Home / Browse projects / Mumbai City, Maharashtra / Chistiya Palace

Registration lapsed Litigation declared Residential / Group Housing project

Chistiya Palace

By Rensar Infra Pvt.Ltd

RG-MH-65202 · RERA P51900005473 · Last updated on MahaRERA portal: 30 Sep 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 1 case
  • 3 complaints at MahaRERA
  • Completion date moved by 47 months
  • 3 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
6 of 11Construction stages donefurthest along: Internal walls, 96%
2 of 16Units unsoldnot recorded sold or booked
3Complaints at MahaRERAon this registration
Jump to the 235 documents Report an error

Chistiya Palace is a Residential / Group Housing project by Rensar Infra Pvt.Ltd in Mumbai City, Maharashtra, registered with MahaRERA as P51900005473 on 11 Aug 2017. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 47 months from the original filing. 14 of the 16 units on this registration are recorded sold or booked, and 6 of 11 construction stages are filed complete. 3 complaints are on record with the regulator.

At a glance

Project

  • NameChistiya Palace
  • TypeResidential / Group Housing
  • Location
    • 4
    • MOTLIBAI STREET
    • AGRIPADA WEST
    • Ward E
    • Mumbai City
    • 400011
  • Pincode400011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900005473
  • ReraGenie IDRG-MH-65202

Builder

  • NameRensar Infra Pvt.Ltd
  • Entity typeCompany
  • Managing DirectorsNadeem Rehmatullah Gubitra, Shafee Shabbir Khan

Key dates

4 months past promisethis monthRegisteredAug 2017First promiseJul 2022Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on11 Aug 2017
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Jul 2022)
  • Buildings1 building record
  • Documents filed235 files

Current status

88%14 of 16 units booked
73.8%Work done, per cost certificate

Figures as on 30 Sep 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Chistiya PalaceNA282216016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 11 construction stages are filed complete. The stage furthest along is Internal walls, at 96%.

Chistiya Palace: 98% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises96%
Sanitary Fittings within the flats / premises96%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks96%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 30 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyNoNot applicable
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes100%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes95%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area804 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on3 Sep 2025
LandownerVillageDistrict
Hicons Developers Pvt. Ltd.AndheriMumbai Suburban
CHISTIYA MANZIL CO-OP HSG SOCIETY LIMITEDGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMunicipal Corporation of Greater Mumbai
Permissible FSI4431.85
Proposed, not sanctioned4,432 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchHILL ROAD, BANDRA WEST
Estimated costRs 18.85 cr
Cost incurredRs 13.91 cr
Work done73.78%
BuildingWingEstimatedIncurred
Chistiya PalaceNARs 18.40 crRs 13.91 cr
-NARs 45.00 lakh-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVIVEK BHARTU CONSULTANT PVT LTD
EngineerFurkhan Pettiwala
Chartered AccountantTodi Tulsyan co
Chartered AccountantMohammed Arif Shaikh
PartnerRole in project
Rensar Infra Pvt.Ltd-

Extensions applied for3

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900012309Jul 2022 → Jul 2023

Reason as filed by the promoterBY VIRTUE OF DEVELOPMENT CONTROL AND PROMOTION REGULATION, 2034, THE PROMOTER IS NOW, FURTHER ENTITLED TO ADDITIONAL FSI FOR WHICH THE PROMOTER HAS REVISED THE PLANS AND APPLIED TO THE COMPETENT AUTHORITY FOR APPROVAL.

EXT51900018553Jul 2022 → Jun 2025

Reason as filed by the promoterWe hereby submit Justification and Reasons for Extension of the project u/s 7(3) to fulfil directions given by the Hon’ble Bombay High Court as explained hereunder:- 1. That the project is a redevelopment project of Chistiya Manzil CHS Ltd and the promoter (Rensar Infra P. Ltd) is a developer promoter, M/s Hicons Developers P Ltd is co-promoter in the project and Chistiya Manzil CHS Ltd is the land owner promoter (hereinafter referred as the Society) 2(zk) of the Real Estate (Regulation and Development) Act, 2016. The project was registered in July 2017 as an ongoing project with project Regis

EA06092502523Jul 2022 → Jun 2026

Reason as filed by the promoterWe are clear and committed that our project will get completed by 30.06.2026. We have got consent of more than 51% allottees of the project which is in compliance of the requirement of MahaRERA Circular No.40 dated 27.12.2022. Granting extension to the project will be in the interest of all the stake holders including allottees of the project. We are following up for OC of the project but it is taking time. Old society members were given fit out possession in 2022 under direction of Bombay HC and simultaneously all allottees also taken possession in 2022. Project is fully completed except few

Litigation declared1

CaseCourtStatus
AT06/00500/25/2025Maharera appellate tribunal mumbaiOngoing

Complaints filed with MahaRERA3

Case no.ComplainantRespondentFiled
CC006000000530718Rais Kasam ShaikhRensar Infra Pvt.Ltd08/06/2024
CC12503131Imtiyaz ZakariaRensar Infra Pvt.Ltd05/09/2025
CC12601732bashiroddin ashaboddin inamdarRensar Infra Pvt.Ltd26/03/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 25 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Nov 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed235

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 235 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2024-2025)File: Form 5 as on FY 24-25.pdf30 Sep 2025
Withdrawal Update Form 1File: Form 1 June 2025.pdf5 Sep 2025
Withdrawal Update Form 2File: Form 2 June 2025.pdf5 Sep 2025
Withdrawal Update Form 3File: Form 3 June 2025.pdf5 Sep 2025
Withdrawal Update Form 1File: Form 1 June 2025.pdf4 Sep 2025
Withdrawal Update Form 2File: Form 2 June 2025.pdf4 Sep 2025
Withdrawal Update Form 3File: Form 3 June 2025.pdf4 Sep 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31122024.pdf23 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 31032025.pdf23 May 2025
Certificates of CA (Form 3)File: Form 3 Rensar Infra PL 311224.pdf22 May 2025
Certificates of CA (Form 3)File: Form 3 Rensar Infra PL 310325.pdf22 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 as on 31122024.pdf22 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 as on 31032025.pdf22 May 2025
Disclosure of sold/ booked inventoryFile: 33-Disclosure of Sold-Booked Inventory as on 31122024.pdf22 May 2025
Disclosure of sold/ booked inventoryFile: 34-Disclosure of Sold-Booked Inventory as on 31032025.pdf22 May 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 as on 30_6_23.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-FORM 2 as on 30_09_2023.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-FORM 2 as on 31_12_2023.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RERA-FORM 2 as on 31_03_2024.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: form 2 as on 30_06_2024.pdf3 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 33 Certificates of Engineer (Form 2)(Mandatory for only ongoing project) (1).pdf3 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 3 Project Information (2).pdf3 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: 5 Project Information.pdf3 Apr 2025
Layout approvalFile: Amended and Approved_dated_ 4-10-2022_highlighted.pdf25 Mar 2025
Copy of Layout Approval (in case of layout)File: Amended and Approved_dated_ 4-10-2022_highlighted.pdf25 Mar 2025
Declaration in FORM BFile: FORM B_30_6_2025.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 AS ON 30-09-2024.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 AS ON 30-06-2024.pdf4 Dec 2024
Declaration in FORM BFile: FORM B_30_6_2025.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 AS ON 30-09-2024.pdf4 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 AS ON 30-06-2024.pdf4 Dec 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory as on 30092024.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_22-23 - rectified SIGN 22-11-2024.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-2023_with stamp.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_23-24 (1) SIGN 22-11-24.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - 2023-2024_with stamp.pdf26 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory as on 30092024.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5_22-23 - rectified SIGN 22-11-2024.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - 2022-2023_with stamp.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5_23-24 (1) SIGN 22-11-24.pdf26 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - 2023-2024_with stamp.pdf26 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 05-FORM 1-Architect Certificate 30-09-2024.pdf9 Nov 2024
Certificates of CA (Form 3)File: Form 3 Rensar Infra PL 30092024.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15-FORM 2 Certificate (05-11-2024) (Jul 2024 To Sep 2024).pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 87-Disclosure of Sold Unsold Inventory dated 31-03-2023.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 86-Disclosure of Sold Unsold Inventory dated 31-12-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 85-Disclosure of Sold Unsold Inventory dated 30-09-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 84-Disclosure of Sold Unsold Inventory dated 31-03-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 83-Disclosure of Sold Unsold Inventory dated 31-12-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 82-Disclosure of Sold Unsold Inventory dated 30-09-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 81-Disclosure of Sold Unsold Inventory dated 30-06-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dated 30-09-2023.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory as on 30092024.pdf9 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-FORM 2A-Site Supervisor Certificate as on 31-03-2022.pdf9 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 05-FORM 1-Architect Certificate 30-09-2024.pdf9 Nov 2024
Certificates of CA (Form 3)File: Form 3 Rensar Infra PL 30092024.pdf9 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 15-FORM 2 Certificate (05-11-2024) (Jul 2024 To Sep 2024).pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 87-Disclosure of Sold Unsold Inventory dated 31-03-2023.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 86-Disclosure of Sold Unsold Inventory dated 31-12-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 85-Disclosure of Sold Unsold Inventory dated 30-09-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 84-Disclosure of Sold Unsold Inventory dated 31-03-2022.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 83-Disclosure of Sold Unsold Inventory dated 31-12-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 82-Disclosure of Sold Unsold Inventory dated 30-09-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: 81-Disclosure of Sold Unsold Inventory dated 30-06-2021.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory dated 30-09-2023.pdf9 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory as on 30092024.pdf9 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 21-FORM 2A-Site Supervisor Certificate as on 31-03-2022.pdf9 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01-FORM 1-Architect Certificate 30-09-2023.pdf8 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 04-FORM 1-Architect Certificate 30-06-2024.pdf8 Nov 2024
Certificates of CA (Form 3)File: Form 3 as on 30062024.pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14-FORM 2 Certificate (12-09-2024) (Apr 2024 To June 2024).pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11-FORM 2 Certificate (12-09-2024) (July 2023 To Sept 2023).pdf8 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory 30062024.pdf8 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 21-FORM 2A-RERA Engineer Certificate as on 31-03-2024.pdf8 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 01-FORM 1-Architect Certificate 30-09-2023.pdf8 Nov 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 04-FORM 1-Architect Certificate 30-06-2024.pdf8 Nov 2024
Certificates of CA (Form 3)File: Form 3 as on 30062024.pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 14-FORM 2 Certificate (12-09-2024) (Apr 2024 To June 2024).pdf8 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 11-FORM 2 Certificate (12-09-2024) (July 2023 To Sept 2023).pdf8 Nov 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Unsold Inventory 30062024.pdf8 Nov 2024

How this compares with Mumbai City

88%of this project is bookeddistrict median 17%
33%of Mumbai City projects moved their completion datethis one moved by 47 months
25%of Mumbai City registrations have lapsed or been cancelledthis one is among them

Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Chistiya Palace on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near AGRIPADA WEST780+ in Mumbai City

2 kmChistiya PalaceCompleted 20Lapsed / revoked 33Other 80Dot size: filed unitsN

Filed coordinates, straight-line distance. 133 registered projects within 2 km.

Builder: Rensar Infra Pvt.Ltd

Rensar Infra Pvt.Ltd has 1 registration on MahaRERA, including Chistiya Palace. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai City district page.

Frequently asked questions

What does it mean that Chistiya Palace shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Chistiya Palace is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Chistiya Palace?

The registered promoter entity is Rensar Infra Pvt.Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Chistiya Palace?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Chistiya Palace?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Chistiya Palace?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Chistiya Palace?

The professionals named in the filing: Architect: VIVEK BHARTU CONSULTANT PVT LTD; Engineer: Furkhan Pettiwala; Chartered Accountant: Todi Tulsyan co; Chartered Accountant: Mohammed Arif Shaikh. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Chistiya Palace?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Chistiya Palace. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Chistiya Palace to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.