Home / Browse projects / Thane, Maharashtra / Runwal Garden City Cluster 6 Tower 6 to 9

Registered Litigation declared Residential / Group Housing project

Runwal Garden City Cluster 6 Tower 6 to 9

By HORIZON PROJECTS PVT LTD

RG-MH-06444 · RERA P51700052561 · Last updated on MahaRERA portal: 18 Jul 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 4 cases
  • Completion date moved by 22 months
  • 1 extension taken
  • Rs 740.15 crore secured on the land, in favour of ICICI BANK LTD

Clear

  • No complaints on record
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Mar 2029Possession promisedmoved 22 months from the original
13 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 87%
843 of 1,186Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 139 documents Report an error

Runwal Garden City Cluster 6 Tower 6 to 9 is a Residential / Group Housing project by HORIZON PROJECTS PVT LTD in Thane, Maharashtra, registered with MahaRERA as P51700052561 on 11 Sep 2023. Possession is promised by 31 Mar 2029. The completion date has moved by 22 months from the original filing. 343 of the 1,186 units on this registration are recorded sold or booked, and 13 of 44 construction stages are filed complete.

At a glance

Project

  • NameRunwal Garden City Cluster 6 Tower 6 to 9
  • TypeResidential / Group Housing
  • Location
    • Diva Manpada Road
    • Dombivali
    • Usarghar
    • Kalyan
    • Thane
    • 421204
  • Pincode421204
  • RERA no.P51700052561
  • ReraGenie IDRG-MH-06444

Builder

  • NameHORIZON PROJECTS PVT LTD
  • Entity typeCompany
  • CINU45400MH2011PTC213029
  • GSTIN27AAFCR1404F1ZS
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsSaurabh Natu, Deepak Lohia, Sameer Parasmal Nahar, Saurabh Natu, Sameer Parasmal Nahar, Saurabh Natu
  • Other registrations9 more →
  • Completed4 of 10
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredSep 2023First promiseMay 2027Revised toMar 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Sep 2023
  • Promised completion31 Mar 2029
  • Revised completionRevised to 31 Mar 2029 (originally 31 May 2027)
  • Buildings4 building records
  • Documents filed139 files

Current status

29%343 of 1,186 units booked
16.5%Work done, per cost certificate

Figures as on 18 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 6NA39333030303
Tower 7NA39333030303
Tower 8NA34333230323
Tower 9NA34332570257

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 18 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

13 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 87%.

Tower 630%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)25%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 735%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)87%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 832%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor38%
Slabs of Super Structure8%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises5%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Tower 940%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure35%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 18 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes0%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area2,612 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofICICI BANK LTD
Secured amountRs 740.15 crore
CERSAI search filedYes
Declared on1 Oct 2025

Approvals and building plan

Sanctioning authorityMMRDA
Permissible FSI88435.68
Proposed, not sanctioned83,436 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchShop 9,10 Mary Land Corner Near Sion Circle Mumbai 400022
Estimated costRs 372.21 cr
Cost incurredRs 61.32 cr
Work done16.47%
BuildingWingEstimatedIncurred
Tower 6NARs 83.39 crRs 7.51 cr
Tower 8NARs 81.23 crRs 18.36 cr
Tower 7NARs 79.06 crRs 9.53 cr
Tower 9NARs 74.10 crRs 20.93 cr
-NARs 54.43 crRs 4.99 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSakaar Architect
EngineerAtul Waman Bapat
EngineerUTTAM KAWATHANKAR
Chartered AccountantKshirsagar and Associates
Chartered AccountantM B Agrawal and CO
PartnerRole in project
HORIZON PROJECTS PVT LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA04052620819May 2027 → Mar 2029

Reason as filed by the promoterThe delay in the completion of the project primarily occurred due to the encounter of unexpected hard rock strata during the excavation and foundation stage, which necessitated specialized, time consuming rock-breaking techniques and caused an initial setback of approximately five months. Furthermore, progress was severely disrupted by the continued non-performance of the initial RCC contractor, Vira Buildtech Pvt Ltd, whose repeated failure to provide adequate labor and essential materials led to their termination in March 2026 and a subsequent transition period to mobilize a new contractor.

Litigation declared4

CaseCourtStatus
3771/2018Bombay High CourtAdmission
1148/2016Bombay High CourtFor hearing of NM
9701/2011Bombay High CourtPre Admission
534/2022Additional Commissioner Konkan DivisionHearing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 8 Aug 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 7 Aug 2023
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2023
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 3 Aug 2023Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Mar 2029

Documents filed139

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 139 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 1 - CL06 T6 to 9 compressed.pdf18 Jul 2026
Withdrawal Update Form 2File: FORM 2 - CL06 T6 to 9.pdf18 Jul 2026
Withdrawal Update Form 3File: Form 3 - Cluster 6.pdf18 Jul 2026
Form 2A (FY 2025-2026)File: FORM 2A 2025-26.pdf15 Jul 2026
Withdrawal Update Form 1File: CL-6 FORM 1.pdf20 Apr 2026
Withdrawal Update Form 2File: ENGINEER CERTIFICATE _CLUSTER_6.pdf20 Apr 2026
Withdrawal Update Form 3File: Form 3 - Cluster 6.pdf20 Apr 2026
Withdrawal Update Form 1File: FORM 1 CLUSTER 6 6 TO 9 DEC 25 compressed.pdf20 Jan 2026
Withdrawal Update Form 2File: ENGINEERS CERTIFICATE CLUSTER 6 P 130122025.pdf20 Jan 2026
Withdrawal Update Form 3File: Form 3 - Cluster 6.pdf20 Jan 2026
Withdrawal Update Form 1File: CL 6 TOWER 6 to 9 30 09 25.pdf19 Oct 2025
Withdrawal Update Form 2File: ENGINEERu0027S CERTIFICATE _CLUSTER_6_ P1_30.09.2025..pdf19 Oct 2025
Withdrawal Update Form 3File: Form 3 - Cluster 6.pdf19 Oct 2025
Form 2A (FY 2024-2025)File: Form 2A_CL06 T6 To 9.pdf18 Oct 2025
Form 5 (FY 2024-2025)File: HPPL Form 5_cluster 6 signed.pdf18 Oct 2025
Form 1File: Form 1 CL 6 TOWER 6 to 9.pdf13 Aug 2025
Form 2File: Form 2 CL06 T6-9.pdf13 Aug 2025
Form 3File: Form 3 Cluster 6.pdf13 Aug 2025
Disclosure of Sold and Booked InventoryFile: MY CITY- PHASE III -CLUSTER 06.pdf13 Aug 2025
Self-declaration of Quarterly ProgressFile: Declaration HPPL signed.pdf13 Aug 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CL6 TOWER 6 to 9 31st March 2025.pdf23 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE CLUSTER 6 P1 31st March 2025.pdf23 Apr 2025
Disclosure of sold/ booked inventoryFile: MY CITY PHASE III CLUSTER 06 Inventory Details.pdf23 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cluster 6.pdf18 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 Cluster 6 TOWER 6 to 9 31 dec 24.pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cluster 6 Tower 6 to 9 24 Jan 2025.pdf3 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE CLUSTER 6 Tower 6 to 9 Dec 2024.pdf3 Feb 2025
Disclosure of sold/ booked inventoryFile: MY CITY PHASE III CLUSTER 06.pdf1 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: ENGINEER'S CERTIFICATE _CLUSTER_6_ P1_Dec'2024.pdf30 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CLUSTER 6.pdf7 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: CLUSTER 6-rotated.pdf7 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A CLUSTER 6.pdf7 Nov 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: CLUSTER 6.pdf6 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Cluster 6.pdf29 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 3 - Cluster 6.pdf29 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A CLUSTER 6.pdf29 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: CLUSTER 6.pdf25 Oct 2024
Disclosure of sold/ booked inventoryFile: MY CITY- PHASE III -CLUSTER 06.pdf21 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: HPPL Form 5-CLUSTER 6 - 6 TO 9-signed.pdf9 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: HPPL Form 5-CLUSTER 6 - 6 TO 9.pdf8 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 TOWER 6 to 9.pdf25 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cluster 6 01.pdf22 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cluster 6 Tower 6 to 9.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cluster T6-T9.pdf23 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Cluster 6 - Tower 6 to 9.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Cl-06 Engineer's Certificate.pdf16 Feb 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Cluster 6 Tower 6 to 9.pdf2 Feb 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 -Cluster 6 - Tower 6 to 9.pdf22 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TOWER 6.pdf8 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TOWER 7.pdf8 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TOWER 8.pdf8 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: TOWER 9.pdf8 Dec 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 30 09 2023 Form 3 Cluster 6.pdf29 Nov 2023
Proforma of Agreement for saleFile: AFS Draft - Cluster 6 Tower 6 to 9 Final version .pdf31 Aug 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report_AFS Cluster 6.pdf31 Aug 2023
Copy of the legal title reportFile: MyCity Title Report - 5 August 2023_11zon.pdf8 Aug 2023
Deviation Report with respect to Allotment letterFile: Allotment Letter - Deviation Report.pdf8 Aug 2023
Layout approvalFile: HIGHLIGHTED PLINTH AREA.pdf7 Aug 2023
Layout approvalFile: HIGHLIGHTED BUILT UP AND PARKING.pdf7 Aug 2023
Copy of Layout Approval (in case of layout)File: HIGHLIGHTED PLINTH AREA.pdf7 Aug 2023
Copy of Layout Approval (in case of layout)File: HIGHLIGHTED BUILT UP AND PARKING.pdf7 Aug 2023
Declaration in FORM BFile: Form B.pdf7 Aug 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate 1 Aug 2023.pdf7 Aug 2023
Proforma of Allotment letterFile: Proforma Allotment Letter Cluster 6.pdf7 Aug 2023
Other - TechnicalFile: plinth area final merge document.pdf7 Aug 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Finance.pdf5 Aug 2023
Details of encumbrances concerned to FinanceFile: Details of encumbrances concerned to Legal.pdf5 Aug 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Finance.pdf5 Aug 2023
Details of encumbrances concerned to LegalFile: Details of encumbrances concerned to Legal.pdf5 Aug 2023
Declaration about Commencement CertificateFile: Form - D - DECLARATION ABOUT COMMENCEMNT CERTIFICATE.pdf5 Aug 2023
CERSAI detailsFile: CERSAI - Security Based Report Declaration.pdf5 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations - Deepak Lohia.pdf5 Aug 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: Disclosure of Interest in Other Real Estate Organizations - Saurabh Nattu.pdf5 Aug 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: DECLARATION OF SEPERATE ACCOUNT.pdf5 Aug 2023
Other - TechnicalFile: Consolidated Parking Declaration Cluster 6.pdf5 Aug 2023
Building plan approvalFile: Ground (Part) Area Calculations- Tower 7- Cluster 6.pdf3 Aug 2023
Building plan approvalFile: Ground floor Area calculations- Tower 8- Cluster 6.pdf3 Aug 2023
Building plan approvalFile: Ground floor line diagram with Shops- Cluster 6.pdf3 Aug 2023
Building plan approvalFile: Ground floor Parking Plan- Cluster 6 parking statment highlighted.pdf3 Aug 2023
Building plan approvalFile: Refuge Floors- Tower 6- Cluster 6.pdf3 Aug 2023

How this compares with Thane

29%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 22 months
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Runwal Garden City Cluster 6 Tower 6 to 9 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Dombivali7,600+ in Thane

Builder: HORIZON PROJECTS PVT LTD

HORIZON PROJECTS PVT LTD has 10 registrations on MahaRERA, including MY CITY - PHASE I - PART I and MY CITY - PHASE I - PART III. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if Runwal Garden City Cluster 6 Tower 6 to 9 is delayed beyond 31 Mar 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Runwal Garden City Cluster 6 Tower 6 to 9?

The registered promoter entity is HORIZON PROJECTS PVT LTD, a company as per the filing. Its CIN U45400MH2011PTC213029 and GSTIN 27AAFCR1404F1ZS can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Runwal Garden City Cluster 6 Tower 6 to 9?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Runwal Garden City Cluster 6 Tower 6 to 9?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Runwal Garden City Cluster 6 Tower 6 to 9?

The professionals named in the filing: Architect: Sakaar Architect; Engineer: Atul Waman Bapat; Engineer: UTTAM KAWATHANKAR; Chartered Accountant: Kshirsagar and Associates; Chartered Accountant: M B Agrawal and CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Runwal Garden City Cluster 6 Tower 6 to 9?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Runwal Garden City Cluster 6 Tower 6 to 9. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Runwal Garden City Cluster 6 Tower 6 to 9 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.