Home / Browse projects / Mumbai City, Maharashtra / Gadkari Paradise
Gadkari Paradise
By Gadkari Builders & Associates
RG-MH-25458 · RERA P51900011571 · Last updated on MahaRERA portal: 11 Aug 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 132 months
- 3 extensions taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Gadkari Paradise is a Residential / Group Housing project by Gadkari Builders & Associates in Mumbai City, Maharashtra, registered with MahaRERA as P51900011571 on 31 Aug 2017. Possession is promised by 31 Dec 2030. The completion date has moved by 132 months from the original filing. 0 of the 3 units on this registration are recorded sold or booked, and 2 of 11 construction stages are filed complete.
At a glance
Project
- NameGadkari Paradise
- TypeResidential / Group Housing
- Location
- Postal Colony
- Chembur
- Mumbai City
- 400071
- Pincode400071
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900011571
- ReraGenie IDRG-MH-25458
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on31 Aug 2017
- Promised completion31 Dec 2030
- Revised completionRevised to 31 Dec 2030 (originally 31 Dec 2019)
- Buildings1 building record
- Documents filed91 files
Current status
Figures as on 11 Aug 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Gadkari Paradise | NA | 0 | 0 | 3 | 0 | 3 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 11 Aug 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
2 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.
Gadkari Paradise: 18% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 11 Aug 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | No | Not applicable |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | Yes | 100% |
Parking filed19
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Gadkari Paradise | NA | Rs 7.70 cr | Rs 3.86 cr |
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar Saee Itkhede |
| Architect | Ar Jairaj Irasamale |
| Engineer | Mehta Sawant |
| Chartered Accountant | MAHENDRA TILAK |
| Partner | Role in project |
|---|---|
| Gadkari Builders & Associates | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterplease see the letter attached
Reason as filed by the promoterwe are not able to start the work and also due to lack of funds on our side we have failed to complete on time. delay in approval , we have not sold any flats in this project now we want to start and complete the project at the earliest.
Reason as filed by the promoteras per the consultation with senior consultants in Mumbai Shri. B.H. Wadhwa, Architect, he advised us to take up this project and accordingly we accepted the said project in the year 2014 and Development Rights & Power of Attorney had been registered. We also obtained all the permissions / approvals from M.C.G.M. We got plinth C.C. and completed plinth construction and thereafter also obtained concessional approval upto 10th floor from the Commissioner of M.C.G.M. Thereafter we approached for further C.C., however, we were informed that further C.C. cannot be granted unless the said Plot is co
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 31 Jul 2017 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Jul 2017 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 31 Jul 2017 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 8 Dec 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2030
Documents filed91
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 91 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: FORM 2 RCC CONSULTANT_March26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 2File: FORM 2 RCC CONSULTANT_March26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_March26.pdf | 11 Aug 2026 |
| Withdrawal Update Form 1File: FORM 1 ARCHITECT_March26.pdf | 29 May 2026 |
| Withdrawal Update Form 2File: FORM 2 RCC CONSULTANT_March26.pdf | 29 May 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_March26.pdf | 29 May 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_June 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 2_RCC CONSULTANT_ Dec 2024.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_March 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_June 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Sept 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 1File: FORM 1_ARCHITECT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_ Dec 2024.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_ March 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_June 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Sept 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 2File: FORM 2_RCC CONSULTANT_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_ June 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_Dec 2024.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3_CA Certificate_March 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_ June 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Sept 2025.pdf | 6 Feb 2026 |
| Withdrawal Update Form 3File: Form 3 CA Certificate_Dec 2025.pdf | 6 Feb 2026 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Fy 18-19.pdf | 20 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Fy 19-20.pdf | 20 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20-21 (1).pdf | 20 Jun 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 20 Jun 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22) (1).pdf | 16 Jun 2023 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf | 16 Jun 2023 |
| Declaration in FORM BFile: Gadkari Paradise.pdf | 31 May 2023 |
| Certificates of CA (Form 3)File: Form 3 - CA Certificate.pdf | 31 May 2023 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 - Architect Certificate.pdf | 30 May 2023 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 - Engineer Certificate.pdf | 30 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A.pdf | 30 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A Declaration.pdf | 23 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A Declaration.pdf | 23 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A Declaration.pdf | 23 May 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 5 FY 21-22.pdf | 23 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 5 FY 20-21.pdf | 23 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 Fy 18-19.pdf | 23 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 Fy 19-20.pdf | 23 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21-22.pdf | 23 Jan 2023 |
| Proforma of Agreement for saleFile: Form 5 FY 20-21.pdf | 23 Jan 2023 |
| Declaration about Commencement CertificateFile: Declaration About Commencement Certificate.pdf | 26 Nov 2022 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate for RERA Extension.pdf | 23 Aug 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - CA Certificate - Gadkari Paradise.pdf | 23 Aug 2022 |
| Certificates of CA (Form 5)File: Scan 1.pdf | 1 Jan 2019 |
| PAN CardFile: GBA Pancard - 1.pdf | 8 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate - Paradise.pdf | 8 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: Further CC upto First Floor - Paradise.pdf | 8 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: postal colony CC Revallation.pdf | 8 Dec 2018 |
| Commencement Certificates / NA Order for plotted developmentFile: postal colony CC.pdf | 8 Dec 2018 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Srushti EnclaveP51900011095 | Chembur, Mumbai Suburban | 59 | Aug 2017 | Ongoing | Jun 2025Registered original: Dec 2019 | Not delivered |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 91 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Gadkari Paradise on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Chembur780+ in Mumbai City
Filed coordinates, straight-line distance. 236 registered projects within 2 km.
Hiranandani Maitri Park Phase 1
SHODEN DEVELOPERS PRIVATE LIMITED
Premiere by Panache
Panache Developers Pvt Ltd.
Sai Shrushti
Shree Sai Realtors
MASS METROPOLIS
GRACE URBAN DEVELOPMENT CORPORATION
ELEVIA
VIDA INFRAHUB LLP
PODDAR HARMONY
PODDAR CREATORS LLP
See every Mumbai City project, with the district possession charts
Builder: Gadkari Builders & Associates
Gadkari Builders & Associates has 2 registrations on MahaRERA, including Srushti Enclave and Gadkari Paradise. Its filings disclose 1 earlier MahaRERA project, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What are my rights if Gadkari Paradise is delayed beyond 31 Dec 2030?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Gadkari Paradise?
The registered promoter entity is Gadkari Builders & Associates, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Gadkari Paradise?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Gadkari Paradise?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Gadkari Paradise?
The professionals named in the filing: Architect: Ar Saee Itkhede; Architect: Ar Jairaj Irasamale; Engineer: Mehta Sawant; Chartered Accountant: MAHENDRA TILAK. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Gadkari Paradise?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback