Jindal Mittal Graha Nirman Pvt. Ltd. has 10 registrations in this build, including Sun Exotica Phase 1 and Sun Sapphire. Its filings disclose 10 earlier MahaRERA projects: 1 of 4 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Sun Exotica Phase 1 | Pune, Maharashtra | - | - | Completed |
| Sun Sapphire | Pune, Maharashtra | - | - | Completed |
| Sun Planet Phase III | Pune, Maharashtra | - | - | Completed |
| Sun Exotica Phase 2 | Pune, Maharashtra | - | - | Completed |
| Sun Emerald | Maharashtra | 150 | 33% | Registered |
| SUN GARNET | Pune, Maharashtra | 129 | 0% | Registered |
| Sun Platina | Pune, Maharashtra | 21 | 0% | Registered |
| SUN APEX | Pune, Maharashtra | 140 | 0% | Registered |
| SUN REGALIA | Pune, Maharashtra | 147 | 0% | Registered |
| SUN GLORY | Pune, Maharashtra | 96 | 0% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Sun Exotica Phase 1 P52100001696 | 31 Dec 2018 | 24 Dec 2018 | On time |
| Sun Sapphire P52100001938 | 31 Dec 2018 | 24 Jun 2019 | +6 months |
| Sun Planet Phase III P52100018258 | 31 Dec 2019 | 2 Jan 2020 | On time |
| Sun Exotica Phase 2 P52100018347 | 30 Jun 2021 | 3 Mar 2023 | +20 months |
| Sun Emerald P52100055372 | 31 Dec 2029 | Not completed yet | Ongoing |
| Sun Platina P52100080580 | 31 Mar 2030 | Not completed yet | Ongoing |
| SUN APEX PR1261012501939 | 31 Dec 2030 | Not completed yet | Ongoing |
| SUN REGALIA PR1261012502103 | 31 Dec 2030 | Not completed yet | Ongoing |
| SUN GARNET PR1260002502092 | 31 Dec 2030 | Not completed yet | Ongoing |
| SUN GLORY PR1260002600531 | 31 Mar 2031 | Not completed yet | Ongoing |
Frequently asked questions
How do I verify Jindal Mittal Graha Nirman Pvt. Ltd. as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Jindal Mittal Graha Nirman Pvt. Ltd.?
Add the median slip shown above to any possession date this promoter quotes you, and plan your rent, loan and school-year decisions around that stressed date. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Jindal Mittal Graha Nirman Pvt. Ltd. unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.