TATVAM CONSTRUCTIONS PRIVATE LIMITED: RERA track record

CIN U45400MH1995PTC093430 · GSTIN 27AACCA7657E1ZN · Company · attribution by exact filing name, entity resolution in progress

TATVAM CONSTRUCTIONS PRIVATE LIMITED has 5 registrations on MahaRERA, including V UPTOWN WING-B and V UPTOWN C WING. Its filings disclose 5 earlier MahaRERA projects: declares 1 of 5 past projects completed on time.

5RERA registrations
5Past projects disclosed
+8 monthsMedian delivery slip
0Registrations with litigation
Follow this developer. An email when TATVAM CONSTRUCTIONS PRIVATE LIMITED registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 5 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
V UPTOWNP52100046930KATALE VASTI, Pune, 41210119461%20 Sep 2022Registered
V-Uptown, A-wingPR1262022600758Kiwale, Pune, 4121011860%12 Jun 2026Registered
V UPTOWN C WINGP52100021002KIWALE ,KATALE VASTI, Pune, 412101--27 May 2019Completed
V UPTOWN F WING MHADA COMMERCIALP52100021198KIWALE, Pune, 412101--14 Jun 2019Registration lapsed
V UPTOWN WING-BP52100005194Kiwale, Pune, 412101--10 Aug 2017Registration lapsed

What this promoter declares as its own experience

TATVAM CONSTRUCTIONS PRIVATE LIMITED declares experience on 5 earlier projects. One carries a registration number we could match on MahaRERA, under this promoter's own name.

One of these declarations can be compared with the dates that project's own registration holds. On that one, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on the one completion recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
VIVANA
31 Dec 201310 Sep 2014+8 months
VIVIANA
31 Dec 201310 Sep 2014+8 months
TATVAM VERTEX
31 Dec 201530 Jun 2016+6 months
V UPTOWN
30 Jun 202130 Jun 2022+12 months
V UPTOWN C WING
P52100021002
12 Jun 202412 Jun 2024On time

Frequently asked questions

How do I verify TATVAM CONSTRUCTIONS PRIVATE LIMITED as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45400MH1995PTC093430 and GSTIN 27AACCA7657E1ZN on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with TATVAM CONSTRUCTIONS PRIVATE LIMITED?

Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

The record above looks clean. What should I still check?

A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback