Venkatesh Hill Side, Plot No. 2, Building 1

By VENKATESH ASSOCIATES

RG-MH-66420 · RERA P52100045700 · Last updated on MahaRERA portal: 30 May 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 11 months past the filed date
  • Completion date moved by 18 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Nov 2025Possession promised11 months past this date
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 14%
1 of 1Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 66 documents Report an error

Venkatesh Hill Side, Plot No. 2, Building 1 is a Residential / Group Housing project by VENKATESH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100045700 on 6 Jun 2022. Possession was promised by 30 Nov 2025 and is now 11 months past that date. The completion date has moved by 18 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameVenkatesh Hill Side, Plot No. 2, Building 1
  • TypeResidential / Group Housing
  • Location
    • MAIN ROAD
    • DHAYARI
    • Haveli
    • Pune
    • 411041
  • Pincode411041
  • RERA no.P52100045700
  • ReraGenie IDRG-MH-66420

Builder

  • NameVENKATESH ASSOCIATES
  • Entity typePartnership
  • GSTIN27AADFV7559E1ZU
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersANIL GOPAL GANDHI, MILIND SHANTIKUMAR PANDIT, KALIDAS NIVRUTTI JAGADE
  • Other registrations13 more →
  • Completed7 of 14
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects12 →

Key dates

11 months past promisethis monthRegisteredJun 2022First promiseMay 2024Revised toNov 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on6 Jun 2022
  • Promised completion30 Nov 2025
  • Revised completionRevised to 30 Nov 2025 (originally 31 May 2024)
  • Buildings1 building record
  • Documents filed66 files

Current status

0%0 of 1 units booked

Figures as on 30 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Venkatesh Hill Side, Plot No 2, Building 1NA76101

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 14%.

Venkatesh Hill Side, Plot No 2, Building 1: 29% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure14%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Land and ownership6

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,201 sq m
Land owned byThe promoter, with other names on the file
Named landowners6
LandownerVillageDistrict
MRS.SUREKHA SUDHAKAR JADHAVARWadgaon BkPune
MR. MAHESH NARAYANDAS AMBAVANINavi Mumbai (M Corp.)Thane
MR. HARSH DEVANDAS LALWANINavi Mumbai (M Corp.)Thane
MR. SACHIN JAIKUMAR BAJAJAhmadnagar (M Corp.)Ahmednagar
MR. SUSHIL RAMLAL BAJAJAhmadnagar (M Corp.)Ahmednagar
MR. SURENDER RAMLAL BAJAJAhmadnagar (M Corp.)Ahmednagar

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI2578.7
Proposed, not sanctioned1,547 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTILAK ROAD, PUNE

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMANOHAR YERAWAR
EngineerStructus Consultantss Pvt. Ltd.
Chartered AccountantJori & Co
Chartered AccountantRajendra Shah & Co
PartnerRole in project
VENKATESH ASSOCIATES-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100019544May 2024 → Nov 2025

Reason as filed by the promoterThe RCC work in progress. In between the work slowed down due to slow booking and project funds were not arranged. Whereas, now funds have been arranged and clients are also ready for booking so to complete the project successfully we need the possession date extension. We also declare that currently we have not booked / sold any of the flat inventory.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 May 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 May 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 May 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 16 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed66

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: FORM 5 HILLSIDE BLDG 1.pdf30 May 2026
Form 1File: Q3 Form 1 Architect Letter Bldg 1.pdf6 May 2026
Form 2File: Q3 FORM 2 Engineer Certificate Bldg 1.pdf6 May 2026
Form 3File: Q3 Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold - Booked Inventory Bldg 1.pdf6 May 2026
Form 1File: Form 1 Architect Letter Bldg 1.pdf6 May 2026
Form 2File: FORM 2 Engineer Certificate Bldg 1.pdf6 May 2026
Form 3File: Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Booked Inventory Bldg 1.pdf6 May 2026
Form 1File: Form 1 Architect Letter Bldg 1.pdf6 May 2026
Form 2File: FORM 2 Engineer Certificate Bldg 1.pdf6 May 2026
Form 3File: Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf6 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Booked Inventory Bldg 1.pdf6 May 2026
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter( Hillside BLDG 1 ).pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accounted ( BLDG - 1 )_compressed.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accounted ( BLDG - 1 )_compressed.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificat ( HILLSIDE BLDG -1 ).pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GetUserDocumentFileContent.pdf24 Jan 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ( Annual Repaort ).pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate ( Bldg 1 ).pdf28 May 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate ( Bldg 1 Dhayari ).pdf28 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Account Certificate ( Bldg 1 )_compressed.pdf28 May 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 Annual Report Hillside Blgd 1 Plot No 2.pdf5 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Gandhi Sir ).pdf5 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Ghate Sir ).pdf5 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Pandit Sir ).pdf5 Apr 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter (Jagade Sir ).pdf5 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf7 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Lettere (Venkatesh Hillside Bldg 1 ).pdf20 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginee Certificate ( Venkatesh Hillside Bldg 1 ).pdf20 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Certificate ( Venkatesh Hillside Bldg 1 )_compressed.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside Bldg 1 - Form 1 - 23-24 Q2_compressed.pdf20 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside Bldg 1 - Form 2 - 23-24 Q2.pdf20 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Hillside Bldg 1 - Form 3 - 23-24 Q2_compressed.pdf20 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside Bldg 1 - Form 1 - 22-23 Q2_compressed.pdf17 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside Bldg 1 - Form 2 - 22-23 Q2_compressed.pdf17 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Hillside Bldg 1 - Form 3 - 22-23 Q2_compressed.pdf17 Jul 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Bldg 1.pdf10 May 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginee Certificate Bldg 1.pdf10 May 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Ac Certificate Bldg 1_compressed.pdf10 May 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Bldg - 1_compressed.pdf7 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Bldg - 1_compressed.pdf7 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Account Certificate Bldg - 1_compressed.pdf7 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (Venkatesh Hill side, Bldg - 1 ).pdf29 Nov 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineenr Certificate ( Venkatesh Hillside , Bldg -1,Plot No 2 )_compressed.pdf29 Nov 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Venkatesh Hill Side Bldg -1 , Plot No 2 ( C A)_compressed.pdf29 Nov 2022
Details of encumbrancesFile: Encumbrance Certificate Plot No.pdf17 May 2022
CERSAI detailsFile: CERSAI_Search_Report_200237508107_For_Asset_Based_Search_17_05_2022_23_58_14_687.pdf17 May 2022
Layout approvalFile: PLOT 2 SANCTION PLAN -01_compressed.pdf16 May 2022
Building plan approvalFile: PLOT 2 SANCTION PLAN -02_compressed.pdf16 May 2022
Building plan approvalFile: PLOT 2 SANCTION PLAN -03_compressed.pdf16 May 2022
Building plan approvalFile: PLOT 2 SANCTION PLAN -04_compressed.pdf16 May 2022
PAN CardFile: PAN CARD VA.pdf16 May 2022
Copy of the legal title reportFile: tile search plot 2.pdf16 May 2022
Copy of Layout Approval (in case of layout)File: PLOT 2 SANCTION PLAN -01_compressed.pdf16 May 2022
Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -02_compressed.pdf16 May 2022
Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -03_compressed.pdf16 May 2022
Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -04_compressed.pdf16 May 2022
Commencement Certificates / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN CC_compressed.pdf16 May 2022
Declaration about Commencement CertificateFile: Declaration Commencemant Certificate.pdf16 May 2022
Declaration in FORM BFile: Affidavit cum declaration_compressed.pdf16 May 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf16 May 2022
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneer Certificate_compressed.pdf16 May 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate_compressed.pdf16 May 2022
Proforma of Allotment letterFile: Allotment Letter.pdf16 May 2022
Proforma of Allotment letterFile: Venk-21-p-2-fl-agr-rera-PLOT NO_2.pdf16 May 2022

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late2 not delivered by the promised date1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Venkatesh KamalaPR1260002502850Navi Peth, Pune11Mar 2026OngoingDec 2028Not due yet
Venkatesh Hillside Building AP52100077270Dhayari, Pune-Aug 2024CompletedApr 2026Late, May 2026
LAKE TOWN D-6, WING - A and BP52100053248KATRAJ, Pune28Oct 2023OngoingMar 2026Registered original: Dec 2025Not delivered
Venkatesh Hillside Building BP52100045766DHAYARI, Pune-Jun 2022CompletedMay 2024Late, May 2025
CRYSTAL PARADISE BUILDING A, BP52100045774., Pune-Jun 2022OngoingMay 2024Not delivered
Venkatesh GalaxyS. No. 44 2 Part Kondhwa Budurk40-CompletedFeb 2016Dec 2015

How this compares with Pune

0%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 18 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Venkatesh Hill Side, Plot No. 2, Building 1 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near DHAYARI13,700+ in Pune

Builder: VENKATESH ASSOCIATES

VENKATESH ASSOCIATES has 14 registrations on MahaRERA, including OXY EVOLVE and OXY DESIRE. Its filings disclose 12 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Venkatesh Hill Side, Plot No. 2, Building 1 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Venkatesh Hill Side, Plot No. 2, Building 1 is delayed beyond 30 Nov 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Venkatesh Hill Side, Plot No. 2, Building 1?

The registered promoter entity is VENKATESH ASSOCIATES, a partnership as per the filing. Its GSTIN 27AADFV7559E1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Venkatesh Hill Side, Plot No. 2, Building 1?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Venkatesh Hill Side, Plot No. 2, Building 1?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Venkatesh Hill Side, Plot No. 2, Building 1?

The professionals named in the filing: Architect: MANOHAR YERAWAR; Engineer: Structus Consultantss Pvt. Ltd.; Chartered Accountant: Jori & Co; Chartered Accountant: Rajendra Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Venkatesh Hill Side, Plot No. 2, Building 1?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Venkatesh Hill Side, Plot No. 2, Building 1. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Venkatesh Hill Side, Plot No. 2, Building 1 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.