Home / Browse projects / Pune, Maharashtra / SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED
SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED
RG-MH-94549 · RERA P52100050177 · Last updated on MahaRERA portal: 25 May 2026
Source: official MahaRERA filing
Red flags
- Completion date moved by 7 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED is a Residential / Group Housing project by SAMRUDDHEE CONSTRUCTIONS in Pune, Maharashtra, registered with MahaRERA as P52100050177 on 21 Mar 2023. The registration is recorded completed; possession was promised by 31 Dec 2025. The completion date has moved by 7 months from the original filing. 14 of the 35 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.
At a glance
Project
- NameSUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED
- TypeResidential / Group Housing
- Location
- VASTU UDYOG
- ANTRIKSHA SOCIETY ROAD
- PIMPRI WAGHERE
- Pimpri Chinchawad (M Corp.)
- Haveli
- Pune
- 411018
- Pincode411018
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100050177
- ReraGenie IDRG-MH-94549
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on21 Mar 2023
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 31 May 2025)
- Buildings1 building record
- Documents filed102 files
Current status
Figures as on 25 May 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| SUNVIEW CO-OPERATIVE SOCIETY LIMITED | NA | 8 | 7 | 35 | 0 | 35 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 25 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.
SUNVIEW CO-OPERATIVE SOCIETY LIMITED: 91% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | No | Not applicable |
| Landscaping & Tree Planting | No | Not applicable |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | No | Not applicable |
| Open Parking | No | Not applicable |
Parking filed18
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership3
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED | Pimpri Chinchawad (M Corp.) | Pune |
| SUNVIEW CO-OPERATIVE HOUSING OCIETY LIMITED | Pimpri Chinchawad (M Corp.) | Pune |
| SUN VIEW CO-OPERATIVE HOUSING SOCIETY LIMITED | Pimpri Chinchawad (M Corp.) | Pune |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| SUNVIEW CO-OPERATIVE SOCIETY LIMITED | NA | Rs 9.39 cr | Rs 9.39 cr |
| - | NA | Rs 29.03 lakh | Rs 29.03 lakh |
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | ASHOKE PAWAR |
| Engineer | SHREEKANT RAMESH LONDHE |
| Engineer | KIRAN SHISODE |
| Chartered Accountant | VISHAKHA VIPIN HARNOL |
| Chartered Accountant | Pankaj Surana |
| Partner | Role in project |
|---|---|
| SAMRUDDHEE CONSTRUCTIONS | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe delay is primarily due to the ongoing agitation and administrative delays in the Maharashtra Bhumi Abhilekh (MAHA Bhulekh) office
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 7 Mar 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Dec 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Dec 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Dec 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed102
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 102 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Gmail - Fwd_ Completion Certificate Verification For RERA Application No -P52100050177 15- | 25 May 2026 |
| Form 5 (FY 2024-2025)File: Samruddhee Constructions Sunview Form 5 2024-2025.pdf | 24 Jan 2026 |
| Withdrawal Update Form 1File: Form-1 -.pdf | 18 Oct 2025 |
| Withdrawal Update Form 2File: Sunview Form-2.pdf | 18 Oct 2025 |
| Withdrawal Update Form 3File: Form-3_compressed.pdf | 18 Oct 2025 |
| Occupational CertificateFile: Sun View Completion.pdf | 1 Oct 2025 |
| Form 1File: Rera Certificate 30 June.pdf | 16 Aug 2025 |
| Form 2File: Engineer Certificate June -23.pdf | 16 Aug 2025 |
| Form 3File: CA Certificate June -30.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Rera Certificate 30 June.pdf | 16 Aug 2025 |
| Form 2File: Engineer Certificate June -23.pdf | 16 Aug 2025 |
| Form 3File: CA Certificate June -30.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Rera Certificate 30 June.pdf | 16 Aug 2025 |
| Form 2File: Engineer Certificate June -23.pdf | 16 Aug 2025 |
| Form 3File: CA Certificate June -30.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Form 1.pdf | 16 Aug 2025 |
| Form 2File: Form 2.pdf | 16 Aug 2025 |
| Form 3File: Form 3.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Architect Certificate Form 1.pdf | 16 Aug 2025 |
| Form 2File: Engineer Certificate Form 2.pdf | 16 Aug 2025 |
| Form 3File: CA Certificate Form 3.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Rera Architect Certificate Sunview.pdf | 16 Aug 2025 |
| Form 2File: Rera Eng Certificate Sunview.pdf | 16 Aug 2025 |
| Form 3File: Rera CA Certificate Sunview.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Sunview Architech Certificate Form-1.pdf | 16 Aug 2025 |
| Form 2File: Form 2_compressed.pdf | 16 Aug 2025 |
| Form 3File: Form 3.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Form 1File: Sunview Form 1 Rera Architech Certificate.pdf | 16 Aug 2025 |
| Form 2File: Sunview Form 2 Rera Eng Certificate.pdf | 16 Aug 2025 |
| Form 3File: Sunview Form 3 Rera CA Certificate.pdf | 16 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Sold Unsold Sunview.pdf | 16 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 16 Aug 2025 |
| Withdrawal Update Form 1File: Form 1.pdf | 16 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 16 Aug 2025 |
| Withdrawal Update Form 2File: Form 2.pdf | 16 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Aug 2025 |
| Withdrawal Update Form 3File: Form 3.pdf | 16 Aug 2025 |
| Form 1File: Form 1 Sun View.pdf | 30 May 2025 |
| Form 2File: Form 2 Sun View.pdf | 30 May 2025 |
| Form 3File: Form 3 Sun View.pdf | 30 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 Sun View.pdf | 25 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Sun View.pdf | 25 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sun View.pdf | 25 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Sunview Form 1 Rera Architech Certificate.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3 Sunview.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Sunview Form 3 Rera CA Certificate.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sunview Form 2 Rera Eng Certificate.pdf | 20 Jan 2025 |
| Layout approvalFile: 01.pdf | 25 Dec 2024 |
| Building plan approvalFile: 02.pdf | 25 Dec 2024 |
| Building plan approvalFile: 03.pdf | 25 Dec 2024 |
| Copy of Layout Approval (in case of layout)File: 01.pdf | 25 Dec 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement_organized.pdf | 25 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 02.pdf | 25 Dec 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: 03.pdf | 25 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Architect Certificate Sunview.pdf | 11 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Rera Eng Certificate Sunview.pdf | 11 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Rera CA Certificate Sunview.pdf | 11 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate Form 1.pdf | 17 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Form 2.pdf | 17 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Form 3.pdf | 17 Apr 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 Samruddhee Constructions.pdf | 15 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf | 15 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf | 15 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf | 15 Feb 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Certificate 30 June.pdf | 7 Dec 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Rera Certificate 30 Sep.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate June -23.pdf | 7 Dec 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate Sep -23.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate June -30.pdf | 7 Dec 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate Sep -30.pdf | 7 Dec 2023 |
| Disclosure of Interest in Other Real Estate OrganizationsFile: 1 Disclosure of Interest in Other Real Estate Organizations_page-0001.pdf | 15 Mar 2023 |
| Proforma of Allotment letterFile: AL.pdf | 15 Mar 2023 |
| Proforma of Agreement for saleFile: sun view__ as per RERA norms 15032023.pdf | 15 Mar 2023 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 102 filed documents as one ZIP, foldered, with a manifest
Keep SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near PIMPRI WAGHERE13,700+ in Pune
Filed coordinates, straight-line distance. 77 registered projects within 2 km.
Godrej Emerald Waters
Godrej Properties Limited
Mahindra Citadel - Phase 5
Mahindra Lifespace Developers limited
Mahindra Citadel Phase 1
Mahindra Lifespace Developers limited
Bramha Sky Uzuri Phase 2
BRAMHA LEISURES PVT LTD
RAJVEER IMPERIA
Waghere Associates
KOHINOOR SHANGRILA PHASE 2
KOHINOOR PROPERTIES
Builder: SAMRUDDHEE CONSTRUCTIONS
SAMRUDDHEE CONSTRUCTIONS has 3 registrations on MahaRERA, including SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED and SAMRUDDHI SUYOG. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED?
The registered promoter entity is SAMRUDDHEE CONSTRUCTIONS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED?
The professionals named in the filing: Architect: ASHOKE PAWAR; Engineer: SHREEKANT RAMESH LONDHE; Engineer: KIRAN SHISODE; Chartered Accountant: VISHAKHA VIPIN HARNOL; Chartered Accountant: Pankaj Surana. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in SUNVIEW CO-OPERATIVE HOUSING SOCIETY LIMITED?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback