Venkatesh Hill Side, Plot No. 2, Building 1
RG-MH-66420 · RERA P52100045700 · Last updated on MahaRERA portal: 30 May 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 11 months past the filed date
- Completion date moved by 18 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Venkatesh Hill Side, Plot No. 2, Building 1 is a Residential / Group Housing project by VENKATESH ASSOCIATES in Pune, Maharashtra, registered with MahaRERA as P52100045700 on 6 Jun 2022. Possession was promised by 30 Nov 2025 and is now 11 months past that date. The completion date has moved by 18 months from the original filing. 0 of the 1 unit on this registration is recorded sold or booked, and 3 of 11 construction stages are filed complete.
At a glance
Project
- NameVenkatesh Hill Side, Plot No. 2, Building 1
- TypeResidential / Group Housing
- Location
- MAIN ROAD
- DHAYARI
- Haveli
- Pune
- 411041
- Pincode411041
- RERA no.P52100045700
- ReraGenie IDRG-MH-66420
Builder
- NameVENKATESH ASSOCIATES
- Entity typePartnership
- GSTIN27AADFV7559E1ZU
- GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- PartnersANIL GOPAL GANDHI, MILIND SHANTIKUMAR PANDIT, KALIDAS NIVRUTTI JAGADE
- Other registrations13 more →
- Completed7 of 14
- No longer live4 lapsed, de-registered or revoked
- Declared earlier projects12 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on6 Jun 2022
- Promised completion30 Nov 2025
- Revised completionRevised to 30 Nov 2025 (originally 31 May 2024)
- Buildings1 building record
- Documents filed66 files
Current status
Figures as on 30 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Venkatesh Hill Side, Plot No 2, Building 1 | NA | 7 | 6 | 1 | 0 | 1 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 30 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 14%.
Venkatesh Hill Side, Plot No 2, Building 1: 29% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 14% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 30 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Land and ownership6
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| MRS.SUREKHA SUDHAKAR JADHAVAR | Wadgaon Bk | Pune |
| MR. MAHESH NARAYANDAS AMBAVANI | Navi Mumbai (M Corp.) | Thane |
| MR. HARSH DEVANDAS LALWANI | Navi Mumbai (M Corp.) | Thane |
| MR. SACHIN JAIKUMAR BAJAJ | Ahmadnagar (M Corp.) | Ahmednagar |
| MR. SUSHIL RAMLAL BAJAJ | Ahmadnagar (M Corp.) | Ahmednagar |
| MR. SURENDER RAMLAL BAJAJ | Ahmadnagar (M Corp.) | Ahmednagar |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners4
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MANOHAR YERAWAR |
| Engineer | Structus Consultantss Pvt. Ltd. |
| Chartered Accountant | Jori & Co |
| Chartered Accountant | Rajendra Shah & Co |
| Partner | Role in project |
|---|---|
| VENKATESH ASSOCIATES | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe RCC work in progress. In between the work slowed down due to slow booking and project funds were not arranged. Whereas, now funds have been arranged and clients are also ready for booking so to complete the project successfully we need the possession date extension. We also declare that currently we have not booked / sold any of the flat inventory.
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 16 May 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 16 May 2022 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 16 May 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 16 May 2022Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed66
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: FORM 5 HILLSIDE BLDG 1.pdf | 30 May 2026 |
| Form 1File: Q3 Form 1 Architect Letter Bldg 1.pdf | 6 May 2026 |
| Form 2File: Q3 FORM 2 Engineer Certificate Bldg 1.pdf | 6 May 2026 |
| Form 3File: Q3 Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Q3 Disclosure of sold - Booked Inventory Bldg 1.pdf | 6 May 2026 |
| Form 1File: Form 1 Architect Letter Bldg 1.pdf | 6 May 2026 |
| Form 2File: FORM 2 Engineer Certificate Bldg 1.pdf | 6 May 2026 |
| Form 3File: Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Booked Inventory Bldg 1.pdf | 6 May 2026 |
| Form 1File: Form 1 Architect Letter Bldg 1.pdf | 6 May 2026 |
| Form 2File: FORM 2 Engineer Certificate Bldg 1.pdf | 6 May 2026 |
| Form 3File: Chartered Accountants ( Bldg 1 Plot No 2)_compressed.pdf | 6 May 2026 |
| Disclosure of Sold and Booked InventoryFile: Disclosure of sold - Booked Inventory Bldg 1.pdf | 6 May 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Letter( Hillside BLDG 1 ).pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accounted ( BLDG - 1 )_compressed.pdf | 24 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accounted ( BLDG - 1 )_compressed.pdf | 24 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificat ( HILLSIDE BLDG -1 ).pdf | 24 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: GetUserDocumentFileContent.pdf | 24 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 ( Annual Repaort ).pdf | 24 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate ( Bldg 1 ).pdf | 28 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate ( Bldg 1 Dhayari ).pdf | 28 May 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Account Certificate ( Bldg 1 )_compressed.pdf | 28 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 5 Annual Report Hillside Blgd 1 Plot No 2.pdf | 5 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Gandhi Sir ).pdf | 5 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Ghate Sir ).pdf | 5 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter ( Pandit Sir ).pdf | 5 Apr 2024 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure Letter (Jagade Sir ).pdf | 5 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold Inventory.pdf | 7 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Lettere (Venkatesh Hillside Bldg 1 ).pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginee Certificate ( Venkatesh Hillside Bldg 1 ).pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Certificate ( Venkatesh Hillside Bldg 1 )_compressed.pdf | 20 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside Bldg 1 - Form 1 - 23-24 Q2_compressed.pdf | 20 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside Bldg 1 - Form 2 - 23-24 Q2.pdf | 20 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Hillside Bldg 1 - Form 3 - 23-24 Q2_compressed.pdf | 20 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Hillside Bldg 1 - Form 1 - 22-23 Q2_compressed.pdf | 17 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Hillside Bldg 1 - Form 2 - 22-23 Q2_compressed.pdf | 17 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Hillside Bldg 1 - Form 3 - 22-23 Q2_compressed.pdf | 17 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architects Certificate Bldg 1.pdf | 10 May 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Enginee Certificate Bldg 1.pdf | 10 May 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Ac Certificate Bldg 1_compressed.pdf | 10 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Bldg - 1_compressed.pdf | 7 Feb 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Bldg - 1_compressed.pdf | 7 Feb 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Account Certificate Bldg - 1_compressed.pdf | 7 Feb 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate (Venkatesh Hill side, Bldg - 1 ).pdf | 29 Nov 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineenr Certificate ( Venkatesh Hillside , Bldg -1,Plot No 2 )_compressed.pdf | 29 Nov 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Venkatesh Hill Side Bldg -1 , Plot No 2 ( C A)_compressed.pdf | 29 Nov 2022 |
| Details of encumbrancesFile: Encumbrance Certificate Plot No.pdf | 17 May 2022 |
| CERSAI detailsFile: CERSAI_Search_Report_200237508107_For_Asset_Based_Search_17_05_2022_23_58_14_687.pdf | 17 May 2022 |
| Layout approvalFile: PLOT 2 SANCTION PLAN -01_compressed.pdf | 16 May 2022 |
| Building plan approvalFile: PLOT 2 SANCTION PLAN -02_compressed.pdf | 16 May 2022 |
| Building plan approvalFile: PLOT 2 SANCTION PLAN -03_compressed.pdf | 16 May 2022 |
| Building plan approvalFile: PLOT 2 SANCTION PLAN -04_compressed.pdf | 16 May 2022 |
| PAN CardFile: PAN CARD VA.pdf | 16 May 2022 |
| Copy of the legal title reportFile: tile search plot 2.pdf | 16 May 2022 |
| Copy of Layout Approval (in case of layout)File: PLOT 2 SANCTION PLAN -01_compressed.pdf | 16 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -02_compressed.pdf | 16 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -03_compressed.pdf | 16 May 2022 |
| Building Plan Approval / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN -04_compressed.pdf | 16 May 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: PLOT 2 SANCTION PLAN CC_compressed.pdf | 16 May 2022 |
| Declaration about Commencement CertificateFile: Declaration Commencemant Certificate.pdf | 16 May 2022 |
| Declaration in FORM BFile: Affidavit cum declaration_compressed.pdf | 16 May 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate_compressed.pdf | 16 May 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engneer Certificate_compressed.pdf | 16 May 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Chartered Accountants Certificate_compressed.pdf | 16 May 2022 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 16 May 2022 |
| Proforma of Allotment letterFile: Venk-21-p-2-fl-agr-rera-PLOT NO_2.pdf | 16 May 2022 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Venkatesh KamalaPR1260002502850 | Navi Peth, Pune | 11 | Mar 2026 | Ongoing | Dec 2028 | Not due yet |
| Venkatesh Hillside Building AP52100077270 | Dhayari, Pune | - | Aug 2024 | Completed | Apr 2026 | Late, May 2026 |
| LAKE TOWN D-6, WING - A and BP52100053248 | KATRAJ, Pune | 28 | Oct 2023 | Ongoing | Mar 2026Registered original: Dec 2025 | Not delivered |
| Venkatesh Hillside Building BP52100045766 | DHAYARI, Pune | - | Jun 2022 | Completed | May 2024 | Late, May 2025 |
| CRYSTAL PARADISE BUILDING A, BP52100045774 | ., Pune | - | Jun 2022 | Ongoing | May 2024 | Not delivered |
| Venkatesh Galaxy | S. No. 44 2 Part Kondhwa Budurk | 40 | - | Completed | Feb 2016 | Dec 2015 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 13 other registrations, which the RERA portal never shows together
- All 66 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Venkatesh Hill Side, Plot No. 2, Building 1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near DHAYARI13,700+ in Pune
VYANA PHASE-I -T5, T6, T7
KOLTE-PATIL DEVELOPERS LIMITED
Pratham Vihar Phase I
LJR Constructions LLP
VYANA PHASE-I-T2,T3 AT THE RESERVE
KOLTE-PATIL DEVELOPERS LIMITED
MAITREE MEGA CITY
MAITREE INFRA
RAMANA MYRA
SAI AND SHANTISHOBHA VENTURE
Apple Regency
Sri Sidhievinayak associetes
Builder: VENKATESH ASSOCIATES
VENKATESH ASSOCIATES has 14 registrations on MahaRERA, including OXY EVOLVE and OXY DESIRE. Its filings disclose 12 earlier MahaRERA projects: declares 6 of 9 past projects completed on time. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Venkatesh Hill Side, Plot No. 2, Building 1 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Venkatesh Hill Side, Plot No. 2, Building 1 is delayed beyond 30 Nov 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Venkatesh Hill Side, Plot No. 2, Building 1?
The registered promoter entity is VENKATESH ASSOCIATES, a partnership as per the filing. Its GSTIN 27AADFV7559E1ZU can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Venkatesh Hill Side, Plot No. 2, Building 1?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Venkatesh Hill Side, Plot No. 2, Building 1?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Venkatesh Hill Side, Plot No. 2, Building 1?
The professionals named in the filing: Architect: MANOHAR YERAWAR; Engineer: Structus Consultantss Pvt. Ltd.; Chartered Accountant: Jori & Co; Chartered Accountant: Rajendra Shah & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Venkatesh Hill Side, Plot No. 2, Building 1?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback