Red flags
- 8 complaints at MahaRERA
Clear
- No litigation declared
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Raigarh registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PURANIK CITY SECTOR 4A is a Others project by Puranik Builders Limited in Raigarh, Maharashtra, registered with MahaRERA as P52000017994 on 3 Oct 2018. Possession is promised by 1 May 2031. 8 complaints are on record with the regulator.
At a glance
Project
- NamePURANIK CITY SECTOR 4A
- TypeOthers
- Location
- Village Street
- Pimploli Karjat
- pimploli bk
- Karjat
- Raigarh
- 410201
- Pincode410201
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52000017994
- ReraGenie IDRG-MH-65593
Builder
- NamePuranik Builders Limited
- Entity typeCompany
- CINU99999MH1990PLC056451
- GSTIN27AABCP0109R1Z9
- Managing DirectorShailesh Gopal Puranik
- DirectorsYogesh Govind Puranik, Shrikant Govind Puranik, Nilesh Ravindra Puranik
- Other registrations19 more →
- Completed5 of 20
- No longer live2 lapsed, de-registered or revoked
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on3 Oct 2018
- Promised completion1 May 2031
- Revised completionNone
- Buildings5 building records
- Documents filed89 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| JB2 | NA | 8 | 0 | 0 | 0 | 0 |
| PB 2 | NA | 8 | 0 | 0 | 0 | 0 |
| HB 3 | NA | 8 | 0 | 0 | 0 | 0 |
| PBC | NA | 8 | 0 | 0 | 0 | 0 |
| GB | NA | 8 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building5
As on 20 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Basement (if any), at 70%.
JB227%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PB 20%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
HB 327%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
PBC22%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 70% |
| Podiums (if any) | 0% |
| Plinth | 70% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
GB27%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities16
As on 20 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
| Club House | Yes | 0% |
Land and ownership
MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners7
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vastushilpa Associates |
| Engineer | M/s. Epicons Consultants Pvt Ltd |
| Engineer | Sagar Abnave |
| Engineer | Kedar Yernalkar |
| Chartered Accountant | HDO & Associates |
| Chartered Accountant | VMD and Company |
| Chartered Accountant | VMd & Co |
| Partner | Role in project |
|---|---|
| Puranik Builders Limited | - |
Litigation declared1
| Case | Court | Status |
|---|---|---|
| CC00600000251370/2022 | Maharashtra Real Estate Regulatory Authority | For Hearing |
Complaints filed with MahaRERA8
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000251370 | Pratibha Avinash More | Puranik Builders Limited | 09/06/2022 |
| CC006000000429536 | Nilkantha Gawade | Puranik Builders Limited | 06/03/2024 |
| CC12500456 | Parinita Ashok Kawale | Puranik Builders Limited | 11/02/2025 |
| CC12501713 | SWAPNIL DINESH PATHAK | Puranik Builders Limited | 26/05/2025 |
| CC12503162 | Rupesh Babu Dhuri | Puranik Builders Limited | 08/09/2025 |
| CC12602850 | Neetu Omprakash Singh | Puranik Builders Limited | 15/05/2026 |
| CC12603668 | Chaitanya Potdar | Puranik Builders Limited | 13/06/2026 |
| CC12603755 | Ravindra Sahadeo Kamble | Puranik Builders Limited | 18/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Sep 2018 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 17 Sep 2018 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 17 Sep 2018 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 17 Sep 2018Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 May 2031
Documents filed89
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 89 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 1File: Form 1.pdf | 20 Apr 2026 |
| Form 2File: Form 2.pdf | 20 Apr 2026 |
| Form 3File: From 3.pdf | 20 Apr 2026 |
| Disclosure of Sold and Booked InventoryFile: Sales data.pdf | 20 Apr 2026 |
| Form 1File: 31122025 Architects cert Sector 04A.pdf | 21 Jan 2026 |
| Form 2File: Form 2 Engineers Certificate Neral Sec 4 31122025.pdf | 21 Jan 2026 |
| Form 3File: CA Certificates - Neral Project -Sector IV-A Final.pdf | 21 Jan 2026 |
| Disclosure of Sold and Booked InventoryFile: Neral Sector 4A 0001.pdf | 21 Jan 2026 |
| Form 1File: 30062025_Architect's cert_Sector_04A_Bldg Type_PBC, HB3, PB2, GB, JB2.pdf | 16 Nov 2025 |
| Form 2File: Form 2 Engineers Certificate Neral Sec 4.pdf | 16 Nov 2025 |
| Form 3File: CA Certificates - Neral_Project-Sector_IV-A.pdf | 16 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of Inventory - Puranik City Neral - 4A-.pdf | 16 Nov 2025 |
| Form 1File: 30092025 Architect's cert_Sector_04A_Bldg Type_PBC, HB3, PB2, GB, JB2.pdf | 16 Nov 2025 |
| Form 2File: Form 2 Engineers Certificate Neral Sec 4.pdf | 16 Nov 2025 |
| Form 3File: CA Certificates - Neral_Project_Sector_IV-A Final.pdf | 16 Nov 2025 |
| Disclosure of Sold and Booked InventoryFile: Neral Sctor 4A_0001.pdf | 16 Nov 2025 |
| Form 5 (FY 2024-2025)File: Rera Form 5 - Puranik City Sector 4A - sign.pdf | 29 Sep 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PC Neral Sector 4.pdf | 20 Apr 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Neral_Project sector 4.pdf | 20 Apr 2025 |
| Certificates of CA (Form 3)File: CA Certificates - Neral_Project_31122024_-Sector_IV-A_compressed.pdf | 23 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 30092024.pdf | 23 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 _311224.pdf | 23 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A- Puranik City Neral Sector 4A 23-24.pdf | 23 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PC Neral Sector 4.pdf | 21 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PC Neral Sector 4A.pdf | 20 Oct 2024 |
| Certificates of CA (Form 3)File: CA Certificates - Neral_Project 30092024 Sector_IV-A.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Puranik city Sector 4A - signed.pdf | 7 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 _300624.pdf | 5 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 30062024 Architects Certificate FORM-1 PC Neral Sector 4A.pdf | 20 Jul 2024 |
| Certificates of CA (Form 3)File: Puranik City sector 4A.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PC Neral Sector 4.pdf | 29 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4.pdf | 29 Apr 2024 |
| Certificates of CA (Form 3)File: Neral 4A_compressed.pdf | 29 Apr 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: PC Neral Sector 4A.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4.pdf | 20 Jan 2024 |
| Certificates of CA (Form 3)File: Neral 4A.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Phase-4a_Architect Certificate.pdf | 16 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 _30092023.pdf | 16 Nov 2023 |
| Certificates of CA (Form 3)File: Neral-4A 80_compressed.pdf | 16 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Rera Form 5 Puranik City Sector 4A - signed final.pdf | 30 Sep 2023 |
| Disclosure of sold/ booked inventoryFile: Puranik City Neral-Sector 4A-GB.PDF | 14 Aug 2023 |
| Disclosure of sold/ booked inventoryFile: Sector-4A GB.PDF | 14 Aug 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A- Puranik City Neral Sector 4A.pdf | 8 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: sector 4.pdf | 7 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 31032023.pdf | 7 Aug 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 30062023.pdf | 7 Aug 2023 |
| Certificates of CA (Form 3)File: HDO - PC SECTOR IV-A - 028.pdf | 7 Aug 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sector-4a_.pdf | 2 May 2023 |
| Certificates of CA (Form 3)File: Neral 4A_compressed.pdf | 2 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: sector 4a.pdf | 25 Mar 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4 31122022.pdf | 25 Mar 2023 |
| Disclosure of sold/ booked inventoryFile: Puranik City Neral-Neral Sector-4A-GB.pdf | 25 Mar 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Form 5 Neral IV.pdf | 7 Feb 2023 |
| Certificates of CA (Form 3)File: Puranik City Sec IV-A.PDF | 31 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SECTOR 4.pdf | 12 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4.pdf | 12 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates Neral Project 31032019 Sector IVA.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral IV A 30092019.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral IV A 30092019.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral Sector IVA 31122019.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral Project 3132020 Sector IV A.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral Project Sector IV June 20.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates Neral Project 30092020 Sector IVA.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: CA Certificates Puranik City Sector IV A 31122020.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral Sector IVA.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral IV A 30092021.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral IV 31122021.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: PURANIK CITY SECTOR IV A.PDF | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Sector IV 31032022 compressed.pdf | 11 Jan 2023 |
| Certificates of CA (Form 3)File: Neral IV 30092022.pdf | 11 Jan 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Neral 4A.pdf | 1 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SECTOR 4.pdf | 3 Aug 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: SECTOR 4.pdf | 3 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4.pdf | 3 Aug 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Engineers Certificate Neral Sec 4.pdf | 7 Jul 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Puranik City 4A.pdf | 30 Sep 2021 |
| Details of Restarting of Construction work post lockdownFile: Neral Sector 4A - REPORT.pdf | 14 Jul 2020 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: PURANIK CITY SECTOR 4A.pdf | 27 Jan 2020 |
| Details of encumbrancesFile: Encumbrance Certificate Sector 4.pdf | 5 Nov 2019 |
| Declaration in FORM BFile: PC SECTOR 4A.PDF | 26 Sep 2018 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Status | Promised | Delivered |
|---|---|---|---|---|---|
| Hometown Part C | Kasarvadavali Ghodbunder Road Thane west 400615 | 108 | Completed | Dec 2016 | Late, Apr 2017 |
| Aldea Annexo | Aldea Annexo Next to Hotel Vits Nr Balewadi Stadium Mhalunge Pune 411045 | 129 | Completed | Dec 2016 | Late, Apr 2017 |
| Hometown Part B | Kasarvadavali Ghodbunder Road Thane west 400615 | 159 | Completed | Aug 2014 | Late, Jan 2015 |
| Hometown Part A | Kasarvadavali Ghodbunder Road Thane west 400615 | 176 | Completed | Jun 2013 | Late, Nov 2013 |
| Puranik City Part A | Kasarvadavali Ghodbunder Road Thane west 400615 | 108 | Completed | Dec 2012 | Late, Feb 2013 |
| Puranik City Part B | Kasarvadavali Ghodbunder Road Thane west 400615 | 80 | Completed | Dec 2011 | Late, Apr 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Raigarh
Computed across the 5,900+ Raigarh projects on ReraGenie, from their own filings.
Free monthly report: Navi Mumbai and Raigad on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 19 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 89 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep PURANIK CITY SECTOR 4A on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Pimploli Karjat5,900+ in Raigarh
Filed coordinates, straight-line distance. 63 registered projects within 2 km.
Bellezza Woods
DOTOM BUILD SQUARE
Winds of Calm
Eiffel Lifespaces Pvt Ltd
PURANIK CITY SECTOR 2
Puranik Builders Limited
Foothills of Matheran P - 2
HOABL Impactum Land Private Limited
FLORENCE TOWN
BRIGHT DEVELOPERS
The Destination
DOVE BUILDMART PRIVATE LIMITED
See every Raigarh project, with the district possession charts
Builder: Puranik Builders Limited
Puranik Builders Limited has 20 registrations on MahaRERA, including Aldea Annexo -C1 and Rumahbali Phase 2. Its filings disclose 6 earlier MahaRERA projects: declares 0 of 6 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Raigarh district page.
Frequently asked questions
What are my rights if PURANIK CITY SECTOR 4A is delayed beyond 1 May 2031?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PURANIK CITY SECTOR 4A?
The registered promoter entity is Puranik Builders Limited, a company as per the filing. Its CIN U99999MH1990PLC056451 and GSTIN 27AABCP0109R1Z9 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PURANIK CITY SECTOR 4A?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PURANIK CITY SECTOR 4A?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PURANIK CITY SECTOR 4A?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PURANIK CITY SECTOR 4A?
The professionals named in the filing: Architect: Vastushilpa Associates; Engineer: M/s. Epicons Consultants Pvt Ltd; Engineer: Sagar Abnave; Engineer: Kedar Yernalkar; Chartered Accountant: HDO & Associates; Chartered Accountant: VMD and Company. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PURANIK CITY SECTOR 4A?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback