Home / Browse projects / Thane, Maharashtra / PUSHPANJALI RESIDENCY PHASE III
PUSHPANJALI RESIDENCY PHASE III
By Shriraam Pioneer Developers Private Limited
RG-MH-38887 · RERA P51700008949 · Last updated on MahaRERA portal: 25 Apr 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 10 months past the filed date
- 12 complaints at MahaRERA
- Completion date moved by 36 months
- 3 extensions taken
Clear
- No litigation declared
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
PUSHPANJALI RESIDENCY PHASE III is a Others project by Shriraam Pioneer Developers Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700008949 on 19 Aug 2017. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 36 months from the original filing. 531 of the 589 units on this registration are recorded sold or booked, and 394 of 605 construction stages are filed complete. 12 complaints are on record with the regulator.
At a glance
Project
- NamePUSHPANJALI RESIDENCY PHASE III
- TypeOthers
- Location
- Ghodbunder Road
- Owale
- Thane (M Corp.)
- Thane
- 400615
- Pincode400615
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700008949
- ReraGenie IDRG-MH-38887
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on19 Aug 2017
- Promised completion31 Dec 2025
- Revised completionRevised to 31 Dec 2025 (originally 30 Dec 2022)
- Buildings55 building records
- Documents filed109 files
Current status
Figures as on 25 Apr 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| S1 | NA | 32 | 30 | 145 | 0 | 145 |
| S2 | NA | 32 | 30 | 145 | 0 | 145 |
| S3 | NA | 32 | 30 | 145 | 0 | 145 |
| S4 | NA | 31 | 30 | 145 | 0 | 145 |
| BUNGALOW 41 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 42 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 43 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 44 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 45 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 46 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 47 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 48 | NA | 2 | 2 | 1 | 0 | 1 |
| BUNGALOW 49 | NA | 2 | 2 | 1 | 0 | 1 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
| NA | NA | 0 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building20
As on 25 Apr 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 55 buildings; the table lists the first 20.
394 of 605 construction stages are filed complete across 55 buildings. The stage furthest along is External plumbing and external plaster, at 55%.
S139%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 30% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 3% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S239%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 30% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 3% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S327%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
S427%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
BUNGALOW 4182%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4282%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4382%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4482%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4582%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4682%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4782%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4882%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
BUNGALOW 4982%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
NA82%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities15
As on 25 Apr 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 95% |
Parking filed493
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Open Space | Total |
|---|---|---|---|
| S1 | 100 | 24 | 124 |
| S2 | 100 | 24 | 124 |
| S3 | 100 | 24 | 124 |
| S4 | 98 | 23 | 121 |
Land and ownership
Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | AKRUTI CONSULTANTS |
| Engineer | Associated Structural Engineers LLP |
| Chartered Accountant | HARIYA AND GANATRA |
| Chartered Accountant | ANJALI GHATKAR & CO |
| Chartered Accountant | N.R Panchal & Co. |
| Partner | Role in project |
|---|---|
| Shriraam Pioneer Developers Private Limited | - |
Extensions applied for3
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterProject got delayed due to eco sensitive zone declared on ghodbunder road, all projects are on Halt. But now it got cleared according to judgement given by the supreme court. Now everything is in place, we can complete this project in dec 2023, kindly grant us the extension.
Reason as filed by the promoter• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led to
Reason as filed by the promoter• The real estate industry went through multiple challenges over the pandemic years with supply chain disruption, labour crisis, and budget crunch slowing down growth. • We have been grappled with shortage of labour and a demand slump challenges triggered by market volatility. Construction rates have shot up and the market has also witnessed the pressure of inflation. • Due to unavailability of skilled labour and labour migration issues, project is affected a lot. Even contractors are asking us to allow them more time due to labour issues. • The geopolitical tension around the globe has led to
Complaints filed with MahaRERA12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000000624 | Mahesh Gopal Bhior | mohan baburao shinde | 15/09/2017 |
| CC006000000079441 | HARVINDER SINGH DHILLON | M/S. RAM DEVELOPERS | 03/06/2019 |
| CC006000000209681 | Anupama Amresh sharma | Ram Developers | 15/01/2022 |
| CC006000000333771 | Hemant Bulchandani | Paradigm UBER INFRA LLP | 31/12/2022 |
| CC006000000375066 | MANASI MANISH PURI | RAM DEVELOPERS | 01/04/2023 |
| CC006000000480023 | MANASI MANISH PURI | M/S RAM DEVELOPERS | 10/04/2024 |
| CC006000000397650 | MADHUSUDAN TAPADIA | Shreeram Pioneers Developers Pvt Ltd | 12/10/2023 |
| CC006000000500486 | Rajeshkumar Vishwakarma | Shriraam pioneer developers pvt ltd | 29/05/2024 |
| CC12401202 | Rajeshkumar Vishwakarma | Shriraam Pioneer Developers Private Limited | 21/12/2024 |
| CC12401203 | Seema Vishwakarma | Shriraam Pioneer Developers Private Limited | 21/12/2024 |
| CC12500069 | prakash suhas halde | Shriraam Pioneer Developers Private Limited | 08/01/2025 |
| CC12503839 | Anil Subhash Jaiswal | Shriraam Pioneer Developers Private Limited | 01/11/2025 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 30 Mar 2022 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 13 Jul 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 30 Mar 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 13 Jul 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 25 Apr 2025
Documents filed109
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 109 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Part OC_11zon.pdf | 25 Apr 2025 |
| Other - TechnicalFile: Part OC_11zon.pdf | 25 Apr 2025 |
| Other - TechnicalFile: CPM RAM.pdf | 30 Mar 2025 |
| Declaration in FORM BFile: Form B.pdf | 28 Mar 2025 |
| Disclosure of sold/ booked inventoryFile: Circular 29.pdf | 28 Mar 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf | 28 Mar 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf | 31 Jan 2025 |
| Certificates of CA (Form 3)File: Form3.pdf | 31 Jan 2025 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 31 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Form5.pdf | 31 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form5.pdf | 31 Jan 2025 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf | 13 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf | 13 Nov 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf | 13 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3_As on 30924_Edited as per query.pdf | 13 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3_As on 30924_Edited as per query.pdf | 13 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 13 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 13 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 13 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 13 Nov 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM2.pdf | 13 Nov 2024 |
| Certificates of CA (Form 3)File: Form 3_As on 30924.pdf | 30 Oct 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1.pdf | 2 Aug 2024 |
| Details of encumbrances concerned to FinanceFile: Annexure_F-Non-Encumbrance_Concerned_to_Finance.pdf | 15 May 2024 |
| Details of encumbrances concerned to LegalFile: Annexure_F-Non-Encumbrance_Concerned_to_Finance.pdf | 15 May 2024 |
| CERSAI detailsFile: Annexure_D-Asset_Based_Declaration_.pdf | 15 May 2024 |
| CERSAI detailsFile: Annexure_E-_Debtor_Based_Declaration.pdf | 15 May 2024 |
| Disclosure of sold/ booked inventoryFile: Annexure_B-Disclosure_of_Sold_or_Unsold_Inventory_compressed.pdf | 15 May 2024 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM_2_311223.pdf | 9 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Self_Declaration_for_FORM_2A.pdf | 9 May 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Self_Declaration_for_FORM_2A.pdf | 9 May 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM_5_20222_2023_2.pdf | 9 May 2024 |
| Declaration in FORM BFile: FORM_B.pdf | 1 Apr 2024 |
| Certificates of CA (Form 3)File: FORM_3_compressed.pdf | 1 Apr 2024 |
| PAN CardFile: PancardSPDPL.pdf | 13 Mar 2024 |
| Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM1.pdf | 5 Feb 2024 |
| Details of encumbrances concerned to FinanceFile: 4 Details of encumbrances_S1S2S3S4.pdf | 27 Oct 2023 |
| Details of encumbrances concerned to LegalFile: 4 Details of encumbrances_S1S2S3S4.pdf | 27 Oct 2023 |
| Layout approvalFile: 1_Layout Plan.pdf | 13 Jul 2023 |
| Copy of Layout Approval (in case of layout)File: 1_Layout Plan.pdf | 13 Jul 2023 |
| Commencement Certificates / NA Order for plotted developmentFile: Revised Commencement Certificate dated_4_7_2023_1.pdf | 13 Jul 2023 |
| Details of encumbrancesFile: Encumbrance_Certificate_RD_.pdf | 27 Jun 2023 |
| Declaration about Commencement CertificateFile: Declaration_for_Extension_Compressed.pdf | 7 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Sold_Inventory__compressed1_11zon.pdf | 7 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Unsold_Inventory__Compressed.pdf | 7 Jan 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: FORM 2A_FY_2019_2020 (1).pdf | 28 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: FORM 2A_FY_2020_2021.pdf | 28 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_FY_2020_2021.pdf | 28 Nov 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A_FY_2021_2022.pdf | 28 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: FORM 5_FY_2018_2019.pdf | 28 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: FORM 5_FY_2019_2020.pdf | 28 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5_FY_2021_2022.pdf | 28 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5_CA Certificate_compressed.pdf | 25 May 2022 |
| Building plan approvalFile: Commencement Certificate_2021_NEW.pdf | 30 Mar 2022 |
| Layout approvalFile: Lay_Out_Plan_2021_NEW.pdf | 30 Mar 2022 |
| Copy of the legal title reportFile: Title Certificate_NEW_07_04_2021_new.pdf | 30 Mar 2022 |
| Copy of Layout Approval (in case of layout)File: Lay_Out_Plan_2021_NEW.pdf | 30 Mar 2022 |
| Building Plan Approval (IOD)File: Commencement Certificate_2021_NEW.pdf | 30 Mar 2022 |
| Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate_2021_NEW.pdf | 30 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate_FORM_2_S1___S2.pdf | 30 Mar 2022 |
| Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Engineering Certificate_FORM_2_S3___S4.pdf | 30 Mar 2022 |
| Certificates of CA (Form 5)File: FORM5_Certificate_CA.pdf | 30 Jul 2019 |
| Copy of the legal title reportFile: 1 to 6.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 7 to 12.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 13 to 18.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 19 to 24.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 25 to 30.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 31 to 36.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 37 to 42.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 43 to 44.pdf | 8 Nov 2017 |
| Copy of the legal title reportFile: 1.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 2.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 3.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 4.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 5.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 6.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 7.pdf | 16 Oct 2017 |
| Copy of the legal title reportFile: 8.pdf | 16 Oct 2017 |
| Details of encumbrancesFile: encumbrance.pdf | 16 Oct 2017 |
| Details of encumbrancesFile: encumbrance.pdf | 16 Oct 2017 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| PUSHPANJALI RESIDENCY PHASE IIIP51700050376 | OWALE THANE, Thane | 403 | Apr 2023 | Ongoing | Dec 2028 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 109 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep PUSHPANJALI RESIDENCY PHASE III on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Owale7,600+ in Thane
Filed coordinates, straight-line distance. 150 registered projects within 2 km.
Godrej Emerald Thane
Godrej Greenview Housing Private Limited
NORTH IMPERIAL GREENS -TOWER 2
Skylark Buildspace Private Limited
VIHANG MARINA
BALAJI ENTERPRISES
Puranik City Reserva Phase 1
Puranik Builders Limited
NORTH IMPERIAL GREENS - TOWER 1
Skylark Buildspace Private Limited
RAUNAK 108
UNNATHI ASSOCIATES
See every Thane project, with the district possession charts
Builder: Shriraam Pioneer Developers Private Limited
Shriraam Pioneer Developers Private Limited has 2 registrations on MahaRERA, including PUSHPANJALI RESIDENCY PHASE III and PUSHPANJALI RESIDENCY PHASE III. Its filings disclose 1 earlier MahaRERA project, none completed yet. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that PUSHPANJALI RESIDENCY PHASE III shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if PUSHPANJALI RESIDENCY PHASE III is delayed beyond 31 Dec 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of PUSHPANJALI RESIDENCY PHASE III?
The registered promoter entity is Shriraam Pioneer Developers Private Limited, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in PUSHPANJALI RESIDENCY PHASE III?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against PUSHPANJALI RESIDENCY PHASE III?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for PUSHPANJALI RESIDENCY PHASE III?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at PUSHPANJALI RESIDENCY PHASE III?
The professionals named in the filing: Architect: AKRUTI CONSULTANTS; Engineer: Associated Structural Engineers LLP; Chartered Accountant: HARIYA AND GANATRA; Chartered Accountant: ANJALI GHATKAR & CO; Chartered Accountant: N.R Panchal & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in PUSHPANJALI RESIDENCY PHASE III?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback