Home / Browse projects / Pune, Maharashtra / Sun Exotica Phase 2

Completed No litigation declared Others project

Sun Exotica Phase 2

By Jindal Mittal Graha Nirman Pvt. Ltd.

RG-MH-46254 · RERA P52100018347 · Last updated on MahaRERA portal: 16 Aug 2023

Source: official MahaRERA filing

Red flags

  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2021Possession promisedregistration recorded completed
30 of 33Construction stages doneacross 3 buildings; furthest along: External plumbing and external plaster, 80%
0Complaints at MahaRERAon this registration
Jump to the 58 documents Report an error

Sun Exotica Phase 2 is a Others project by Jindal Mittal Graha Nirman Pvt. Ltd. in Pune, Maharashtra, registered with MahaRERA as P52100018347 on 24 Oct 2018. The registration is recorded completed; possession was promised by 30 Jun 2021.

At a glance

Project

  • NameSun Exotica Phase 2
  • TypeOthers
  • Location
    • -
    • S. No. 10/2/4
    • YAWALEWADI
    • Haveli
    • Pune
    • 411048
  • Pincode411048
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100018347
  • ReraGenie IDRG-MH-46254

Builder

  • NameJindal Mittal Graha Nirman Pvt. Ltd.
  • Entity typeCompany
  • CINU45202PN2002PTC016883
  • GSTIN27AABCJ3501F1Z2
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorAshok Ramchandra Mittal
  • Other registrations9 more →
  • Completed4 of 10
  • Declared earlier projects10 →

Key dates

this monthRegisteredOct 2018PromisedJun 2021Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Oct 2018
  • Promised completion30 Jun 2021
  • Revised completionNone
  • Buildings3 building records
  • Documents filed58 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A WingNA150000
B WingNA150000
E WingNA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 16 Aug 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

30 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is External plumbing and external plaster, at 80%.

A Wing89%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B Wing91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
E Wing100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 16 Aug 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes66%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes66%
Landscaping & Tree PlantingYes100%
Street LightingYes80%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes66%
Energy managemcntYes66%
Fire protection and fire safety requirementsYes66%
Electrical meter room, sub-station, receiving stationYes66%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes66%

Parking filed193

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots193
Closed/Covered193
BuildingClosed/CoveredTotal
A Wing9696
B Wing7272
E Wing2525

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area6,955 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI13219.0
Proposed, not sanctioned11,437 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchTilak Road, Near Grahak Peth, Pune - 411030

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkur Associates
PartnerRole in project
Jindal Mittal Graha Nirman Pvt. Ltd.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100009854Jun 2021 → Jun 2022

Reason as filed by the promoterWork stopped by local government body (Pune Municipal Corporation) from 03/10/2019, so its need to extend the date of completion of the project - building No. E

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Oct 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Oct 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 14 Jul 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Jul 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 27 Mar 2023

Documents filed58

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate - SUN EXOCITA E WING 11-08-2023.pdf16 Aug 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 Engineer Certificate - Exotica Phase 2 -July 2023.pdf15 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Sun Harmony Form 2A.pdf15 Jul 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A -SUN EXOTICA.pdf15 Jul 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Exotica 2 - March 22.pdf9 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Sun Exotica -Sept 22.pdf9 Jun 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5-Sun Exotica Phase II.pdf9 Jun 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate E Wing - 03-03-23.pdf27 Mar 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Exotica 2 - March 22.pdf3 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 - Sun Exotica -Sept 22.pdf3 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A -SUN EXOTICA.pdf17 Jan 2023
Disclosure of sold/ booked inventoryFile: SOLD - UNSOLD INVENTORY.pdf17 Jan 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part Completion - Sun Exotica E wing.pdf17 Jan 2023
Engineers Certificate on Quality Assurance (Form 2A)File: Sun Exotica 2 - April 22 -.pdf22 Apr 2022
CERSAI detailsFile: CERSAI - Exotica 2.pdf22 Apr 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 - Exotica 2 - April 22.pdf22 Apr 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Completion Certificate Wing A - B.pdf22 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate - SUN EXOCITA A WING 12-10-2021.pdf22 Apr 2022
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Certificate - SUN EXOCITA B WING 17-08-2021.pdf22 Apr 2022
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Exotica Phase 2.pdf24 Jul 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 - Exotica Phs 2 Final.pdf24 Jul 2021
Building plan approvalFile: E Wing 3.pdf14 Jul 2021
Building plan approvalFile: E Wing 4.pdf14 Jul 2021
Building Plan Approval (IOD)File: E Wing 3.pdf14 Jul 2021
Building Plan Approval (IOD)File: E Wing 4.pdf14 Jul 2021
Commencement Certificates / NA Order for plotted developmentFile: CC Revised - 05-07-2021.pdf14 Jul 2021
Declaration about Commencement CertificateFile: Declaration about commencement certificate - Exotica.pdf14 Jul 2021
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form No 5.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form No 5-1.pdf23 Jun 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form No 5-2.pdf23 Jun 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A.pdf16 Jun 2021
Disclosure of sold/ booked inventoryFile: Form 3A - Sold Inventary - Sun Exotica PHS 2.pdf16 Jun 2021
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 - Exotica Phs II.pdf16 Mar 2021
Engineers Certificate on Quality Assurance (Form 2A)File: Form 2A - Exotica 2A.pdf18 Feb 2020
Engineers Certificate on Quality Assurance (Form 2A)File: Quality Assurance Certificate Form 2A - 1.pdf2 Oct 2019
Annual Audit Report of Statutory CA (Form 5)File: CA Certificate - 1.pdf2 Oct 2019
Building plan approvalFile: A Wing 1.pdf16 Oct 2018
Building plan approvalFile: A Wing 2.pdf16 Oct 2018
Building plan approvalFile: B WIng 1.pdf16 Oct 2018
Building plan approvalFile: B Wing 2.pdf16 Oct 2018
Building plan approvalFile: E Wing 1.pdf16 Oct 2018
Building plan approvalFile: E Wing 2.pdf16 Oct 2018
Layout approvalFile: Layout.pdf16 Oct 2018
PAN CardFile: 2 Pan Card JMGNPL.pdf16 Oct 2018
Copy of the legal title reportFile: Title - Search Report.pdf16 Oct 2018
Details of encumbrancesFile: Index II.pdf16 Oct 2018
Copy of Layout Approval (in case of layout)File: Layout.pdf16 Oct 2018
Building Plan Approval (IOD)File: A Wing 1.pdf16 Oct 2018
Building Plan Approval (IOD)File: A Wing 2.pdf16 Oct 2018
Building Plan Approval (IOD)File: B WIng 1.pdf16 Oct 2018
Building Plan Approval (IOD)File: B Wing 2.pdf16 Oct 2018
Building Plan Approval (IOD)File: E Wing 1.pdf16 Oct 2018
Building Plan Approval (IOD)File: E Wing 2.pdf16 Oct 2018
Commencement Certificates / NA Order for plotted developmentFile: CC - 07-08-2018.pdf16 Oct 2018
Declaration in FORM BFile: Form B - Phase II.pdf16 Oct 2018
Certificates of CA (Form 3)File: Form 3 CA - Exotica PS2.pdf16 Oct 2018
Proforma of Allotment letterFile: Agreement Draft as per Rera_Sun Exotica Phase II.pdf16 Oct 2018

Promoter's earlier projects9

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise2 delivered late6 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SUN GLORYPR1260002600531Sadashiv Peth, Pune96May 2026OngoingMar 2031Not due yet
SUN REGALIAPR1261012502103Wadgaon Bk, Pune147Jan 2026OngoingDec 2030Not due yet
SUN GARNETPR1260002502092Mundhawa, Pune129Jan 2026OngoingDec 2030Not due yet
SUN APEXPR1261012501939AMBEGAON Bk, Pune140Dec 2025OngoingDec 2030Not due yet
Sun PlatinaP52100080580Koregaon Park Annex, Pune21Jun 2025OngoingMar 2030Not due yet
Sun EmeraldP52100055372Raghavendra Nagar150Mar 2024OngoingDec 2029Not due yet
Sun Planet Phase IIIP52100018258Anand Nagar, Pune-Oct 2018CompletedDec 2019Late, Jan 2020
Sun SapphireP52100001938-, Pune-Jul 2017CompletedDec 2018Late, Jun 2019
Sun Exotica Phase 1P52100001696-, Pune-Jul 2017CompletedDec 2018Dec 2018

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is completed

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Sun Exotica Phase 2 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near S. No. 10/2/413,700+ in Pune

2 kmSun Exotica Phase 2Completed 162Lapsed / revoked 119Other 152Dot size: filed unitsN

Filed coordinates, straight-line distance. 433 registered projects within 2 km.

Builder: Jindal Mittal Graha Nirman Pvt. Ltd.

Jindal Mittal Graha Nirman Pvt. Ltd. has 10 registrations on MahaRERA, including Sun Exotica Phase 1 and Sun Sapphire. Its filings disclose 10 earlier MahaRERA projects: declares 1 of 4 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Sun Exotica Phase 2 is delayed beyond 30 Jun 2021?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Sun Exotica Phase 2?

The registered promoter entity is Jindal Mittal Graha Nirman Pvt. Ltd., a company as per the filing. Its CIN U45202PN2002PTC016883 and GSTIN 27AABCJ3501F1Z2 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Sun Exotica Phase 2?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Sun Exotica Phase 2?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Sun Exotica Phase 2?

The professionals named in the filing: Architect: Ankur Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Sun Exotica Phase 2?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Sun Exotica Phase 2. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Sun Exotica Phase 2 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.