Home / Browse projects / Pune, Maharashtra / SHALIGRAM PAVILLIA

Registered No litigation declared Others project

SHALIGRAM PAVILLIA

By SHALIGRAM REALTY LLP

RG-MH-27719 · RERA P52100034451 · Last updated on MahaRERA portal: 8 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2027Possession promisedno revision filed
17 of 55Construction stages doneacross 5 buildings; furthest along: Internal walls, 95%
68 of 224Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 116 documents Report an error

SHALIGRAM PAVILLIA is a Others project by SHALIGRAM REALTY LLP in Pune, Maharashtra, registered with MahaRERA as P52100034451 on 5 Apr 2022. Possession is promised by 31 Dec 2027. 156 of the 224 units on this registration are recorded sold or booked, and 17 of 55 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameSHALIGRAM PAVILLIA
  • TypeOthers
  • Location
    • GAHUNJE
    • Mawal
    • Pune
    • 412101
  • Pincode412101
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034451
  • ReraGenie IDRG-MH-27719

Builder

  • NameSHALIGRAM REALTY LLP
  • Entity typePartnership
  • PartnersTUSHAR CHANDUBHAI PATEL, SURESH MOHANBHAI MEGHANI, RASIK MAGANBHAI ROKAD, KAPILKUMAR DINESHBHAI PATEL, YOGESH DNYANESWAR CHINCHWADE, MARUTI DEEPAK MORE, AMAN BALWANT PATEL
  • Other registrations1 more →
  • Declared earlier projects2 →

Key dates

this monthRegisteredApr 2022PromisedDec 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on5 Apr 2022
  • Promised completion31 Dec 2027
  • Revised completionNone
  • Buildings5 building records
  • Documents filed116 files

Current status

70%156 of 224 units booked
38.3%Work done, per cost certificate

Figures as on 8 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
A-WINGNA210000
B-WINGNA210000
C-WINGNA20181050105
D-WINGNA20181050105
COMMERCIAL BUILDINGNA5201414

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building5

As on 8 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

17 of 55 construction stages are filed complete across 5 buildings. The stage furthest along is Internal walls, at 95%.

A-WING14%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
B-WING23%
ActivityProgress
Excavation100%
Basement (if any)50%
Podiums (if any)100%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
C-WING80%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises95%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D-WING82%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
COMMERCIAL BUILDING9%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes90%
Water SupplyYes90%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes90%
Storm Water DrainsYes90%
Landscaping & Tree PlantingYes90%
Street LightingYes90%
Community BuildingsYes90%
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes90%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed4

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4
Closed/Covered4
BuildingClosed/CoveredTotal
A-WING11
B-WING11
C-WING11
D-WING11

Land and ownership4

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area12,000 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
LandownerVillageDistrict
TANAJI BABURAO BODAKETalegaon Dabhade (R)Pune
MACHINDRA BABURAO BODAKEGahunjePune
GORAKH BABURAO BODAKEGahunjePune
ASHOK BABURAO BODAKEGahunjePune

Approvals and building plan

Sanctioning authorityPune Metropolitan Regional Development Authority
Permissible FSI41991.76
Proposed, not sanctioned9,666 sq m
Buildings approved5
Buildings sanctioned5

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchPLOT NO 1, SEC-27, PRADHIKARAN, NIGADI, PUNE-411044
Estimated costRs 122.00 cr
Cost incurredRs 46.69 cr
Work done38.27%
BuildingWingEstimatedIncurred
C-WINGNARs 56.34 crRs 21.01 cr
D-WINGNARs 56.23 crRs 20.97 cr
COMMERCIAL BUILDINGNARs 5.77 crRs 2.15 cr
-NARs 3.66 crRs 2.56 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectUNUSUAL SPACES
EngineerShreyas Naran Divekar
EngineerSK Consultants & Engineers
EngineerShaligram Pavillia.
Chartered AccountantCAVIREN POKAR
Chartered AccountantN B Sayed & Associates
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantPHP & Associates
PartnerRole in project
Shaligram Realty LLP-

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC12602602Suraj Sanjay OtariShaligram Realty LLP04/05/2026
CC12603521Vijaykumar Siddayya HiremathShaligram Realty LLP07/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 25 Mar 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Apr 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Apr 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 25 Mar 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2027

Documents filed116

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 116 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 2A (FY 2025-2026)File: Shaligram Pavillia Form2A FOR 2025-26.pdf8 Jul 2026
Layout approvalFile: 01 Layout Plan 28-08-2025_1_11zon.pdf16 Apr 2026
Building plan approvalFile: 01 Layout Plan 28-08-2025_1_11zon.pdf16 Apr 2026
Building plan approvalFile: 2.pdf16 Apr 2026
Building plan approvalFile: 7_8_3_4_5_6_merged.pdf16 Apr 2026
Building plan approvalFile: 9-15.pdf16 Apr 2026
Withdrawal Update Form 1File: Form 1 - Shaligram Pavillia as on March 2026.pdf16 Apr 2026
Withdrawal Update Form 2File: Form 2 - Shaligram Pavillia as on March 2026.pdf16 Apr 2026
Withdrawal Update Form 3File: Form 3 - Shaligram Pavillia as on March 2026.pdf16 Apr 2026
Form 5 (FY 2022-2023)File: Form 5 Shalligram Pavillia of FY 22-23.pdf12 Mar 2026
Form 5 (FY 2023-2024)File: Form 5 Shalligram Pavillia of FY 23-24.pdf12 Mar 2026
Form 5 (FY 2024-2025)File: Form 5 Shalligram Pavillia of FY 2024-25.pdf12 Mar 2026
Withdrawal Update Form 1File: Form 1 - Shaligram Pavillia as on Dec 2025.pdf14 Jan 2026
Withdrawal Update Form 2File: Form 2 - Shaligram Pavillia as on Dec 2025.pdf14 Jan 2026
Withdrawal Update Form 3File: Form 3 - Shaligram Pavillia as on Dec 2025.pdf14 Jan 2026
Withdrawal Update Form 1File: Form 1 - Shaligram Pavillia as on Sep 2025.pdf7 Nov 2025
Withdrawal Update Form 1File: Form 1 - Shaligram Pavillia as on Sep 2025.pdf7 Nov 2025
Withdrawal Update Form 2File: Form 2 - Shaligram Pavillia as on Sept 2025.pdf7 Nov 2025
Withdrawal Update Form 2File: Form 2 - Shaligram Pavillia as on Sept 2025.pdf7 Nov 2025
Withdrawal Update Form 3File: Form 3 of Shaligram Pavillia as on 30-09-2025.pdf7 Nov 2025
Withdrawal Update Form 3File: Form 3 of Shaligram Pavillia as on 30-09-2025.pdf7 Nov 2025
Layout approvalFile: 01 Layout Plan 28-08-2025_1_11zon.pdf11 Sep 2025
Building plan approvalFile: 2.pdf11 Sep 2025
Building plan approvalFile: 3.pdf11 Sep 2025
Building plan approvalFile: 4.pdf11 Sep 2025
Building plan approvalFile: 5.pdf11 Sep 2025
Building plan approvalFile: 6.pdf11 Sep 2025
Building plan approvalFile: 7.pdf11 Sep 2025
Building plan approvalFile: 8.pdf11 Sep 2025
Building plan approvalFile: 9.pdf11 Sep 2025
Building plan approvalFile: 10.pdf11 Sep 2025
Building plan approvalFile: 11.pdf11 Sep 2025
Building plan approvalFile: 12.pdf11 Sep 2025
Building plan approvalFile: 13.pdf11 Sep 2025
Building plan approvalFile: 14.pdf11 Sep 2025
Form 1File: Form 1 - Shaligram Pavillia as on March 2025.pdf6 Sep 2025
Form 2File: Form 2 - Shaligram Pavillia as on March 2025.pdf6 Sep 2025
Form 3File: Form 3 - Shaligram Pavillia as on March 2025.pdf6 Sep 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Shaligram Pavillia as on March 2025.pdf6 Sep 2025
Form 1File: Form 1 - Shaligram Pavillia as on June 2025.pdf20 Jul 2025
Form 2File: Form 2- Shaligram Pavillia as on June 2025.pdf20 Jul 2025
Form 3File: Form 3 - Shaligram Pavillia as on June 2025.pdf20 Jul 2025
Disclosure of Sold and Booked InventoryFile: Circular 29 - Shaligram Pavillia as on June 2025.pdf20 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shaligram Pavillia as on March 2025.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2022.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2023.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2023_compressed.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March 2024.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - June 2024_compressed.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Sep 2024.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Dec 2024.pdf3 May 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Shaligram Pavillia as on March 2025.pdf3 May 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2- Shaligram Pavillia as on March 2025.pdf3 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form 5 - 22-23.pdf3 May 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 - 23-24.pdf3 May 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Shaligram Pavillia as on March 2025.pdf19 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM-1.pdf24 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3-Q3_11zon.pdf24 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2.pdf24 Jan 2025
Disclosure of sold/ booked inventoryFile: SOLD - UNSOLD_11zon.pdf24 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT’S CERTIFICATE D BUILDING.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_11zon.pdf22 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf22 Oct 2024
Disclosure of sold/ booked inventoryFile: SOLD-UNSOLD_11zon.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE_compressed.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECT CERTIFICATE.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_compressed.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3-QUERTER ENDED-31-3-2024.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_compressed.pdf8 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_compressed.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE FORM-2.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER CERTIFICATE.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Eng Certificate_compressed.pdf8 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf8 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: From 2A Shaligram Pavillia.pdf8 Oct 2024
Proforma of Agreement for saleFile: SHALIGRAM PAVILLIA DRAFT.pdf14 Nov 2022
Layout approvalFile: LAYOUT_compressed.pdf25 Mar 2022
Layout approvalFile: PARKING LAYOUT.pdf25 Mar 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
SHALIGRAM SKYP52100033364KIWALE, Pune653Feb 2022OngoingAug 2026Not delivered

How this compares with Pune

70%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep SHALIGRAM PAVILLIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GAHUNJE13,700+ in Pune

2 kmSHALIGRAM PAVILLIACompleted 21Lapsed / revoked 12Other 34Dot size: filed unitsN

Filed coordinates, straight-line distance. 67 registered projects within 2 km.

Builder: SHALIGRAM REALTY LLP

SHALIGRAM REALTY LLP has 2 registrations on MahaRERA, including SHALIGRAM SKY and SHALIGRAM PAVILLIA. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if SHALIGRAM PAVILLIA is delayed beyond 31 Dec 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of SHALIGRAM PAVILLIA?

The registered promoter entity is SHALIGRAM REALTY LLP, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in SHALIGRAM PAVILLIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against SHALIGRAM PAVILLIA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for SHALIGRAM PAVILLIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at SHALIGRAM PAVILLIA?

The professionals named in the filing: Architect: UNUSUAL SPACES; Engineer: Shreyas Naran Divekar; Engineer: SK Consultants & Engineers; Engineer: Shaligram Pavillia.; Chartered Accountant: CAVIREN POKAR; Chartered Accountant: N B Sayed & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in SHALIGRAM PAVILLIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About SHALIGRAM PAVILLIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save SHALIGRAM PAVILLIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.