Runwal Gardens Phase I
By Runwal Residency Private Limited
RG-MH-14458 · RERA P51700022699 · Last updated on MahaRERA portal: 20 Oct 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 16 months past the filed date
- 12 complaints at MahaRERA
- Completion date moved by 12 months
- 1 extension taken
- Rs 525.00 crore secured on the land, in favour of ICICI Bank Ltd
Clear
- No litigation declared
- Separate project account declared
- Allotment letter follows the model form
6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Runwal Gardens Phase I is a Residential / Group Housing project by Runwal Residency Private Limited in Thane, Maharashtra, registered with MahaRERA as P51700022699 on 12 Oct 2019. Possession was promised by 30 Jun 2025 and is now 16 months past that date. The completion date has moved by 12 months from the original filing. 1,881 of the 1,937 units on this registration are recorded sold or booked, and 130 of 143 construction stages are filed complete. 12 complaints are on record with the regulator.
At a glance
Project
- NameRunwal Gardens Phase I
- TypeResidential / Group Housing
- Location
- Village Gharivali usarghar and Sagoan
- Dombivli
- Kalyan
- Thane
- 421204
- Pincode421204
- RERA no.P51700022699
- ReraGenie IDRG-MH-14458
Builder
- NameRunwal Residency Private Limited
- Entity typeCompany
- CINU45400MH2011PTC212140
- CIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
- DirectorsVijay Kisan Patil, Lucy Roychoudhury
- Other registrations17 more →
- Completed3 of 18
- No longer live5 lapsed, de-registered or revoked
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on12 Oct 2019
- Promised completion30 Jun 2025
- Revised completionRevised to 30 Jun 2025 (originally 30 Jun 2024)
- Buildings13 building records
- Documents filed404 files
Current status
Figures as on 20 Oct 2025, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Building No 2 | NA | 25 | 23 | 134 | 0 | 134 |
| Building No 3 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 4 | NA | 25 | 23 | 134 | 0 | 134 |
| Building No 5 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 6 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 7 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 8 | NA | 25 | 23 | 134 | 0 | 134 |
| Building No 9 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 10 | NA | 25 | 23 | 134 | 0 | 134 |
| Building No 11 | NA | 25 | 23 | 179 | 0 | 179 |
| Building No 12 | NA | 25 | 23 | 134 | 0 | 134 |
| Commercial Building MLCP 1 | NA | 22 | 20 | 0 | 14 | 14 |
| Building No 1 | NA | 25 | 23 | 179 | 0 | 179 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building13
As on 20 Oct 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
130 of 143 construction stages are filed complete across 13 buildings. The stage furthest along is Podiums (if any), at 0%.
Building No 291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 391%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 491%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 591%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 691%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 791%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 891%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 991%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 1091%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 1191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 1291%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Commercial Building MLCP 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Building No 191%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 100% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 100% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 100% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 100% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 100% |
Progress on shared amenities31
As on 20 Oct 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 100% |
| Water Supply | Yes | 100% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 100% |
| Storm Water Drains | Yes | 100% |
| Landscaping & Tree Planting | Yes | 100% |
| Street Lighting | Yes | 100% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 100% |
| Solid Waste Management And Disposal | Yes | 100% |
| Water conservation /Rain water harvesting | Yes | 100% |
| Energy managemcnt | Yes | 100% |
| Fire protection and fire safety requirements | Yes | 100% |
| Electrical meter room, sub-station, receiving station | Yes | 100% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 100% |
| Yoga zone | Yes | 100% |
| Amphitheatre | Yes | 100% |
| Basketball court | Yes | 100% |
| Common Parking | Yes | 100% |
| DG backup for common area | Yes | 100% |
| Doodle corner | No | Not applicable |
| Double height entrance lobby | Yes | 100% |
| Temple | Yes | 100% |
| Senior citizen sitting area | Yes | 100% |
| Outdoor gym | Yes | 100% |
| Multipurpose court | Yes | 100% |
| Kids play area | Yes | 100% |
| Jogging track | Yes | 100% |
| Herb garden | Yes | 100% |
| Hammock garden | Yes | 100% |
| Elevators of reputed brand | Yes | 100% |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners14
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Ar. Sandeep Prabhu for SAAKAAR |
| Architect | Precise architects and consultants |
| Architect | SAAKAR ARCHITECTS |
| Architect | Sakar Architects |
| Engineer | Chetan Sampat |
| Engineer | Uttam Kawathankar |
| Engineer | SHAILESH MAHIMTURA |
| Engineer | SAAKAR ARCHITECTS |
| Chartered Accountant | Bhatter & Company Chartered Accountants |
| Chartered Accountant | kshirsagar and associates |
| Chartered Accountant | SINGHI AND CO |
| Chartered Accountant | M B AGARWAL AND CO |
| Partner | Role in project |
|---|---|
| Runwal Residency Private Limited | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoter1. I, Saurabh Natu duly authorised by Runwal Residency Private Limited, Promoter of the project “Runwal Gardens Phase I” registered with MahaRERA under project registration number P51700022699 (hereinafter referred to as the “said Project”), state on behalf of the Promoters as under; 2. We state that the project registration validity of the said Project is due to expire on 30th June 2024. 3. We state that Runwal Gardens Phase I comprises of 12 residential buildings and one Multi-Level Car Parking building with shops at ground floor ("MLCP1"). Till date we have received occupation certificates
Complaints filed with MahaRERA12
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC006000000199336 | MOHAMMAD AYUB SHAIKH | Runwal Residency Pvt Ltd. | 20/05/2022 |
| CC006000000344267 | Runwal Residency Private Limited | Rajesh Yograj Sharma | 14/02/2023 |
| CC006000000334082 | Vikas Devidas Gudadhe | Runwal Residency private limited | 23/01/2023 |
| CC006000000396913 | Uma Sonappa Nandrankar | Runwal Residencey Pvt. Ltd | 02/08/2023 |
| CC006000000397663 | Satish Haribhau Wagh | Runwal Residency Private Limited | 01/10/2023 |
| CC006000000429254 | SANTOSH RAMCHANDRA KALE | Runwal Residency Pvt. Ltd. | 20/02/2024 |
| CC006000000591059 | Manoj Manohar Gokhale | Runwal Residency Pvt Ltd | 08/07/2024 |
| CC12500786 | Santosh Sitaram Gupta | Runwal Residency Private Limited | 07/03/2025 |
| CC12501006 | Santosh Sitaram Gupta | Runwal Residency Private Limited | 22/03/2025 |
| CC12502963 | Runwal Residency Private Limited | Sandeep Patil | 22/08/2025 |
| CC12601112 | MOHAMMAD AYUB SHAIKH | Runwal Residency Private Limited | 01/03/2026 |
| CC12603865 | Runwal Residency Private Limited | PRAVIN VINOD NIKAM | 22/06/2026 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 17 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 12 Jul 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Oct 2022 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 15 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 15 Jun 2024
Documents filed404
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 404 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 2A (FY 2024-2025)File: Form 2A Phase 1 Final.pdf | 20 Oct 2025 |
| Form 5 (FY 2024-2025)File: RRPL T1-12.pdf | 20 Oct 2025 |
| Form 1File: Form 1 T1 T12 MLCP 1 June 25.pdf | 12 Aug 2025 |
| Form 2File: PH1 T1 to T12 RERA FORM 2 30 06 2025.pdf | 12 Aug 2025 |
| Form 3File: Form 3 Phase 1 Tower 1 to 12.pdf | 12 Aug 2025 |
| Disclosure of Sold and Booked InventoryFile: Runwal Gardens Phase 1.pdf | 12 Aug 2025 |
| Self-declaration of Quarterly ProgressFile: Declaration for Compliance RRPL.pdf | 12 Aug 2025 |
| Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase I.pdf | 3 May 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 1 Tower 1 to 12.pdf | 2 May 2025 |
| Form 1 T1 T12 and MLCP 1 25 04 25 | 29 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH1 T1 to T12 RERA FORM 2 ENGINEERS CERTIIFICATE.pdf | 18 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 1 Tower 1 to 12-1.pdf | 12 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase I.pdf | 31 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase I.pdf | 31 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Done PH1 T1 to T12 RERA FORM 2 ENGINEERS CERTIIFICATE.pdf | 30 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH1 T1 to T12 RERA FORM 2 ENGINEERS CERTIIFICATE 30-09-2024.pdf | 22 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -T1 - T12 - MLCP-1 - Sept 2024 FINAL.pdf | 21 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Runwal Gardens Phase I.pdf | 21 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 1 Tower 1 to 12.pdf | 18 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RRPL TOWER 1-12 Form-5 FY 23-24_signed.pdf | 7 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: RRPL TOWER 1-12 Form-5 FY 23-24_signed.pdf | 7 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 T1 T12 MLCP.pdf | 25 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: PH1 T1 to T12 FORM 2.pdf | 18 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Phase 1 Tower 1 to 12.pdf | 18 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A -2022-23.pdf | 28 Jun 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - 2023-24.pdf | 28 Jun 2024 |
| Declaration in FORM BFile: Form B.pdf | 27 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: Building number 3 11 12 OC.pdf | 15 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Building number 3 11 12 OC.pdf | 15 Jun 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: MLCP 1 shops OC.pdf | 15 Jun 2024 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold Inventory - Phase 1 compressed.pdf | 14 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 1-12 MLCP1 - March 24.pdf | 2 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Phase 1 T 1 to T 12.pdf | 18 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 1-12.pdf | 17 Apr 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: 1-6.pdf | 1 Feb 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: 7-12.pdf | 1 Feb 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Application for registration of society.pdf | 31 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 1-12 MLCP.pdf | 23 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Tower 1-12.pdf | 20 Jan 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Tower 1-12.pdf | 19 Jan 2024 |
| Other - FinanceFile: Details of encumbrances for all projects.pdf | 16 Jan 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: runwal garden tower 1 to 6.pdf | 10 Jan 2024 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: runwal garden tower 7 to 12.pdf | 10 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf | 8 Dec 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: TOWER 1 TO 6 SOCIETY.pdf | 21 Nov 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: TOWER 7 TO 12 SOCEITY.pdf | 21 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1-12.pdf | 21 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: T1-T12.pdf | 21 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1-12.pdf | 20 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Tower 1-12 Form 5 FY 2022-23-min.pdf | 30 Sep 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Tower 1-12 Form 5 FY 2022-23-min.pdf | 30 Sep 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Name Reservation Certificate of RG T1-6.pdf | 24 Jul 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Name Reservation Certificate of RG T7-12.pdf | 24 Jul 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 - 1 to 12.pdf | 21 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1-12.pdf | 21 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 1-12.pdf | 24 Jun 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 T1-12.pdf | 24 Jun 2023 |
| Other - FinanceFile: Encumbrances Certificate - Finance.pdf | 22 Jun 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Runwal Gardens - Form 1 - Tower 1 to 12.pdf | 28 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: INVENTORY - 1.pdf | 22 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2 BLDG NO 1 TO 12_compressed.pdf | 21 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3 PHASE 1_compressed.pdf | 21 Apr 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A BLDG-1-12.pdf | 17 Apr 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: Runwal Name Registation - Phase 1 Tower 1 to 12.pdf | 12 Apr 2023 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: phase 1 - BUILDING NO 5 - 6 AND 9.pdf | 30 Mar 2023 |
| Status of Formation of Legal Entity (Society/Co Op etc.)File: PHASE 1_compressed.pdf | 28 Feb 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: phase 1 21-22.pdf | 1 Dec 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Phase_1(19-20).pdf | 9 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Phase_1(19-20).pdf | 9 Nov 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Phase_1(20-21).pdf | 9 Nov 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTS CERTIFICATE PHASE 1_compressed.pdf | 22 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineering Certificate phase 1_compressed.pdf | 22 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Runwal Gardens Phase 1_compressed.pdf | 22 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_28.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_26.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_27.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_1.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_1.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_1.pdf | 21 Oct 2022 |
| Building plan approvalFile: Phase -1 OC B-2,4,7,8,10 Plans 11 October 2022_2.pdf | 21 Oct 2022 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 6 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 17 other registrations, which the RERA portal never shows together
- All 404 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep Runwal Gardens Phase I on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Dombivli7,600+ in Thane
Constrcution of 2557 EWS tenements at S.No.157
ARUN SHANKARRAO BORGAVE
Runwal Garden City Cluster 6 Tower 6 to 9
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 6A Bldg No. 53-54
Runwal Residency Private Limited
RGC Runwal My City EWS - LIG Building
HORIZON PROJECTS PVT LTD
BALAJI ESTATE PHASE 2
M/S SAI BALAJI BUILDCON
Runwal Gardens Phase 2 Bldg no 13-17
Runwal Residency Private Limited
See every Thane project, with the district possession charts
Builder: Runwal Residency Private Limited
Runwal Residency Private Limited has 18 registrations on MahaRERA, including Runwal Gardens Phase I and Runwal Gardens Phase 2 Bldg no 18-23. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What does it mean that Runwal Gardens Phase I shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Runwal Gardens Phase I is delayed beyond 30 Jun 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Runwal Gardens Phase I?
The registered promoter entity is Runwal Residency Private Limited, a company as per the filing. Its CIN U45400MH2011PTC212140 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Runwal Gardens Phase I?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Runwal Gardens Phase I?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Runwal Gardens Phase I?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Runwal Gardens Phase I?
The professionals named in the filing: Architect: Ar. Sandeep Prabhu for SAAKAAR; Architect: Precise architects and consultants; Architect: SAAKAR ARCHITECTS; Architect: Sakar Architects; Engineer: Chetan Sampat; Engineer: Uttam Kawathankar. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Runwal Gardens Phase I?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.