Red flags

  • Possession 1 months past the filed date
  • Litigation declared, 2 cases
  • 10 complaints at MahaRERA
  • Completion date moved by 21 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Sep 2026Possession promised1 month past this date
10 of 11Construction stages donefurthest along: Stilt Floor, 0%
176 of 467Units unsoldnot recorded sold or booked
10Complaints at MahaRERAon this registration
Jump to the 387 documents Report an error

MASS METROPOLIS is a Others project by GRACE URBAN DEVELOPMENT CORPORATION in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012210 on 1 Sep 2017. Possession was promised by 30 Sep 2026 and is now 1 months past that date. The completion date has moved by 21 months from the original filing. 291 of the 467 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 10 complaints are on record with the regulator.

At a glance

Project

  • NameMASS METROPOLIS
  • TypeOthers
  • Location
    • MAHARASHTRA
    • CHEMBUR
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012210
  • ReraGenie IDRG-MH-25552

Builder

  • NameGRACE URBAN DEVELOPMENT CORPORATION
  • Entity typePartnership
  • PartnersDanish Ataullah Ansari, SHABNAM ATAULLAH ANSARI

Key dates

1 months past promisethis monthRegisteredSep 2017First promiseDec 2024Revised toSep 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Sep 2017
  • Promised completion30 Sep 2026
  • Revised completionRevised to 30 Sep 2026 (originally 30 Dec 2024)
  • Buildings1 building record
  • Documents filed387 files

Current status

62%291 of 467 units booked
88.5%Work done, per cost certificate

Figures as on 19 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MASS METROPOLISNA1919339128467

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 19 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

MASS METROPOLIS: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 19 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes0%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes90%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed132

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots132
Closed/Covered132

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area10,030 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on9 Jan 2026
LandownerVillageDistrict
PNR BUILDERS AND DEVELOPERSAndheriMumbai Suburban

Approvals and building plan

Sanctioning authoritySLUM REHABILITATION AUTHORITY
Permissible FSI27596.82
Proposed, not sanctioned27,597 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchLINKING ROAD BANDRA WEST
Estimated costRs 128.35 cr
Cost incurredRs 113.59 cr
Work done88.5%
BuildingWingEstimatedIncurred
MASS METROPOLISNARs 89.85 crRs 80.86 cr
-NARs 38.51 crRs 32.73 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIEW DIMENSION
EngineerMOHSIN SHAIKH
Chartered AccountantAnita Choudhari & Co.
Chartered AccountantAnand A. Yadav & Associates
PartnerRole in project
GRACE URBAN DEVELOPMENT CORPORATION-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800025793Dec 2024 → Dec 2025

Reason as filed by the promoterDue to ongoing litigation pertaining to the vacating of the project plot, which directly impeded progress during a critical phase of the project timeline, Furthermore, the outbreak of the COVID-19 pandemic caused a complete suspension of project operations for a period of one year in compliance with government-mandated lockdowns and health regulations. This disruption was compounded by a subsequent shortage of skilled labour, which further hampered the ability to resume and sustain project activities at the required pace. As a direct result of these cumulative factors, the completion timeline

EA21012619529Dec 2024 → Mar 2026

Reason as filed by the promoterDue to the Occupancy Certificate application being under scrutiny and compliance verification by the competent planning authority and Certain procedural compliances, clarifications, and statutory approvals required by the authority are currently in process and are beyond the direct control of the Promoter, resulting in additional time being required despite the Promoter’s due diligence and timely compliance.

EA31032620498Dec 2024 → Sep 2026

Reason as filed by the promoterThe RERA-designated bank account of the project remained blocked for a period of approximately one month due to the expiry of the RERA registration certificate. During this period, the project funds were inaccessible, and we were consequently unable to make timely payments to contractors and subcontractors. The said circumstances, being beyond our immediate control, adversely impacted the progress of work at site. As a direct result thereof, there has been a delay of approximately three (3) months from the originally scheduled date of completion.

Litigation declared2

CaseCourtStatus
23971/2015/2015SUPREME COURTTO PROCEED WITH THE SCHEME
23971/2015SUPREME COURTOngoing

Complaints filed with MahaRERA10

Case no.ComplainantRespondentFiled
CC006000000078369RASHMI BEHERADANISH ANSARI "MASS METROPOLIS" PROJECT KURLA MUMBAI07/03/2019
CC006000000292588Aruna Prasann MoreGrace Urban Development Corporation17/09/2022
CC006000000292595Sunil Vishwanath SinghGrace Urban Development Corporation13/09/2022
CC006000000292597Chandrashekhar Janakram VermaGrace Urban Development Corporation13/09/2022
CC006000000292610Altaf Nisar Ahmed KhanGrace Urban Development Corporation14/09/2022
CC006000000303089Mohammed Tariq SiddiqueGrace Urban Development corporation21/10/2022
CC12504409Asgar Ali ShaikhGRACE URBAN DEVELOPMENT CORPORATION11/12/2025
CC12504529Asgar Ali ShaikhGRACE URBAN DEVELOPMENT CORPORATION18/12/2025
CC12603541GRACE URBAN DEVELOPMENT CORPORATIONPrashant Devnand Nagella08/06/2026
CC12605388mariyam mohammed mujeeb shaikhGRACE URBAN DEVELOPMENT CORPORATION22/08/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Oct 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 19 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 5 Apr 2018Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Jan 2025

Documents filed387

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 387 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: GUDC architect certificate March 2026.pdf19 Jun 2026
Withdrawal Update Form 2File: GUDC engineer certificate 310326.pdf19 Jun 2026
Withdrawal Update Form 3File: Grace Urban Form 3 March 26 Signed PDF.pdf19 Jun 2026
Withdrawal Update Form 1File: GUDC ARCHITECT CERTIFICATE 122025.pdf21 Jan 2026
Withdrawal Update Form 2File: RERA ENG CERTIFICATE GUDC 122025.pdf21 Jan 2026
Withdrawal Update Form 3File: GUDC 31122025 - Signed-scan.pdf21 Jan 2026
Withdrawal Update Form 1File: GUDC ARCHITECT CERTIFICATE 062025.pdf20 Jan 2026
Withdrawal Update Form 1File: GUDC ARCHITECT CERTIFICATE 092025.pdf20 Jan 2026
Withdrawal Update Form 2File: RERA ENG CERTIFICATE GUDC 062025.pdf20 Jan 2026
Withdrawal Update Form 2File: RERA ENG CERTIFICATE GUDC 092025.pdf20 Jan 2026
Withdrawal Update Form 3File: GUDC 30062025 - Signed-scan.pdf20 Jan 2026
Withdrawal Update Form 3File: GUDC 30092025 - Signed-scan.pdf20 Jan 2026
Form 2A (FY 2017-2018)File: MM Form 2A-draft Form New Format 2018.pdf20 Jan 2026
Form 2A (FY 2018-2019)File: MM Form 2A-draft Form New Format 2019.pdf20 Jan 2026
Form 2A (FY 2019-2020)File: MM Form 2A-draft Form New Format 2020.pdf20 Jan 2026
Form 2A (FY 2020-2021)File: MM Form 2A-draft Form New Format 2021.pdf20 Jan 2026
Form 2A (FY 2021-2022)File: MM Form 2A-draft Form New Format 2022.pdf20 Jan 2026
Form 2A (FY 2022-2023)File: MM Form 2A-draft Form New Format 2023.pdf20 Jan 2026
Form 2A (FY 2023-2024)File: MM Form 2A-draft Form New Format 2024.pdf20 Jan 2026
Form 2A (FY 2024-2025)File: MM Form 2A-draft Form New Format 2025.pdf20 Jan 2026
Form 5 (FY 2018-2019)File: Mass Metropolis Form 5- MAR 19.pdf20 Jan 2026
Form 5 (FY 2019-2020)File: Mass Metropolis Form 5- MAR 20.pdf20 Jan 2026
Form 5 (FY 2020-2021)File: Mass Metropolis Form 5- MAR 21.pdf20 Jan 2026
Form 5 (FY 2021-2022)File: Mass Metropolis Form 5- MAR 22.pdf20 Jan 2026
Form 5 (FY 2022-2023)File: Mass Metroplois Form 5- MAR 23.pdf20 Jan 2026
Form 5 (FY 2023-2024)File: Mass Metropolis Form 5- MAR 24.pdf20 Jan 2026
Form 1File: RERA Architect Certificate 31122017 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineers Certificate 31122017 GUDC_compressed.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 31122017.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31122017_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31122017 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineers Certificate 31122017 GUDC_compressed.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 31122017.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31122017_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30062018 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30062018 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30062018.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30062018_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30092018 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30092018 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30092018.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30092018_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31122018 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31122018 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 31122018.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31122018_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31032019 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31032019 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis Form 3 FY 1819 Signed.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31032019_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30062019 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30062019 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30062019.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30062019_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30092019 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30092019 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30092019.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30092019_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31122019 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31122019 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 31122019.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31122019_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31032020 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31032020 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis Form 3 FY 1920 Signed.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31032020_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30062020 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30062020 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30062020.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30062020_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 30092020 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 30092020 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 30092020.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 30092020_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31122020 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31122020 GUDC.pdf19 Jan 2026
Form 3File: Mass Metropolis - Form 3 - 31122020.pdf19 Jan 2026
Disclosure of Sold and Booked InventoryFile: Mass Metropolis sold inventory disclosure 31122020_compressed.pdf19 Jan 2026
Form 1File: RERA Architect Certificate 31032021 GUDC_compressed.pdf19 Jan 2026
Form 2File: RERA Engineer Certificate 31032021 GUDC.pdf19 Jan 2026

How this compares with Mumbai Suburban

62%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 21 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MASS METROPOLIS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHEMBUR6,700+ in Mumbai Suburban

2 kmMASS METROPOLISCompleted 157Lapsed / revoked 134Other 170Dot size: filed unitsN

Filed coordinates, straight-line distance. 461 registered projects within 2 km.

Builder: GRACE URBAN DEVELOPMENT CORPORATION

GRACE URBAN DEVELOPMENT CORPORATION has 1 registration on MahaRERA, including MASS METROPOLIS. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MASS METROPOLIS is delayed beyond 30 Sep 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MASS METROPOLIS?

The registered promoter entity is GRACE URBAN DEVELOPMENT CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MASS METROPOLIS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MASS METROPOLIS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MASS METROPOLIS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MASS METROPOLIS?

The professionals named in the filing: Architect: VIEW DIMENSION; Engineer: MOHSIN SHAIKH; Chartered Accountant: Anita Choudhari & Co.; Chartered Accountant: Anand A. Yadav & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MASS METROPOLIS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MASS METROPOLIS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MASS METROPOLIS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.