| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| VENKATESH HILLSIDE BUILDING CPR1260002601043 | Dhayri, Pune, 411041 | 46 | 0% | 6 Jul 2026 | Registered |
| LAKE TOWN D-6, WING - A and BP52100053248 | KATRAJ, Pune, 411046 | 28 | 43% | 23 Oct 2023 | Completed |
| Venkatesh KamalaPR1260002502850 | Navi Peth, Pune, 411030 | 11 | 0% | 16 Mar 2026 | Registered |
| Venkatesh GitanjaliPR1260002601871 | Sadashiv Peth, Pune, 411030 | 6 | 0% | 10 Sep 2026 | Registered |
| Venkatesh Hill Side, Plot No. 2, Building 1P52100045700 | DHAYARI, Pune, 411041 | 1 | 0% | 6 Jun 2022 | Registration lapsed |
| CRYSTAL PARADISE BUILDING A, BP52100045774 | ., Pune, 411048 | - | - | 9 Jun 2022 | Registration lapsed |
| OXY DESIREP52100002355 | GADE VASTI, Pune, 412207 | - | - | 31 Jul 2017 | Registration lapsed |
| OXY EVOLVEP52100000772 | WAGHOLI, Pune, 412207 | - | - | 23 Jul 2017 | Completed |
| Venkatesh GalaxyP52100006088 | Tilekar Nagar, Pune, 411048 | - | - | 14 Aug 2017 | Completed |
| Venkatesh Galaxy Wing D2 and FP52100033881 | Kondhwa BK, Pune, 411048 | - | - | 14 Mar 2022 | Completed |
| VENKATESH HEIGHTSP52100015206 | BABURAO NAGAR, SHIRUR, Pune, 412210 | - | - | 7 Feb 2018 | Registration lapsed |
| Venkatesh Hillside Building AP52100077270 | Dhayari, Pune, 411041 | - | - | 2 Aug 2024 | Completed |
| Venkatesh Hillside Building BP52100045766 | DHAYARI, Pune, 411041 | - | - | 9 Jun 2022 | Completed |
| Venketesh Galaxy Wing D1P52100021669 | Kondhwa Budruk, Pune, 411048 | - | - | 19 Jul 2019 | Completed |
What this promoter declares as its own experience
VENKATESH ASSOCIATES declares experience on 12 earlier projects. 6 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.
6 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it. A completion date is also recorded against 1 registration MahaRERA does not show as completed. A registration lapses when a promoter files neither a completion nor an extension, so that can mean the completion was never filed rather than that the project was not finished.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Venkatesh Classic | 1 May 2013 | 2 Mar 2013 | On time |
| Venkatesh Classic B | 1 May 2013 | 2 Mar 2013 | On time |
| OXY PRIMO | 30 Jun 2015 | 1 Sep 2016 | +14 months |
| Venkatesh Galaxy | 1 Feb 2016 | 21 Dec 2015 | On time |
| VENKATESH GALAXY | 1 Feb 2016 | 21 Dec 2015 | On time |
| Venkatesh Prasad | 30 Jun 2017 | 24 Apr 2017 | On time |
| CRYSTAL PARADISE BUILDING A, B P52100045774 | 31 May 2024 | Not completed yet | Ongoing |
| Venkatesh Hillside Building B P52100045766 | 31 May 2024 | 31 May 2025 | +12 months |
| Venkatesh Hill Side, Plot No. 2, Building 1 P52100045700 | 30 Nov 2025 | 30 Nov 2025 | On time |
| LAKE TOWN D-6, WING - A and B P52100053248 | 31 Mar 2026 | Not completed yet | Ongoing |
| Venkatesh Hillside Building A P52100077270 | 30 Apr 2026 | 8 May 2026 | On time |
| Venkatesh Kamala PR1260002502850 | 17 Dec 2028 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify VENKATESH ASSOCIATES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its GSTIN 27AADFV7559E1ZU on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with VENKATESH ASSOCIATES?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.
Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.
Report an errorShare feedbackData from official MahaRERA filings. How we handle corrections is on the about page.