 4-6 months. (iii) This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks of Customers’ need the RERA Certificate showing availability of project completion date.
Reason as filed by the promoterAll the project facilities are ready only landscaping work in under construction which requires additional time. The extension is needed as, while executing the agreement of sale unsold plots with registering authority and financing banks of customers need the RERA certificate showing availability of project completion date.
Reason as filed by the promoteri. Amenities like club house & Landscaping Work are under construction which requires additional time. ii. This extension is needed as, while executing the agreement of sale of unsold plots with registering authority & financing banks Customers need the RERA Certificate showing the availability of the project completion date.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 24 Jul 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 24 Jul 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 24 Jul 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 24 Jul 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed57
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Architect’s Certificate on Completion of Project (Form 4)File: S1-Q4-FY 23-24- Architect Completion Certificate.pdf | 23 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: S1-Q2-FY 23-24- Architect Certificate.pdf | 25 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: S1-Q3-FY 23-24- Architect Certificate.pdf | 25 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: S1-Q3-FY 23-24- Engineer Certificate.pdf | 25 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: S1-Q4-FY 23-24- Engineer Certificate.pdf | 25 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: S1-Q4-FY 23-24- Engineer Quality Certificate.pdf | 25 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: S1-Q3-FY 23-24- CA Certificate.pdf | 25 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: S1-Q4-FY 23-24- CA Certificate.pdf | 25 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector 1 -Architect Certifciate.pdf | 4 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: SECTOR-1 ENGINEERS CERTIFICATE.PDF | 4 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: SECTOR-1 QUALITY ASSURANCE CERTIFICATE.PDF | 4 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 CA Certificate Phase I - Kekarav-compressed.pdf | 4 Apr 2024 |
| Details of encumbrancesFile: SECTOR1.pdf | 21 Dec 2023 |
| CERSAI detailsFile: SECTOR1DEC.pdf | 21 Dec 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200290865033_For_Debtor_Based_Search_21_12_2023_15_23_11_976.pdf | 21 Dec 2023 |
| CERSAI detailsFile: CERSAI_Search_Report_200290864898_For_Debtor_Based_Search_21_12_2023_15_22_51_595.pdf | 21 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf | 22 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf | 22 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A.pdf | 22 Aug 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 of CA.pdf | 22 Aug 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Phase 1_FORM 5 MAHARERA 22-23_0001.pdf | 27 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Architect Cert.pdf | 19 Apr 2023 |
| Declaration in FORM BFile: FORM - B SECTOR 1.pdf | 17 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 - SECTOR 1.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Disclosure- Phase I.pdf | 17 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase I Signed_compressed.pdf | 17 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM -5_2021-2022_Phase_I.pdf | 17 Apr 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM -5_2021-2022_Phase_I.pdf | 17 Apr 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM - 1 SECTOR - 1.pdf | 30 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM - 2 SECTOR - 1.pdf | 30 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM - 2A SECTOR - 1.pdf | 30 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM - 3 SECTOR (Compressed).pdf | 30 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE SECTOR 1.pdf | 22 Apr 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE SECTOR 1.pdf | 22 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200233953499_For_Debtor_Based_Search_30_03_2022_15_00_26_768.pdf | 22 Apr 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200233953746_For_Debtor_Based_Search_30_03_2022_15_02_06_885.pdf | 22 Apr 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM_3_Sec1.pdf | 30 Mar 2022 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Kekarav_Society Formation.PDF | 2 Sep 2021 |
| Layout approvalFile: Layout Approval.pdf | 24 Jul 2020 |
| Building plan approval or NA orderFile: NA Order Plotted Dev.pdf | 24 Jul 2020 |
| PAN CardFile: Shrem PAN.pdf | 24 Jul 2020 |
| Copy of the legal title reportFile: 1Legal Title.pdf | 24 Jul 2020 |
| Copy of the legal title reportFile: 2Legal Title.pdf | 24 Jul 2020 |
| Copy of the legal title reportFile: 3Legal Title.pdf | 24 Jul 2020 |
| Copy of the legal title reportFile: 4Legal Title.pdf | 24 Jul 2020 |
| Details of encumbrancesFile: ENCUMBRANCE CERTIFICATE.pdf | 24 Jul 2020 |
| Details of encumbrancesFile: Index II Mortgage Deed.pdf | 24 Jul 2020 |
| Copy of Layout Approval (in case of layout)File: Layout Approval.pdf | 24 Jul 2020 |
| Building Plan Approval / NA Order for plotted developmentFile: NA Order Plotted Dev.pdf | 24 Jul 2020 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert.pdf | 24 Jul 2020 |
| Declaration in FORM BFile: RERA DECLARATION FORM -B_compressed.pdf | 24 Jul 2020 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Cert.pdf | 24 Jul 2020 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate - Form 2.pdf | 24 Jul 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-1-3.pdf | 24 Jul 2020 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate-4-6_compressed.pdf | 24 Jul 2020 |
| Proforma of Allotment letterFile: Agreement for Sale (main) -Final.pdf | 24 Jul 2020 |
| Proforma of Allotment letterFile: ANNEXURE I Guidelines and Constraints.pdf | 24 Jul 2020 |
Promoter's earlier projects2
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Kekarav Phase IIIP52100034729 | Bavdhan Bk, Pune | 92 | Apr 2022 | Ongoing | Jun 2025Registered original: Jun 2023 | Not delivered |
| Kekarav Phase IIP52100031548 | Bavadhan Budruk, Pune | 17 | Oct 2021 | Ongoing | Sep 2022 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 3 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 57 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Kekarav Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Bavdhan13,700+ in Pune
Filed coordinates, straight-line distance. 32 registered projects within 2 km.
NYATI EQUINOX I
MIHIR HOMES ENTERPRISE LLP
Puraniks Abitante Fiore, Phase 2A
Puranik Buildcon Private Limited
Puraniks Abitante Fiore, Phase 2B
Puranik Buildcon Private Limited
cloud 51
OREE REALITY PVT LTD
CIELO BY VTP LUXE
DELAS REALCON LLP
Puraniks Abitante Fiore Phase 2C1
Puranik Buildcon Private Limited
Builder: SHREM TRADING LLP
SHREM TRADING LLP has 4 registrations on MahaRERA, including Kekarav Phase I and Kekarav Phase II. Its filings disclose 3 earlier MahaRERA projects: declares 1 of 1 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Kekarav Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Kekarav Phase I is delayed beyond 31 Mar 2024?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Kekarav Phase I?
The registered promoter entity is SHREM TRADING LLP, a partnership as per the filing. Its GSTIN 27ABYFS9682H1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Kekarav Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Kekarav Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Kekarav Phase I?
The professionals named in the filing: Architect: VKu Urban; Engineer: Geetanjali Chappar; Chartered Accountant: K K S S & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Kekarav Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback