ReraGenieLog inGet a buyer report

Home / Developers / Puranik Builders Limited

Puranik Builders Limited: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

Puranik Builders Limited has 20 registrations in this build, including Aldea Annexo -C1 and Rumahbali Phase 2. Its filings disclose 6 earlier MahaRERA projects: 0 of 6 past projects completed on time. Litigation is declared on 3 of its registrations.

20Registrations in this build
6Past projects disclosed
+4 monthsMedian delivery slip
3Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
Aldea Annexo -C1Pune, Maharashtra--Completed
Rumahbali Phase 2Thane, Maharashtra--Completed
Puranik City Reserva Phase 1Thane, Maharashtra87989%Registered
Puranik Home Town - EThane, Maharashtra--Completed
Sayama Phase 3Pune, Maharashtra--Completed
Aldea Annexo - C2Pune, Maharashtra--Registered
Sayama Phase 2Pune, Maharashtra--Registered
Sayama Phase 4Pune, Maharashtra--Registered
Puraniks CapitolThane, Maharashtra--Registered
Rumah Bali Phase 3Thane, Maharashtra61574%Registered
PURANIK CITY SECTOR 1Raigarh, Maharashtra22876%Registered
PURANIK CITY SECTOR 2Raigarh, Maharashtra46359%Registered
PURANIK CITY SECTOR 3Raigarh, Maharashtra24326%Registered
PURANIK CITY SECTOR 4ARaigarh, Maharashtra--Registered
PURANIK CITY SECTOR 5Raigarh, Maharashtra--De-registered
PURANIK CITY SECTOR 6Raigarh, Maharashtra--De-registered
Aldea Annexo - DPune, Maharashtra--Completed
Puraniks Unicorn Phase 1Thane, Maharashtra25282%Registered
Rumah Bali Phase 4Thane, Maharashtra24076%Registered
Puraniks Unicorn Phase 2Thane, Maharashtra26664%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
Puranik City Part B
31 Dec 201121 Apr 2012+4 months
Puranik City Part A
31 Dec 201221 Feb 2013+2 months
Hometown Part A
30 Jun 20136 Nov 2013+4 months
Hometown Part B
31 Aug 201420 Jan 2015+5 months
Aldea Annexo
31 Dec 201629 Apr 2017+4 months
Hometown Part C
31 Dec 201626 Apr 2017+4 months

Frequently asked questions

How do I verify Puranik Builders Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Puranik Builders Limited?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Puranik Builders Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.