ReraGenieLog inGet a buyer report

Home / Browse projects / Thane, Maharashtra / Pearl B

Completed No litigation declared Residential / Group Housing project

Pearl B

By MACROTECH DEVELOPERS LIMITED

RG-MH-66331 · RERA P51700048930 · Last updated on MahaRERA portal: 24 Jan 2025

Source: official MahaRERA filing

Red flags

  • 1 complaint at MahaRERA

Clear

  • No litigation declared
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA
  • All 1 earlier projects delivered on promise

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jul 2026Possession promisedregistration recorded completed
2 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
1Complaints at MahaRERAon this registration
Jump to the 56 documents Report an error

Pearl B is a Residential / Group Housing project by MACROTECH DEVELOPERS LIMITED in Thane, Maharashtra, registered with MahaRERA as P51700048930 on 24 Jan 2023. The registration is recorded completed; possession was promised by 31 Jul 2026. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePearl B
  • TypeResidential / Group Housing
  • Location
    • Khoni Street
    • Khoni
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700048930
  • ReraGenie IDRG-MH-66331

Builder

  • NameMACROTECH DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • ChairpersonsRAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA, RAJENDRA LODHA and 1 more
  • Other registrations140 more →
  • Completed126 of 141
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredJan 2023PromisedJul 2026Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on24 Jan 2023
  • Promised completion31 Jul 2026
  • Revised completionNone
  • Buildings1 building record
  • Documents filed56 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing G of Cluster 10 Point 03NA140000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jan 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

2 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

Wing G of Cluster 10 Point 03: 53% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises75%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%

Progress on shared amenities16

As on 24 Jan 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes80%
Water SupplyYes80%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes80%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes60%
Street LightingYes40%
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes50%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes50%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes80%
Open ParkingYes80%
Closed ParkingYes15%

Parking filed307

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots307
Closed/Covered307

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,974 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI12145.09
Proposed, not sanctioned12,145 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchFort Mumbai

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVilas Desai & Associate
EngineerK C Shah Consultants
Chartered AccountantChirag Sarvaiya & Co
PartnerRole in project
LODHA DEVELOPERS LIMITED-

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC12500895RAVINDRA RAMCHANDRA KALESHMACROTECH DEVELOPERS LIMITED14/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Oct 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 18 Jan 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Feb 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 17 Feb 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 31 Dec 2024

Documents filed56

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B.pdf24 Jan 2025
Architect’s Certificate on Completion of Project (Form 4)File: Pearl B - Form4.pdf31 Dec 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Pearl B - Full OC.pdf31 Dec 2024
Disclosure of sold/ booked inventoryFile: Signed Sold Unsold Pearl B Sep 2024.pdf26 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Form 3 Pearl B Sep 2024.pdf24 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Signed Form 2 Pearl B Sep 2024.pdf24 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B.pdf4 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: P51700048930 - Pearl B.pdf19 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Pearl B - P51700048930.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B - P51700048930 - June24.pdf10 Aug 2024
Disclosure of sold/ booked inventoryFile: Pearl B - P51700048930 - June24.pdf7 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Pearl B - P51700048930 - March 24.pdf28 May 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - Pearl B - P51700048930 - March 24.pdf7 May 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold - Pearl B - P51700048930 - Dec23.pdf27 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form1 - Pearl B - P51700048930 - Dec23.pdf26 Feb 2024
Disclosure of sold/ booked inventoryFile: Pearl B - Sold Unsold - Sep23.pdf23 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B - Form1 - Sep23 - 2.pdf21 Nov 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B - June23 - Form1.pdf1 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Pearl B.pdf16 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Pearl B.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Pearl B.pdf21 Sep 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pear B - Form3-annexure - March23.pdf21 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Pearl B - Form1 - March23.pdf20 Sep 2023
Disclosure of sold/ booked inventoryFile: Pearl B - March23.pdf24 Jul 2023
Disclosure of sold/ booked inventoryFile: Pearl B - June23.pdf24 Jul 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl - Form3.pdf24 Jul 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 9 Pearel B.pdf26 Apr 2023
Building plan approvalFile: Pearl B_compressed.pdf17 Feb 2023
Building Plan Approval / NA Order for plotted developmentFile: Pearl B_compressed.pdf17 Feb 2023
Commencement Certificates / NA Order for plotted developmentFile: New CC.pdf17 Feb 2023
Building plan approvalFile: Building Layout 2 (3).pdf18 Jan 2023
Layout approvalFile: Layout for Upload.pdf18 Jan 2023
Layout approvalFile: New Layout.pdf18 Jan 2023
Copy of Layout Approval (in case of layout)File: Layout for Upload.pdf18 Jan 2023
Copy of Layout Approval (in case of layout)File: New Layout.pdf18 Jan 2023
Building Plan Approval / NA Order for plotted developmentFile: Building Layout 2 (3).pdf18 Jan 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: AML.PDF10 Jan 2023
Other - TechnicalFile: Building Declaration.pdf10 Jan 2023
CERSAI detailsFile: CERSAI 2.pdf23 Nov 2022
Deviation Report with respect to Allotment letterFile: New Allotment Deviation.pdf21 Nov 2022
Deviation Report with respect to model copy of AgreementFile: New AFS Deviation.pdf21 Nov 2022
Proforma of Allotment letterFile: Allotment letter Uploaded -Final.pdf18 Nov 2022
Proforma of Agreement for saleFile: NEW AFS For Residential.pdf18 Nov 2022
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Bank Declaration.pdf4 Nov 2022
Building plan approvalFile: Building Layout 1.pdf31 Oct 2022
Details of encumbrances concerned to FinanceFile: Fina Encum-Latest.pdf31 Oct 2022
Details of encumbrances concerned to FinanceFile: Encumbrances of Concern to Legal-No Litigation.pdf31 Oct 2022
Details of encumbrances concerned to LegalFile: Fina Encum-Latest.pdf31 Oct 2022
Details of encumbrances concerned to LegalFile: Encumbrances of Concern to Legal-No Litigation.pdf31 Oct 2022
Building Plan Approval / NA Order for plotted developmentFile: Building Layout 1.pdf31 Oct 2022
Declaration about Commencement CertificateFile: CC Decl Latest.pdf31 Oct 2022
PAN CardFile: Macrotech Developers Ltd PAN CARD.pdf18 Oct 2022
Copy of the legal title reportFile: Legal Report on Title-Lodha Crown Taloja.pdf18 Oct 2022
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf18 Oct 2022
Declaration in FORM BFile: Form B.pdf18 Oct 2022
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Pearl B -Form 3.pdf18 Oct 2022

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
LODHA PARKP51900001339.2,210Jul 2017CompletedDec 2023Registered original: Dec 2021Feb 2022

How this compares with Thane

24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is completed

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Pearl B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Khoni7,600+ in Thane

Builder: MACROTECH DEVELOPERS LIMITED

Macrotech Developers Limited has 141 registrations on MahaRERA, including LODHA BELMONDO ASHBRIDGE D, E and LODHA BELMONDO AUGUSTA B. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Pearl B is delayed beyond 31 Jul 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Pearl B?

The registered promoter entity is MACROTECH DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Pearl B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Pearl B?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Pearl B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Pearl B?

The professionals named in the filing: Architect: Vilas Desai & Associate; Engineer: K C Shah Consultants; Chartered Accountant: Chirag Sarvaiya & Co. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Pearl B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Pearl B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Pearl B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.