Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project
RG-MH-29208 · RERA P51700029534 · Last updated on MahaRERA portal: 1 Dec 2023
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Completion date moved by 63 months
- 1 extension taken
Clear
- No litigation declared
- No complaints on record
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project is a Residential / Group Housing project by ARUN SHANKARRAO BORGAVE in Thane, Maharashtra, registered with MahaRERA as P51700029534 on 4 Jun 2021. Possession is promised by 6 Jun 2028. The completion date has moved by 63 months from the original filing. 0 of the 2,591 units on this registration are recorded sold or booked, and 5 of 88 construction stages are filed complete.
At a glance
Project
- NameConstrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project
- TypeResidential / Group Housing
- Location
- NEAR PANVEL MUMBRA HIGHWAY
- NEAR MSETCL RECIEVING STATION
- UTTARSHIV VILLAGE ROAD
- Goteghar
- Thane
- 421204
- Pincode421204
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51700029534
- ReraGenie IDRG-MH-29208
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on4 Jun 2021
- Promised completion6 Jun 2028
- Revised completionRevised to 6 Jun 2028 (originally 8 Mar 2023)
- Buildings8 building records
- Documents filed24 files
Current status
Figures as on 1 Dec 2023, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| 1 | NA | 30 | 16 | 480 | 0 | 480 |
| 2 | NA | 15 | 15 | 240 | 0 | 240 |
| 3 | NA | 15 | 15 | 240 | 0 | 240 |
| 4 | NA | 15 | 15 | 240 | 0 | 240 |
| 5 | NA | 16 | 15 | 288 | 0 | 288 |
| 6 | NA | 30 | 30 | 480 | 0 | 480 |
| 7 | NA | 31 | 31 | 432 | 0 | 432 |
| 8 | NA | 16 | 16 | 191 | 0 | 191 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building8
As on 1 Dec 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 88 construction stages are filed complete across 8 buildings. The stage furthest along is Basement (if any), at 80%.
127%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
29%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
30%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
40%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
50%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
624%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 80% |
| Podiums (if any) | 0% |
| Plinth | 80% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
70%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
80%
| Activity | Progress |
|---|---|
| Excavation | 0% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Dec 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | Yes | 0% |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed704
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Open Space | Total |
|---|---|---|
| 1 | 130 | 130 |
| 2 | 66 | 66 |
| 3 | 65 | 65 |
| 4 | 65 | 65 |
| 5 | 78 | 78 |
| 6 | 130 | 130 |
| 7 | 117 | 117 |
| 8 | 53 | 53 |
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| MHADA | Andheri | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | N R Pradhan |
| Architect | ANILKUMAR SHARMA R SHARMA |
| Engineer | A S Borgave |
| Chartered Accountant | N P Lavale |
| Chartered Accountant | Shushma Patil |
| Partner | Role in project |
|---|---|
| Maharashtra Housing and Area Development Board Konkan | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe work of Phase 1 is almost completed and for phase II is in progress. the delay fir the building to be completed are due to various reasons, since to worldwide out break of Covid -19, countrywide lock down declared by Govt. of India for almost more than 2 years, during this epidemic period reverse migration of labour took place to their native places, shortage of construction material with supply chain of construction material was totally disturb and hampered to a very large extend which had adversely affected the construction activities severely and work could not be completed in timebound
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 5 Mar 2021 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 5 Mar 2021 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 5 Mar 2021 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 5 Mar 2021Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 6 Jun 2028
Documents filed24
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: form 2A.pdf | 1 Dec 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: 2A 20- 21.pdf | 25 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: 2A 21- 22.pdf | 25 Nov 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 2A 22 -23.pdf | 25 Nov 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate form 2.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: Annexure F FORM 5 RERA 2022 to 2023.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Annexure F FORM 5 RERA 2019 to 2020_page-0001.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Annexure F FORM 5 RERA 2019 to 2020_page-0001.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Annexure F FORM 5 RERA 2020 to 2021_page-0001.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Annexure F FORM 5 RERA 2022 to 2023.pdf | 11 Nov 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Annexure F FORM 5 RERA 2022 to 2023.pdf | 11 Nov 2023 |
| Building plan approvalFile: IOA-compressed.pdf | 5 Mar 2021 |
| Layout approvalFile: LAYOUT APPROVAL.pdf | 5 Mar 2021 |
| PAN CardFile: Pan Card.pdf | 5 Mar 2021 |
| Copy of the legal title reportFile: land title.pdf | 5 Mar 2021 |
| Details of encumbrancesFile: Non encumbrance.pdf | 5 Mar 2021 |
| Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf | 5 Mar 2021 |
| Building Plan Approval / NA Order for plotted developmentFile: IOA-compressed.pdf | 5 Mar 2021 |
| Commencement Certificates / NA Order for plotted developmentFile: CC.pdf | 5 Mar 2021 |
| Declaration in FORM BFile: Form B.pdf | 5 Mar 2021 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Arch Cert.pdf | 5 Mar 2021 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engineer cert.pdf | 5 Mar 2021 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate.pdf | 5 Mar 2021 |
| Proforma of Allotment letterFile: Allotment Letter compressed.pdf | 5 Mar 2021 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|
| 1771 EWS and 88 LIG tenements at Survey no.13, Bhandarli, Tal. Dist. Thane PMAY projectP51700024403 | Bhandarli, Thane | Feb 2020 | Certificate Signed | Mar 2024Registered original: Mar 2023 | Late, Nov 2024 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Thane
Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.
Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 2 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 1 other registration and every project registered within 2 km, which the RERA portal never shows together
- All 24 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Constrcution of 2557 EWS tenements at S.No.1 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near NEAR MSETCL RECIEVING STATION,UTTARSHIV VILLAGE ROAD7,600+ in Thane
Filed coordinates, straight-line distance. 21 registered projects within 2 km.
Runwal Gardens Phase I
Runwal Residency Private Limited
Runwal Garden City Cluster 6 Tower 6 to 9
HORIZON PROJECTS PVT LTD
Runwal Gardens Phase 6A Bldg No. 53-54
Runwal Residency Private Limited
RGC Runwal My City EWS - LIG Building
HORIZON PROJECTS PVT LTD
BALAJI ESTATE PHASE 2
M/S SAI BALAJI BUILDCON
Runwal Gardens Phase 2 Bldg no 13-17
Runwal Residency Private Limited
See every Thane project, with the district possession charts
Builder: ARUN SHANKARRAO BORGAVE
ARUN SHANKARRAO BORGAVE has 2 registrations on MahaRERA, including Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project and Construction of 328 EWS t/s S.No. 392 pt village bolinj Tal - Vasai Dist - Palghar - PMAY. Its filings disclose 1 earlier MahaRERA project: declares 0 of 1 past projects completed on time. Read the full track record. See more projects on the Thane district page.
Frequently asked questions
What are my rights if Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project is delayed beyond 6 Jun 2028?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project?
The registered promoter entity is ARUN SHANKARRAO BORGAVE, an individual as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project?
The professionals named in the filing: Architect: N R Pradhan; Architect: ANILKUMAR SHARMA R SHARMA; Engineer: A S Borgave; Chartered Accountant: N P Lavale; Chartered Accountant: Shushma Patil. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Constrcution of 2557 EWS tenements at S.No.157/1,village Gotheghar,Tal . Dist.-Thane PMAY Project?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback