Home / Browse projects / Pune, Maharashtra / V UPTOWN

Registered No litigation declared Residential / Group Housing project

V UPTOWN

By TATVAM CONSTRUCTIONS PRIVATE LIMITED

RG-MH-87153 · RERA P52100046930 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 27 months
  • 2 extensions taken
  • Rs 20.00 crore secured on the land, in favour of Aditya Birla Capital Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • No litigation declared
  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 27 months from the original
18 of 22Construction stages doneacross 2 buildings; furthest along: Installation of Lifts, 95%
76 of 194Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 127 documents Report an error

V UPTOWN is a Residential / Group Housing project by TATVAM CONSTRUCTIONS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100046930 on 20 Sep 2022. Possession is promised by 30 Jun 2027. The completion date has moved by 27 months from the original filing. 118 of the 194 units on this registration are recorded sold or booked, and 18 of 22 construction stages are filed complete.

At a glance

Project

  • NameV UPTOWN
  • TypeResidential / Group Housing
  • Location
    • PUNE
    • KATALE VASTI
    • Kivale
    • Mawal
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100046930
  • ReraGenie IDRG-MH-87153

Builder

  • NameTATVAM CONSTRUCTIONS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45400MH1995PTC093430
  • GSTIN27AACCA7657E1ZN
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorDIPAK RAMNIKLAL SHAH
  • DirectorSAMEER RAMNIKLAL SHAH
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live2 lapsed, de-registered or revoked
  • Declared earlier projects5 →

Key dates

this monthRegisteredSep 2022First promiseMar 2025Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on20 Sep 2022
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 31 Mar 2025)
  • Buildings2 building records
  • Documents filed127 files

Current status

61%118 of 194 units booked
105.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
D WINGNA19161260126
E WINGNA191768068

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

18 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Installation of Lifts, at 95%.

D WING91%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E WING90%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises90%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes70%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed417

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots417
Closed/Covered417
BuildingClosed/CoveredTotal
D WING318318
E WING9999

Land and ownership2

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area16,600 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared present
Charge in favour ofAditya Birla Capital Ltd
Secured amountRs 20.00 crore
CERSAI search filedYes
Declared on12 Mar 2026
LandownerVillageDistrict
BALKRISHNA PRABHAKAR KATALEKiwalePune
SANDEEP PRABHAKAR KATALEKiwalePune

Approvals and building plan

Sanctioning authorityPimpri-Chinchwad Municipal Corporation
Permissible FSI18478.35
Proposed, not sanctioned18,478 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBRAMHAPURI NIVAS KIWALE
Estimated costRs 50.82 cr
Cost incurredRs 53.33 cr
Work done104.95%
BuildingWingEstimatedIncurred
D WINGNARs 23.38 crRs 25.39 cr
E WINGNARs 21.64 crRs 22.03 cr
-NARs 5.81 crRs 5.91 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUNUSUAL SPACES
EngineerMR SOMNATH TAGRE
EngineerDevendra Ramlu Pingale
EngineerSuraj H Kapre
Chartered AccountantSANDEEP MORAB
Chartered AccountantMorab & Associates
Chartered AccountantP R C & Co.
Chartered AccountantNavdeep Jindal And Associates
PartnerRole in project
TATVAM CONSTRUCTIONS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100028294Mar 2025 → Jun 2026

Reason as filed by the promoterWe apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2026 to complete the project and fulfil all regulatory requirements. We seek your understa

EA16062621389Mar 2025 → Jun 2027

Reason as filed by the promoterThe project could not be completed within the stipulated validity period due to factors beyond our control, including delays in the supply of raw materials owing to ongoing geopolitical conditions, shortage of labour during the construction period, and delays in obtaining various NOCs from competent authorities. These constraints have adversely impacted the timely progress and completion of the project.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Aug 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 8 Aug 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 27 Jul 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2027

Documents filed127

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 127 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 Jun_26.pdf20 Jul 2026
Withdrawal Update Form 2File: FORM 2-Jun_26 Sign.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3-Sign.pdf20 Jul 2026
Form 1File: 7-2-Form 1-Arch cert-Mar 25.pdf16 Jun 2026
Form 2File: Form-2-DE-Mar 25-revised.pdf16 Jun 2026
Form 3File: Form-3-DE-Mar 25-revised.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory March-25.pdf16 Jun 2026
Form 1File: 7-1-Form 1-Arch cert-Dec 24.pdf16 Jun 2026
Form 2File: Form 2 - Dec 24.pdf16 Jun 2026
Form 3File: Form 3 -Dec 24.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Dec-24.pdf16 Jun 2026
Form 1File: Form-1-June24.pdf16 Jun 2026
Form 2File: Form-2-30-06-24.pdf16 Jun 2026
Form 3File: Form 3 Jun 24 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Jun_24.pdf16 Jun 2026
Form 1File: Form-1 march24.pdf16 Jun 2026
Form 2File: Form-2-31-03-24.pdf16 Jun 2026
Form 3File: Form 3 Mar 24 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory March 24.pdf16 Jun 2026
Form 1File: Form-1 Dec23.pdf16 Jun 2026
Form 2File: Form-2-31-12-23.pdf16 Jun 2026
Form 3File: Form 3 Dec 23 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Dec 23.pdf16 Jun 2026
Form 1File: Form-1-Sept 23.pdf16 Jun 2026
Form 2File: Form-2-30-09-23.pdf16 Jun 2026
Form 3File: Form 3 Sep 23 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Sept 23.pdf16 Jun 2026
Form 1File: Form-1-Sept 24.pdf16 Jun 2026
Form 2File: Form-2-30-09-24.pdf16 Jun 2026
Form 3File: Form-3-30-09-24 Signed.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Sep 24 Sign.pdf16 Jun 2026
Form 1File: Form-1-June23.pdf16 Jun 2026
Form 2File: Form-2-30-06-23.pdf16 Jun 2026
Form 3File: Form 3 Jun 23 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory June-23.pdf16 Jun 2026
Form 1File: Form-1 March 23.pdf16 Jun 2026
Form 2File: Form-2-31-03-23.pdf16 Jun 2026
Form 3File: Form 3 Mar 23 Sign.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Mar 23.pdf16 Jun 2026
Form 1File: Form-1-Dec22.pdf16 Jun 2026
Form 2File: Form-2-31-12-22.pdf16 Jun 2026
Form 3File: Form 3 Dec 22 Sign Compressed.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Dec 22.pdf16 Jun 2026
Form 1File: Form-1-Sept 22.pdf16 Jun 2026
Form 2File: Form-2-30-09-22.pdf16 Jun 2026
Form 3File: Form-3-30-09-22.pdf16 Jun 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of sold-Booked Inventory Sep 22.pdf16 Jun 2026
Withdrawal Update Form 1File: Form 1-Arch Cert-31 03 26.pdf16 Jun 2026
Withdrawal Update Form 2File: Form 2-Mar 26.pdf16 Jun 2026
Withdrawal Update Form 3File: Form 3 Mar 26 Compressed.pdf16 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A.pdf16 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A - 24-25.pdf16 Jun 2026
Form 2A (FY 2023-2024)File: Form 2A - 23-24.pdf16 Jun 2026
Form 2A (FY 2022-2023)File: Form 2A - 22-23.pdf16 Jun 2026
Form 5 (FY 2022-2023)File: Form 5-22-23.pdf16 Jun 2026
Form 5 (FY 2023-2024)File: Form 5-23-24.pdf16 Jun 2026
Form 5 (FY 2024-2025)File: Form 5-24-25.pdf16 Jun 2026
Form 5 (FY 2025-2026)File: Form-5-FY 25-26.pdf16 Jun 2026
Withdrawal Update Form 1File: Arch Cert-311225.pdf9 Jun 2026
Withdrawal Update Form 2File: Engg Cert-311225.pdf9 Jun 2026
Withdrawal Update Form 3File: CA Cert-311225_.pdf9 Jun 2026
Layout approvalFile: HPSCANNER1234-Highlighted.pdf20 Jan 2026
Withdrawal Update Form 1File: Form 1 - 30-6-25.pdf9 Dec 2025
Withdrawal Update Form 1File: Form 1 - 30-9-25.pdf9 Dec 2025
Withdrawal Update Form 2File: Form 2-30-6-25.pdf9 Dec 2025
Withdrawal Update Form 2File: Form 2-30-9-25.pdf9 Dec 2025
Withdrawal Update Form 3File: Form 3 - 30-6-25.pdf9 Dec 2025
Withdrawal Update Form 3File: Form 3 - 30-9-25.pdf9 Dec 2025
Building plan approvalFile: HPSCANNER1234-Highlighted (1).pdf8 Aug 2025
Building plan approvalFile: 7 OF 15 D WING.pdf24 Jul 2025
Building plan approvalFile: 8 OF 15 D WING.pdf24 Jul 2025
Building plan approvalFile: 9 OF 15 D WING.pdf24 Jul 2025
Building plan approvalFile: HPSCANNER1235.pdf23 Jul 2025
Building plan approvalFile: HPSCANNER1236.pdf23 Jul 2025
Layout approvalFile: HPSCANNER1234-Highlighted.pdf19 Jul 2025
Declaration in FORM BFile: Form B.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Dec 24.pdf28 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1-Mar 25.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 31-12-2024_11zon.pdf28 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - 31-03-25_11zon.pdf28 Apr 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
V UPTOWN C WINGP52100021002KIWALE ,KATALE VASTI, Pune-May 2019Certificate SignedJun 2024Registered original: Dec 2022Jun 2024
V UPTOWNSR NO 9392-CompletedJun 2021Late, Jun 2022

How this compares with Pune

61%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 27 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep V UPTOWN on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KATALE VASTI13,700+ in Pune

2 kmV UPTOWNCompleted 163Lapsed / revoked 119Other 151Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: TATVAM CONSTRUCTIONS PRIVATE LIMITED

TATVAM CONSTRUCTIONS PRIVATE LIMITED has 5 registrations on MahaRERA, including V UPTOWN WING-B and V UPTOWN C WING. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if V UPTOWN is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of V UPTOWN?

The registered promoter entity is TATVAM CONSTRUCTIONS PRIVATE LIMITED, a company as per the filing. Its CIN U45400MH1995PTC093430 and GSTIN 27AACCA7657E1ZN can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in V UPTOWN?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for V UPTOWN?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at V UPTOWN?

The professionals named in the filing: Architect: UNUSUAL SPACES; Engineer: MR SOMNATH TAGRE; Engineer: Devendra Ramlu Pingale; Engineer: Suraj H Kapre; Chartered Accountant: SANDEEP MORAB; Chartered Accountant: Morab & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in V UPTOWN?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About V UPTOWN. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save V UPTOWN to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.