Home / Browse projects / Palghar, Maharashtra / PARAMOUNT ENCLAVE PHASE 02

Registration lapsed No litigation declared Residential / Group Housing project

PARAMOUNT ENCLAVE PHASE 02

By OM SAI CONSTRUCTION

RG-MH-29434 · RERA P99000028976 · Last updated on MahaRERA portal: 24 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 10 months past the filed date
  • 1 complaint at MahaRERA
  • Completion date moved by 24 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2025Possession promised10 months past this date
5 of 11Construction stages donefurthest along: Staircases, 75%
33 of 48Units unsoldnot recorded sold or booked
1Complaints at MahaRERAon this registration
Jump to the 60 documents Report an error

PARAMOUNT ENCLAVE PHASE 02 is a Residential / Group Housing project by OM SAI CONSTRUCTION in Palghar, Maharashtra, registered with MahaRERA as P99000028976 on 23 Apr 2021. Possession was promised by 31 Dec 2025 and is now 10 months past that date. The completion date has moved by 24 months from the original filing. 15 of the 48 units on this registration are recorded sold or booked, and 5 of 11 construction stages are filed complete. 1 complaint is on record with the regulator.

At a glance

Project

  • NamePARAMOUNT ENCLAVE PHASE 02
  • TypeResidential / Group Housing
  • Location
    • .
    • HARANWADI
    • Mahim
    • Palghar
    • 401404
  • Pincode401404
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000028976
  • ReraGenie IDRG-MH-29434

Builder

  • NameOM SAI CONSTRUCTION
  • Entity typePartnership
  • PartnersBRIJESH SITARA DUBEY, SHEELA BRIJESH DUBEY
  • Other registrations14 more →
  • Completed3 of 15
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects13 →

Key dates

10 months past promisethis monthRegisteredApr 2021First promiseDec 2023Revised toDec 2025

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on23 Apr 2021
  • Promised completion31 Dec 2025
  • Revised completionRevised to 31 Dec 2025 (originally 31 Dec 2023)
  • Buildings1 building record
  • Documents filed60 files

Current status

31%15 of 48 units booked

Figures as on 24 Feb 2025, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BUILDING NO 4 TYPE ANA8740848

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

5 of 11 construction stages are filed complete. The stage furthest along is Staircases, at 75%.

BUILDING NO 4 TYPE A: 66% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises50%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks75%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 24 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed15

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots15
Closed/Covered15

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area2,136 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MAYANK REALTYVasai-Virar City (M Corp)Palghar

Approvals and building plan

Sanctioning authorityCollector of Palghar
Permissible FSI1602.04
Proposed, not sanctioned1,602 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNALLASOPARA EAST NARAYAN NAGAR TANKI ROAD

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
Architectvastu shilp
Engineerjai shree krishna consulting engg
EngineerMUKESH KUMAR
EngineerCENTRE LINE CONSULTANTS AND ENGINEERS
Chartered AccountantMadhusudan sharma
Chartered AccountantAGP AND ASSOCIATES
Chartered AccountantKAMLESH DUGGAR AND CO
Chartered AccountantArvind Jugraj Jain
PartnerRole in project
OM SAI CONSTRUCTION-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT99000019034Dec 2023 → Dec 2025

Reason as filed by the promoter1) REVISED CC AND PLAN COPIES TOOK MORE TIME TO SANCTION. 2) LABOUR SHORTAGE PROBLEM, MATERIAL SHORTAGE, RAIN ETC 3) SALE IS ALSO POOR

Complaints filed with MahaRERA1

Case no.ComplainantRespondentFiled
CC006000000429455Vinod Dudha ParmarOm Sai Construction06/03/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 5 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Mar 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 11 Mar 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 11 Mar 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed60

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTCERTIFICATE_1.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: ARCHITECTCERTIFICATE1.pdf24 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: om sai construction1.pdf24 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Jun 24 1.pdf24 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer sep 24 1.pdf24 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Dec1.pdf24 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf17 Mar 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: FORM 2A 2122.pdf16 Mar 2024
Disclosure of sold/ booked inventoryFile: SOLD UNSOLD INVENTORY.pdf16 Mar 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1_compressed (1).pdf12 Mar 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2A 2223.pdf12 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 FY 2021.pdf12 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 FY 2223.pdf12 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: FORM 5 FY 2122.pdf12 Mar 2024
Layout approvalFile: LAYOUT OM SAI.pdf11 Mar 2024
Building plan approvalFile: TYPE A PLAN OM SAI.pdf11 Mar 2024
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCES.pdf11 Mar 2024
Details of encumbrances concerned to FinanceFile: NO ENCUMBRANCES.pdf11 Mar 2024
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCES.pdf11 Mar 2024
Details of encumbrances concerned to LegalFile: NO ENCUMBRANCES.pdf11 Mar 2024
Copy of Layout Approval (in case of layout)File: LAYOUT OM SAI.pdf11 Mar 2024
Building Plan Approval / NA Order for plotted developmentFile: TYPE A PLAN OM SAI.pdf11 Mar 2024
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE.pdf11 Mar 2024
Declaration about Commencement CertificateFile: cc declaration.pdf11 Mar 2024
Declaration in FORM BFile: FORM B BUILDER.pdf11 Mar 2024
CERSAI detailsFile: NO CERSAI.pdf11 Mar 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: MEMBER DETAILS.pdf11 Mar 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: BANK DECLARATION.pdf11 Mar 2024
Deviation Report with respect to Allotment letterFile: DEVIATION REPORT.pdf11 Mar 2024
Deviation Report with respect to model copy of AgreementFile: DEVIATION REPORT.pdf11 Mar 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: form 5 2023.pdf20 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form 1 march 2023.pdf26 Dec 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: form june 2023.pdf26 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June 2023.pdf26 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 march 2023.pdf26 Dec 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Dec form 2.pdf30 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Sep form 2.pdf30 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: March form 2.pdf30 Apr 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: June form 2.pdf30 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: FORM 5 2021.pdf24 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM1.pdf14 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 OM SAI.pdf14 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1 om sai construction.pdf14 Apr 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: om sai form 1.pdf14 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: om sai construction.pdf17 Feb 2023
Declaration in FORM BFile: Form- B OM SAI CONSTRUCTION_compressed.pdf12 Apr 2021
Copy of the legal title reportFile: Legal Search Report Om sai.pdf5 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: cc om sai constructionA .pdf5 Mar 2021
Layout approvalFile: PARAMOUNT ENCLAVE PHASE 2 LEYOUT_compressed.pdf18 Feb 2021
Building plan approvalFile: blue print layout.PDF18 Feb 2021
PAN CardFile: firm pan card.pdf18 Feb 2021
Details of encumbrancesFile: encumbrances certificates om sai construction.pdf18 Feb 2021
Copy of Layout Approval (in case of layout)File: PARAMOUNT ENCLAVE PHASE 2 LEYOUT_compressed.pdf18 Feb 2021
Building Plan Approval / NA Order for plotted developmentFile: blue print layout.PDF18 Feb 2021
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: architek certificate.pdf18 Feb 2021
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: engneer certificate.pdf18 Feb 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: om sai rera ca certificates_compressed.pdf18 Feb 2021
Proforma of Allotment letterFile: DRAFT AGREEMENT.pdf18 Feb 2021
Proforma of Allotment letterFile: OM SAI CONSTRUCTION ALLOTMENT LETTER.pdf18 Feb 2021

How this compares with Palghar

31%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 24 months
26%of Palghar registrations have lapsed or been cancelledthis one is among them

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep PARAMOUNT ENCLAVE PHASE 02 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near HARANWADI3,200+ in Palghar

2 kmPARAMOUNT ENCLAVE PHASE Completed 21Lapsed / revoked 15Other 10Dot size: filed unitsN

Filed coordinates, straight-line distance. 46 registered projects within 2 km.

Builder: OM SAI CONSTRUCTION

OM SAI CONSTRUCTION has 15 registrations on MahaRERA, including SAI SAMRUDDHI and SAI SUMIRAN APARTMENT. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What does it mean that PARAMOUNT ENCLAVE PHASE 02 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if PARAMOUNT ENCLAVE PHASE 02 is delayed beyond 31 Dec 2025?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of PARAMOUNT ENCLAVE PHASE 02?

The registered promoter entity is OM SAI CONSTRUCTION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in PARAMOUNT ENCLAVE PHASE 02?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against PARAMOUNT ENCLAVE PHASE 02?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for PARAMOUNT ENCLAVE PHASE 02?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at PARAMOUNT ENCLAVE PHASE 02?

The professionals named in the filing: Architect: vastu shilp; Engineer: jai shree krishna consulting engg; Engineer: MUKESH KUMAR; Engineer: CENTRE LINE CONSULTANTS AND ENGINEERS; Chartered Accountant: Madhusudan sharma; Chartered Accountant: AGP AND ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in PARAMOUNT ENCLAVE PHASE 02?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About PARAMOUNT ENCLAVE PHASE 02. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save PARAMOUNT ENCLAVE PHASE 02 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.