Completed No litigation declared Residential / Group Housing project

LODHA PARK

By MACROTECH DEVELOPERS LIMITED

RG-MH-11852 · RERA P51900001339 · Last updated on MahaRERA portal: 14 Jun 2024

Source: official MahaRERA filing

Red flags

  • 67 complaints at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2023Possession promisedregistration recorded completed
10 of 11Construction stages donefurthest along: Stilt Floor, 0%
67Complaints at MahaRERAon this registration
Jump to the 181 documents Report an error

LODHA PARK is a Residential / Group Housing project by MACROTECH DEVELOPERS LIMITED in ., 400013, registered with MahaRERA as P51900001339 on 27 Jul 2017. The registration is recorded completed; possession was promised by 30 Dec 2023. The completion date has moved by 24 months from the original filing. 67 complaints are on record with the regulator.

At a glance

Project

  • NameLODHA PARK
  • TypeResidential / Group Housing
  • Location
    • .
    • 400013
  • Pincode400013
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900001339
  • ReraGenie IDRG-MH-11852

Builder

  • NameMACROTECH DEVELOPERS LIMITED
  • Entity typeCompany
  • CINL45200MH1995PLC093041
  • GSTIN27AAACL1490J1ZG
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • ChairpersonsRAJENDRA NARPATMAL LODHA, RAJENDRA NARPATMAL LODHA
  • Other registrations140 more →
  • Completed126 of 141
  • No longer live13 lapsed, de-registered or revoked
  • Declared earlier projects6 →

Key dates

this monthRegisteredJul 2017First promiseDec 2021Revised toDec 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on27 Jul 2017
  • Promised completion30 Dec 2023
  • Revised completionRevised to 30 Dec 2023 (originally 31 Dec 2021)
  • Buildings1 building record
  • Documents filed181 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING 1 TO 5NA880000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 14 Jun 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 0%.

WING 1 TO 5: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities16

As on 14 Jun 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes97%
Water SupplyYes85%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes90%
Street LightingYes75%
Community BuildingsYes97%
Treatment And Disposal Of Sewage And Sullage WaterYes75%
Solid Waste Management And DisposalYes50%
Water conservation /Rain water harvestingYes65%
Energy managemcntYes65%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes75%
Closed ParkingsYes75%

Parking filed4389

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots4,389
Closed/Covered4,389

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area53,345 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI226345.75
Proposed, not sanctioned188,471 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchKamala Mill Compound Lower Parel Mumbai

Certifying professionals and partners

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

PartnerRole in project
LODHA DEVELOPERS LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51900003725Dec 2021 → Dec 2022

Reason as filed by the promoterReasons as mentioned in the attached self certified copy.

Complaints filed with MahaRERA67

Case no.ComplainantRespondentFiled
CC006000000078496Kandar ParikhLodha Developers Limited15/03/2019
CC006000000089625Katmandu Apparel Private LimitedLodha Developers Limited08/06/2019
CC006000000210229JOLLY MATHURMACROTECH DEVELOPERS LTD02/03/2022
CC006000000001533Kishor P. GadaJawala Real Estate Pvt. Ltd. through its director Ramanandam Omprakash Pandey30/10/2017
CC006000000022876Rajesh Padmasing SolankiJawala Real Estate Private Limited (Lodha Developers Private Limited)16/01/2018
CC006000000055262Abhishek GuptaLodha DEveloper09/08/2018
CC006000000057054Parikshit Ravindra KshirsagarLodha Developers30/11/2018
CC006000000078294TW Buildwell Pvt. Ltd.Lodha Developers Pvt. Ltd.07/03/2019
CC006000000058028Mr. Satish Dhondulal Parakh HUFM/s. Jawala Real Estate Pvt Ltd (Lodha Developers)11/02/2019
CC006000000058029Mrs. Asha Ashok KatariyaM/s. Jawala Real Estate Pvt Ltd12/02/2019
CC006000000182065HEMANG JAGDISH ENGINEERMACROTECH DEVELOPERS LTD09/01/2020
CC006000000090182Irving Fred DesousaLodha Developers Limited17/07/2019
CC006000000089763ANUBHAV JAINM/s Jawala Real Estate Pvt.Ltd. ( Lodha Developers Pvt.Ltd.)21/06/2019
CC006000000195903ANUBHAV JAINJawala Real Estate Pvt. Ltd. ( Lodha Developers Pvt Ltd.11/02/2021
CC006000000100425BHAGWAN H CHANDNANIMACROTECH DEVELOPERS LIMITED05/08/2019
CC006000000193952Arvind SubramanianMacrotech Developers Limited09/09/2020
CC006000000100470Pratap Singh BohraMacrotech Developers Limited13/08/2019
CC006000000100571Mrs. Krishna Deepak Wadhwani and Deepak Gobindram WadhwaniMacrotech DevelopersLimited25/11/2019
CC006000000110906Bhavesh BafnaMacrotech Developers pvt ltd15/09/2019
CC006000000120942SUDATTA PATILJAWALA REAL ESTATE PVT LTD18/09/2019
CC006000000141146Ms. Shelly AgarwalJawala Real Estate Private Ltd.03/10/2019
CC006000000141065Macrotech Developers LimitedAnita Hemraj Bora30/09/2019
CC006000000141148SAURABH JAINMACROTECH DEVELOPERS PVT.LTD. ( LODHA DEVELOPERS PVT.LTD.)03/10/2019
CC006000000171846Anita Hemraj BoraJawala Real Estate Private Limited13/12/2019
CC006000000171886Shiv Autoriders Private LImitedMACRTOTECH DEVELOPERS PRIVATE LIMITED (JAWALA REAL ESTATE PRIVATE LIMITED)26/12/2019
CC006000000192733Leela Buildcon & InfrastructureMacrotech Developers Limited27/02/2020
CC006000000192757Mr. Sunil SoodMacrotech Developers Limited20/06/2020
CC006000000193555Mr. Anirudh Lal & Mrs. Shailly Anirudh LalMacrotech Developers Limited24/07/2020
CC006000000192966MANJUSHA SUHAS NIRGUDKARMACROTECH DEVELOPERS LIMITED12/09/2020
CC006000000193296Ratan Kumar KandoiJawala Real Estate Pvt. Ltd.16/06/2020
CC006000000196547Savitri Devi ChowdharyMacmotech Developers Limited30/03/2021
CC006000000193337Bhavesh BafnaMessers Macrotech Developers Ltd24/06/2020
CC006000000193739Komalkant F SharmaMacrotech Developers Limited16/08/2020
CC006000000193791A Infrastructure LimitedMacrotech Developers Limited21/08/2020
CC006000000193793A Infrastructure LimitedMacrotech Developers Limited21/08/2020
CC006000000193830Ramakant V PaiMacrotech Developers Limited01/09/2020
CC006000000194865Axis Electrical Components (India) Pvt LtdJawala Real Estate Pvt Ltd19/11/2020
CC006000000195082Varshit Dinesh Jain, Dinesh M Jain and Hemlata D JainMacrotech Developers Limited01/12/2020
CC006000000195676MANISHA TULSIANIMACROTECH DEVELOPERS LIMITED18/01/2021
CC006000000198232M/S VSK DISTRIBUTORS PRIVATE LTDM/S MICROTECH DEVELOPERSLIMITED04/09/2021
CC006000000195884Mahendra Kalyanji Ghelani And Mina Mahendra GhelaniMacrotech Developers Pvt Ltd (formerly known as Jawala Real Estates Pvt. Ltd)05/02/2021
CC006000000196082Ghamsham Lalwani andMeher LalwaniMacrotech Developers Lts17/02/2021
CC006000000196605Pankaj C Jhaveri and Jesal P JhaveriMacrotech Developers Ltd03/04/2021
CC006000000196921Morries Realtors LLP (formerly Known as Morries Realtors Private Limited)Macrotech Developers Limited10/05/2021
CC006000000196932SURESH M RAMCHANDANILODHA DEVELOPERS08/05/2021
CC006000000197476Mrs. Surekha BodaMacrotech Developers Limited03/07/2021
CC006000000197477Mugatlal Bhagwandas Boda and Co. Pvt. Ltd.Macrotech Developers Limited03/07/2021
CC006000000198490Vibha Ashokkumar BorkarMacrotech Developers Ltd.28/09/2021
CC006000000198698Amitava MajumdarMacrotech Developers Limited18/10/2021
CC006000000198960Sasikumar KatamreddyMocrotechDevelopersLimited08/11/2021
CC006000000199107Avish Tekwani and Vivish TekwaniMacrotech Developers Ltd22/11/2021
CC006000000209997Bharat Kheria and Suresh Kumar KheriaMacrotech Developers Ltd.11/02/2022
CC006000000220668Rasseek Jivraj HariyaMacrotech Developers Limited02/04/2022
CC006000000251556Divyakumar Sunilkumar SiraslewalaMACROTECH DEVELOPERS LIMITED27/06/2022
CC006000000292442HEMANSHU CHOKHANIM/S. MACROTECH DEVELOPERS LIMITED24/08/2022
CC006000000292456SUNIL SHARMAMacrotech Developers Ltd25/08/2022
CC006000000303036ADVANCED MANAGEMENT SYSTEM P. LTD.Macrotech Developers Limited17/10/2022
CC006000000375212RONAKALI S DHOLKAWALA RONAK ROCKS PRIVATE LIMITEDMACROTECH DEVELOPERS LIMITED10/04/2023
CC006000000396407Allied Financial Services Pvt LtdMacrotech Developers Limited26/06/2023
CC006000000396431Allied Financial Services Pvt LtdMacrotech Developers Limited05/07/2023

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Apr 2018
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 14 Jun 2018
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Jul 2017
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 25 Jul 2022

Documents filed181

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 181 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Disclosure of sold/ booked inventoryFile: LODHA PARK - P51900001339 - March 24.pdf14 Jun 2024
Disclosure of sold/ booked inventoryFile: LODHA Park - P51900001339 Dec 23.pdf27 Feb 2024
Disclosure of sold/ booked inventoryFile: Lodha Park - P51900001339 - Sep23.pdf27 Dec 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Reg Allura.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Reg Marquise.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Society Reg Parkside.pdf13 Jan 2023
Status of Formation of Legal Entity (Society/Co Op etc.)File: Soicety Registration Certificate-Trump Tower.pdf13 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: 16 LODHA PARK.pdf14 Nov 2022
Architect’s Certificate on Completion of Project (Form 4)File: Lodha Park.pdf23 Aug 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Lodha Adrina.pdf3 Aug 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20190520 OC Wing 1,2,3- till 42nd fl.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20190613 MTM OC Wing 1,2,3- from 43rd to 62nd fl.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20190722- MTM -Part OC Letter of wing 1,2,3.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20210921 Kiara 7th to 42nd and Parkside full OC 64th.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 20211215 OC Kiara (43 to 58 pt and 59 to 66).pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 1.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 3.pdf25 Jul 2022
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 4.pdf25 Jul 2022
Disclosure of sold/ booked inventoryFile: LODHA PARK_compressed.pdf27 Dec 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 67 THE PARK.pdf17 Dec 2021
Certificates of CA (Form 3)File: 16 LODHA PARK.pdf15 Dec 2021
Form 2AFile: 113 THE PARK.pdf18 Nov 2021
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 67 THE PARK.pdf3 Nov 2021
Certificates of CA (Form 3)File: THE PARK - T1 to T5, RETAIL.pdf3 Nov 2021
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 63_Lodha Park.pdf15 Oct 2021
Disclosure of sold/ booked inventoryFile: P51900001339_New.pdf15 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: 110 THE PARK - T1 to T5, RETAIL.pdf15 Oct 2021
Details of encumbrancesFile: The Park.pdf22 Sep 2021
Details of encumbrancesFile: The Park.pdf16 Sep 2021
Form 2AFile: Form 2ALodha Park-Santosh Gaikwad-4.pdf12 Aug 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 129 The Park T1 to T5 Retail.pdf27 Oct 2020
Form 2AFile: The Park.pdf25 Aug 2020
Proforma of Allotment letterFile: ATS_MDL.pdf5 May 2020
Details of encumbrancesFile: The Park.pdf11 Nov 2019
Certificates of CA (Form 5)File: The Park T1 to T5.pdf11 Oct 2019
Form 2AFile: THe Park.pdf17 Jun 2019
OtherFile: LDL to MDL.pdf29 May 2019
Commencement Certificates / NA Order for plotted developmentFile: 2019_04_11 MTM Approval letter.pdf12 Apr 2019
Details of encumbrancesFile: THE PARK.pdf25 Feb 2019
Status of Formation of Legal Entity (Society/Co Op etc.)File: NR Allura.pdf18 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: NR Kiara.pdf18 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: NR Marquise.pdf18 Dec 2018
Status of Formation of Legal Entity (Society/Co Op etc.)File: NR Parkside.pdf18 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: 2018 12 11 MTM CC Wing 5 till 63rd fl.pdf13 Dec 2018
Commencement Certificates / NA Order for plotted developmentFile: MTM CC dated 17 11 2018.pdf19 Nov 2018
Details of encumbrancesFile: The Park.pdf16 Nov 2018
Certificates of CA (Form 5)File: THE PARK.pdf1 Oct 2018
Details of encumbrancesFile: The Park.pdf13 Aug 2018
Layout approvalFile: Mumbai Mill - Environmental Clearance NOC 2.pdf14 Jun 2018
Copy of Layout Approval (in case of layout)File: Mumbai Mill - Environmental Clearance NOC 2.pdf14 Jun 2018
Copy of the legal title reportFile: The Park_All TR upto 28_03_18.pdf30 Apr 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: THE PARK.pdf6 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: THE PARK.pdf6 Apr 2018
Certificates of CA (Form 3)File: The-Park-1-27.pdf29 Mar 2018
Certificates of CA (Form 3)File: The-Park-28-54.pdf29 Mar 2018
Details of encumbrancesFile: ENCUMBRANCES THE PARK_v2 as on Feb18.pdf26 Mar 2018
Details of encumbrancesFile: ENCUMBRANCES THE PARK_v1.pdf20 Mar 2018
Details of encumbrancesFile: ENCUMBRANCES THE PARK.pdf16 Mar 2018
Certificates of CA (Form 3)File: park 1 to 5.pdf28 Feb 2018
Commencement Certificates / NA Order for plotted developmentFile: 20180216 MTM CC.PDF19 Feb 2018
Copy of the legal title reportFile: The Park Third Supplemental dated 22-12-2017.pdf22 Dec 2017
Proforma of Allotment letterFile: ATS (The Park) - v3 - 8 November 2017Consol.pdf8 Nov 2017
Proforma of Allotment letterFile: ATS (The Park) - v3 - 2 November 2017.pdf6 Nov 2017
Certificates of CA (Form 3)File: RERA Bank Details.pdf31 Oct 2017
Layout approvalFile: Layout Plan.pdf25 Jul 2017
Copy of Layout Approval (in case of layout)File: Layout Plan.pdf25 Jul 2017
Declaration in FORM BFile: The Park Form B.pdf25 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: the park.pdf25 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: The Park - Form 2_Reduced.pdf25 Jul 2017
Certificates of CA (Form 3)File: Form 3 The Park A.pdf25 Jul 2017
Certificates of CA (Form 3)File: Form 3 The Park B.pdf25 Jul 2017
Certificates of CA (Form 3)File: Form 3 The Park C.pdf25 Jul 2017
Building plan approvalFile: 9.pdf24 Jul 2017
Building plan approvalFile: 10.pdf24 Jul 2017
Building plan approvalFile: 1.pdf24 Jul 2017
Building plan approvalFile: 2.pdf24 Jul 2017
Building plan approvalFile: 5.pdf24 Jul 2017
Building plan approvalFile: 6.pdf24 Jul 2017
Building plan approvalFile: 3.pdf24 Jul 2017

Keep LODHA PARK on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near .

2 kmLODHA PARKCompleted 21Lapsed / revoked 12Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: MACROTECH DEVELOPERS LIMITED

Macrotech Developers Limited has 141 registrations on MahaRERA, including LODHA BELMONDO ASHBRIDGE D, E and LODHA BELMONDO AUGUSTA B. Its filings disclose 6 earlier MahaRERA projects: declares 5 of 6 past projects completed on time. Litigation is declared on 2 of its registrations. Read the full track record.

Frequently asked questions

What are my rights if LODHA PARK is delayed beyond 30 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LODHA PARK?

The registered promoter entity is MACROTECH DEVELOPERS LIMITED, a company as per the filing. Its CIN L45200MH1995PLC093041 and GSTIN 27AAACL1490J1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LODHA PARK?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LODHA PARK?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LODHA PARK?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

What should I check before booking in LODHA PARK?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LODHA PARK. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LODHA PARK to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.