Central Tower - Tower 2
RG-MH-47398 · RERA P51900016482 · Last updated on MahaRERA portal: 30 Jun 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 4 months past the filed date
- Litigation declared, 30 cases
- 10 complaints at MahaRERA
- Rs 300.00 crore secured on the land, in favour of TATA CAPITAL HOUSING FINANCE LIMITED
Clear
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai City registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Central Tower - Tower 2 is a Residential / Group Housing project by Glider Buildcon Realtors in Mumbai City, Maharashtra, registered with MahaRERA as P51900016482 on 18 May 2018. Possession was promised by 30 Jun 2026 and is now 4 months past that date. 148 of the 183 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete. 10 complaints are on record with the regulator.
At a glance
Project
- NameCentral Tower - Tower 2
- TypeResidential / Group Housing
- Location
- GB Satkal marg and Kamlakant singh marg Dhobighat Saatrasta Mumbai
- Saatraasta
- Mumbai City
- 400011
- Pincode400011
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51900016482
- ReraGenie IDRG-MH-47398
Builder
- NameGlider Buildcon Realtors
- Entity typeCompany
- CINU70200MH2015PTC265844
- GSTIN27AAGCG0288B1ZU
- DirectorPankaj S Mundada
- Other registrations2 more →
- No longer live2 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on18 May 2018
- Promised completion30 Jun 2026
- Revised completionNone
- Buildings1 building record
- Documents filed239 files
Current status
Figures as on 30 Jun 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Central Tower - Tower 2 | NA | 62 | 50 | 183 | 0 | 183 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.
Central Tower - Tower 2: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 30 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | Yes | 100% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed518
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership4
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| Gliders Buildon Realtors Private Limited | Mumbai City | Mumbai City |
| Omkar Realtors Projects Private Limited | Kurla | Mumbai Suburban |
| Padmalaya Realty LLP | Kurla | Mumbai Suburban |
| Resonant Realtors Projects Pvt Ltd | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| Central Tower - Tower 2 | NA | Rs 562.94 cr | Rs 413.35 cr |
| - | NA | Rs 73.67 cr | Rs 40.92 cr |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Anand Vishnu Dhokay |
| Engineer | WTP Cost Advisory Services India Pvt. Ltd |
| Engineer | Kishor Parmar |
| Chartered Accountant | D B Ketkar & Co |
| Chartered Accountant | SRBC & CO LLP |
| Partner | Role in project |
|---|---|
| Glider Buildcon Realtors Private Ltd | - |
Litigation declared30
| Case | Court | Status |
|---|---|---|
| 2524/2016 | Bombay City Civil Court | Notice of Motion for Hearing |
| 199/2018 | Bombay City Civil Court | Notice of Motion Reply Rejoinder |
| 1234/2015 | Before the Consumer Redressal Commission New Delhi | Closed |
| 1423/2015 | Bombay City Civil Court | Pending for Hearing |
| 2147/2015 | Bombay City Civil Court | For writ of summons |
| 1207/2016 | Bombay City Civil Court | Closed |
| 1033141/2016 | Bombay City Civil Court | For Compliance |
| 105749/2007 | Bombay City Civil Court | For Order on Chamber Summons |
| 7887/2018 | High Court of Judicature at Bombay | For Order |
| 368/2018 | Before Additional Collector Mumbai City | For Hearing |
| 1817/2018 | High Court of Judicature at Bombay | For Admission |
| 1775/2016 | Bombay City Civil Court | Closed |
| 35886/2018 | High Court of Judicature at Bombay | For Admission |
| 3610/2019 | High Court of Judicature at Bombay | Closed |
| 35886/2018 | High Court of Judicature at Bombay | Duplicate Entry to be ignored |
| 30608/2018 | High Court of Judicature at Bombay | Closed |
| 30699/2018 | High Court of Judicature at Bombay | Closed |
| 30685/2018 | High Court of Judicature at Bombay | Closed |
| 54/2018 | Bombay City Civil Court | For Hearing |
| 2255/2016 | Bombay City Civil Court | For Hearing |
| 855/2016 | Bombay City Civil Court | For Hearing |
| 645/2017 | Bombay City Civil Court | Closed |
| 147/2016 | Bombay City Civil Court | For Hearing |
| 2582/2015 | Bombay City Civil Court | Closed |
| 1434/2017 | Bombay City Civil Court | For Hearing |
| 2347/2019 | High Court of Judicature at Bombay | Duplicate Entry to be ignored |
| 9681/2019 | Bombay City Civil Court | Pending for Hearing |
| 2637/2019 | Bombay City Civil Court | Pending for Hearing |
| 1247/2019 | High Court of Judicature at Bombay | PreAdmission |
| 260/2020 | Bombay City Civil Court | Summons to answer Plaint |
Complaints filed with MahaRERA10
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000196359 | Gurpreet Singh Malhi | Glider Buildcon Realtors Private Limited | 15/03/2021 |
| CC006000000196476 | Muffazzal Hafiji | Glider Buildcon Realtors Pvt Ltd | 24/03/2021 |
| CC006000000292721 | ANANTA LANDWISE PVT LTD | Glider Buildcon Realtors | 20/09/2022 |
| CC006000000333772 | Krishna Prasad | Glider Buildcon Realtors Private Limited | 27/12/2022 |
| CC006000000354439 | Clifford Francis Lima | Glider Buildcon Realtors Private Limited | 21/02/2023 |
| CC006000000397646 | Ruby Sharma | Glider Buildcon Realtors Private Limited | 28/09/2023 |
| CC006000000429560 | Ashok kumar Singh | Resonant Realtors Projects Private Limited | 07/03/2024 |
| CC12400202 | Glider Buildcon Realtors | Clifford Francis Lima | 23/09/2024 |
| CC12504696 | Rashida Burhanuddin Dohadwala | Glider Buildcon Realtors | 30/12/2025 |
| CC12602338 | Splendor Global Infraspace LLP | Glider Buildcon Realtors | 21/04/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 9 Dec 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 9 Aug 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 23 May 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Aug 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed239
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 239 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2025-2026)File: 00 Form 2A Mahalaxmi CT.pdf | 30 Jun 2026 |
| Withdrawal Update Form 1File: Form 1, CT.pdf | 16 Oct 2025 |
| Withdrawal Update Form 2File: Form 2, CT.pdf | 16 Oct 2025 |
| Withdrawal Update Form 3File: Form 3, CT.pdf | 16 Oct 2025 |
| Form 2A (FY 2024-2025)File: Central tower.pdf | 30 Sep 2025 |
| Form 5 (FY 2024-2025)File: Mahalaxmi CT.pdf | 30 Sep 2025 |
| Form 1File: Form 1, CT_17042025171016.PDF | 17 Jul 2025 |
| Form 2File: Engineers Certificate Central Tower-Works upto 31st March 2025.pdf | 17 Jul 2025 |
| Form 3File: Form 3, CT Updated 2.pdf | 17 Jul 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold CT_17042025172824 .pdf | 17 Jul 2025 |
| Certificates of CA (Form 3)File: Form 3, CT Updated.pdf | 21 Apr 2025 |
| Certificates of CA (Form 3)File: Form 3_CT.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2_CT.pdf | 19 Apr 2025 |
| Details of encumbrancesFile: Encumbrances CT_17042025171531.PDF | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1, CT_17042025171016.PDF | 17 Apr 2025 |
| OtherFile: FSI Concession CT_17042025171948.PDF | 17 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold CT_17042025172824 .pdf | 17 Apr 2025 |
| CERSAI detailsFile: 400089706666_Glider_2850 mn.pdf | 17 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Piramal Mahalaxmi T2 CT Form 1, December'2024.pdf | 20 Jan 2025 |
| Certificates of CA (Form 3)File: Mahalaxmi Central Tower.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Piramal Mahalaxmi CT Form 2, December'2024.pdf | 20 Jan 2025 |
| OtherFile: CT.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Piramal Mahalaxmi CT Sold Unsold Inventory.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Piramal Mahalaxmi_CT Form 1, Sept'2024.pdf | 18 Oct 2024 |
| Certificates of CA (Form 3)File: Piramal Mahalaxmi_CT Form 3, Sept'2024.pdf | 18 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Piramal Mahalaxmi_CT Form 2, Sept'2024.pdf | 18 Oct 2024 |
| OtherFile: 04 Piramal Mahalaxmi CT, FSI Declaration.pdf | 17 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 05 Piramal Mahalaxmi CT, Sold Unsold Inventory.pdf | 17 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 CT 2023-2024.pdf | 7 Oct 2024 |
| Layout approvalFile: (central) Sheet 4-4.pdf | 9 Aug 2024 |
| Layout approvalFile: (central) Sheet 1-4_compressed_compressed.pdf | 9 Aug 2024 |
| Layout approvalFile: (central) Sheet 2-4.pdf | 9 Aug 2024 |
| Layout approvalFile: (central) Sheet 3-4.pdf | 9 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: (central) Sheet 1-4_compressed_compressed.pdf | 9 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: (central) Sheet 2-4.pdf | 9 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: (central) Sheet 3-4.pdf | 9 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: (central) Sheet 4-4.pdf | 9 Aug 2024 |
| Layout approvalFile: Performa A.pdf | 7 Aug 2024 |
| Copy of Layout Approval (in case of layout)File: Performa A.pdf | 7 Aug 2024 |
| Disclosure of sold/ booked inventoryFile: Central Tower.pdf | 7 Aug 2024 |
| Certificates of CA (Form 3)File: Mahalxmi_CT_Form3_June 24_Updated.pdf | 7 Aug 2024 |
| Details of encumbrancesFile: Central Tower.pdf | 5 Aug 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC_8 MAY 2024_Mahalaxumi_compressed.pdf | 5 Aug 2024 |
| Certificates of CA (Form 3)File: M_CT_merged.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Mahalaxmi_CT_Form 2_June 24.pdf | 19 Jul 2024 |
| Details of encumbrancesFile: Encumbrance Certificate - Piramal Mahalaxmi.pdf | 18 Jul 2024 |
| CERSAI detailsFile: CERSAI_Piramal Mahalaxmi.pdf | 18 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Mahalaxmi CT.pdf | 18 Jul 2024 |
| OtherFile: Mahalaxmi_Central_FSI_June 24.pdf | 16 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Mahalaxmi Central.pdf | 15 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Central Tower_SoldUnsold.pdf | 4 Jul 2024 |
| OtherFile: Mahalaxmi Central_FsiC_June 24 .pdf | 4 Jul 2024 |
| Building plan approvalFile: CT 1.pdf | 23 May 2024 |
| Building plan approvalFile: CT 2.pdf | 23 May 2024 |
| Building plan approvalFile: CT 3.pdf | 23 May 2024 |
| Building plan approvalFile: CT 4.pdf | 23 May 2024 |
| Building plan approvalFile: CT 5.pdf | 23 May 2024 |
| Building plan approvalFile: CT 6.pdf | 23 May 2024 |
| Building plan approvalFile: CT 7.pdf | 23 May 2024 |
| Building plan approvalFile: CT 8.pdf | 23 May 2024 |
| Building plan approvalFile: CT 9.pdf | 23 May 2024 |
| Building plan approvalFile: CT 10.pdf | 23 May 2024 |
| Building plan approvalFile: CT 11.pdf | 23 May 2024 |
| Building plan approvalFile: CT 12.pdf | 23 May 2024 |
| Building plan approvalFile: CT 13.pdf | 23 May 2024 |
| Building plan approvalFile: CT 14.pdf | 23 May 2024 |
| Building plan approvalFile: CT 15.pdf | 23 May 2024 |
| Building plan approvalFile: CT 16.pdf | 23 May 2024 |
| Building plan approvalFile: CT 17.pdf | 23 May 2024 |
| Building plan approvalFile: CT 18.pdf | 23 May 2024 |
| Building plan approvalFile: CT 19.pdf | 23 May 2024 |
| Building plan approvalFile: CT 20.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 1.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 2.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 3.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 4.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 5.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 6.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 7.pdf | 23 May 2024 |
| Building Plan Approval (IOD)File: CT 8.pdf | 23 May 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai City
Computed across the 780+ Mumbai City projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 239 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Central Tower - Tower 2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Saatraasta780+ in Mumbai City
Filed coordinates, straight-line distance. 117 registered projects within 2 km.
NATHANI HEIGHTS SALE
Nathani Parekh Constructions Private Limit
North Tower - Tower 3
Glider Buildcon Realtors
MONTESOUTH ZERMATT-1
SWAYAM REALTORS & TRADERS LLP
South Tower
Glider Buildcon Realtors
MINERVA
Lokhandwala Kataria Construction Private L
Lodha Bellevue
Lodha Developers Limited
See every Mumbai City project, with the district possession charts
Builder: Glider Buildcon Realtors
Glider Buildcon Realtors has 3 registrations on MahaRERA, including South Tower and Central Tower - Tower 2. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Mumbai City district page.
Frequently asked questions
What does it mean that Central Tower - Tower 2 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Central Tower - Tower 2 is delayed beyond 30 Jun 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Central Tower - Tower 2?
The registered promoter entity is Glider Buildcon Realtors, a company as per the filing. Its CIN U70200MH2015PTC265844 and GSTIN 27AAGCG0288B1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Central Tower - Tower 2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Central Tower - Tower 2?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Central Tower - Tower 2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Central Tower - Tower 2?
The professionals named in the filing: Architect: Anand Vishnu Dhokay; Engineer: WTP Cost Advisory Services India Pvt. Ltd; Engineer: Kishor Parmar; Chartered Accountant: D B Ketkar & Co; Chartered Accountant: SRBC & CO LLP. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Central Tower - Tower 2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback