PRISTINE PALAZZO

By KANHA DEVELOPERS

RG-MH-22567 · RERA P52100032976 · Last updated on MahaRERA portal: 23 Jan 2025

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 4 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 38%
0Complaints at MahaRERAon this registration
Jump to the 62 documents Report an error

PRISTINE PALAZZO is a Commercial project by KANHA DEVELOPERS in Pune, Maharashtra, registered with MahaRERA as P52100032976 on 2 Feb 2022. Possession is promised by 31 Dec 2026.

At a glance

Project

  • NamePRISTINE PALAZZO
  • TypeCommercial
  • Location
    • Mumbai Pune Highway
    • Punawale
    • Mulshi
    • Pune
    • 411018
  • Pincode411018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100032976
  • ReraGenie IDRG-MH-22567

Builder

  • NameKANHA DEVELOPERS
  • Entity typePartnership
  • GSTIN27AAWFK5031H1Z1
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersParitosh Rajendra Agarwal, Sachin Ishwarchand Goyal, Sankalp Subhash Goel
  • Other registrations4 more →
  • Completed1 of 5
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredFeb 2022PromisedDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Feb 2022
  • Promised completion31 Dec 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed62 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
PRISTINE PALAZZONA84000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 23 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 38%.

PRISTINE PALAZZO: 33% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure38%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises20%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks10%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 23 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes5%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed39

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots39
Closed/Covered37
Open Space2

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area4,200 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Sanctioning authorityPimpri Chinchwad Municipal Corporation
Permissible FSI2938.99
Proposed, not sanctioned2,939 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchM-4, Virwani Plaza,11, East Street, Pune - 411004

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectJAY AERAM
EngineerSantosh Beknalkar
EngineerSK Consultants & Builders
EngineerSTS Consultants LLP
Chartered AccountantRSMS and Associates
Chartered AccountantRutuja Narsingh & Associates
Chartered AccountantN B Sayed & Associates
PartnerRole in project
KANHA DEVELOPERS-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 7 Jan 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Apr 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Apr 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Apr 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed62

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form_1_.pdf23 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf23 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form1.pdf10 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf10 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 (2).pdf18 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engg cetificate 31-3-24.pdf15 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf3 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A Pristine Palazzo.pdf3 Apr 2024
Disclosure of sold/ booked inventoryFile: Circular 29.pdf3 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf3 Apr 2024
Details of encumbrancesFile: Mortgage Index 2.pdf2 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arichtech Certificate.pdf13 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf13 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf21 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf21 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf26 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf29 Aug 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: ANNEXTURE-5 ANNUAL RETURN.pdf21 Aug 2023
CERSAI detailsFile: AMPL_KANHA _CERSAI REGISTRATION.pdf17 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Scan_20230817_144618.pdf17 Aug 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1.pdf26 Jul 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: form 2.pdf26 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: RSMS FROM NO 3_1.pdf28 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RSMS FROM NO 5.pdf28 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEERS CERTIFICATE 1904.pdf24 Apr 2023
Declaration about Commencement CertificateFile: FORM D DECLARATION COMMECEMENT.pdf12 Apr 2023
Layout approvalFile: HPSC1059_Compressed.pdf11 Apr 2023
Building plan approvalFile: HPSC1058_Compressed.pdf11 Apr 2023
Building plan approvalFile: HPSC1060_Compressed.pdf11 Apr 2023
Building plan approvalFile: HPSC1058_Compressed.pdf11 Apr 2023
Building plan approvalFile: HPSC1061_Compressed.pdf11 Apr 2023
Copy of Layout Approval (in case of layout)File: HPSC1059_Compressed.pdf11 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1058_Compressed.pdf11 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1060_Compressed.pdf11 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1058_Compressed.pdf11 Apr 2023
Building Plan Approval / NA Order for plotted developmentFile: HPSC1061_Compressed.pdf11 Apr 2023
Commencement Certificates / NA Order for plotted developmentFile: REVISED CC2023.pdf11 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architect certificate 11 04 2023.pdf11 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: RERA ENGINEERS CERTIFICATE 11 04 2023.pdf11 Apr 2023
CERSAI detailsFile: CERSAI_Search_Report_200228272158_For_Asset_Based_Search_18_01_2022_12_41_48_356.pdf18 Jan 2022
Copy of the legal title reportFile: Title Search Report Kanha.pdf7 Jan 2022
Declaration about Commencement CertificateFile: Declaration About Commencemnt Certificate.pdf23 Dec 2021
Declaration in FORM BFile: Affidavit - B 1.pdf23 Dec 2021
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf16 Dec 2021
PAN CardFile: PAN_Kanha Developers (1).pdf16 Dec 2021
Details of encumbrancesFile: Encumbrances Lettar Dt 20-12-2021.pdf16 Dec 2021
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf16 Dec 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 (2).pdf16 Dec 2021
Proforma of Allotment letterFile: Pristine Palazzo Agreement to Sale.pdf16 Dec 2021
Proforma of Allotment letterFile: Allotment Letter Palazzo.pdf16 Dec 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf7 Dec 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf7 Dec 2021
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf8 Nov 2021
Building plan approvalFile: PLAN 2.pdf8 Nov 2021
Building plan approvalFile: PLAN 3.pdf8 Nov 2021
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf8 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN 2.pdf8 Nov 2021
Building Plan Approval / NA Order for plotted developmentFile: PLAN 3.pdf8 Nov 2021
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf8 Nov 2021

How this compares with Pune

26%of Pune projects moved their completion datethis one has not
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PRISTINE PALAZZO on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Punawale13,700+ in Pune

2 kmPRISTINE PALAZZOCompleted 94Lapsed / revoked 35Other 118Dot size: filed unitsN

Filed coordinates, straight-line distance. 247 registered projects within 2 km.

Builder: KANHA DEVELOPERS

KANHA DEVELOPERS has 5 registrations on MahaRERA, including KANHA PLATINUM and PRISTINE PALAZZO. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if PRISTINE PALAZZO is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PRISTINE PALAZZO?

The registered promoter entity is KANHA DEVELOPERS, a partnership as per the filing. Its GSTIN 27AAWFK5031H1Z1 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PRISTINE PALAZZO?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for PRISTINE PALAZZO?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PRISTINE PALAZZO?

The professionals named in the filing: Architect: JAY AERAM; Engineer: Santosh Beknalkar; Engineer: SK Consultants & Builders; Engineer: STS Consultants LLP; Chartered Accountant: RSMS and Associates; Chartered Accountant: Rutuja Narsingh & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PRISTINE PALAZZO?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PRISTINE PALAZZO. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PRISTINE PALAZZO to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.