Home / Developers / OM SAI CONSTRUCTION
OM SAI CONSTRUCTION: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
OM SAI CONSTRUCTION has 15 registrations on MahaRERA, including SAI SAMRUDDHI and SAI SUMIRAN APARTMENT. Its filings disclose 13 earlier MahaRERA projects: declares 10 of 13 past projects completed on time.
Projects by this developer
Showing all 15 projects.
Largest first, by the unit count in the filing.
| Project | Location | Units | Booked | Registered | Status |
|---|---|---|---|---|---|
| OM GALAXYPR1220002600259 | PATHARDI SHIWAR, Nashik, 422010 | 97 | 0% | 24 Apr 2026 | Registered |
| SHREE GAYATRIDEEPP51700076836 | Village Kulgaon, Thane, 421503 | 50 | 2% | 28 Jun 2024 | Registered |
| PARAMOUNT ENCLAVE PHASE 02P99000028976 | HARANWADI, Palghar, 401404 | 48 | 31% | 23 Apr 2021 | Registration lapsed |
| SAI SAGAR RESIDENCYP51700052074 | KALYAN EAST, Thane, 421306 | 37 | 76% | 19 Jul 2023 | Registered |
| BK. RESIDENCYP51700051563 | MURBAD, Thane, 421401 | 30 | 0% | 27 Jun 2023 | Registered |
| Harshnil ResidencyPR1220002400090 | Nashik, Nashik, 422003 | 24 | 0% | 8 Oct 2024 | Registered |
| Shree Ganraj ResidencyP51700054872 | Village Kulgaon, Thane, 421503 | 14 | 64% | 15 Feb 2024 | Registered |
| OM SAI APARTMENTP99000079346 | CHINTUPADA ROAD, Palghar, 401404 | - | - | 28 Feb 2025 | Registered |
| Sai AaradhyaP52000021572 | kharghar Navi Mumbai, Raigarh, 410210 | - | - | 9 Jul 2019 | Registration lapsed |
| SAI MAULI APARTMENTP52000055076 | VARSE, Raigarh, 402116 | - | - | 29 Feb 2024 | Registered |
| SAI PANDURANG HEIGHTP51700026563 | CHINCHPADA, Thane, 421306 | - | - | 4 Oct 2020 | Completed |
| SAI SAMRUDDHIP52000011177 | Nadgaon Tarf Birwadi (CT), Raigarh, 402102 | - | - | 31 Aug 2017 | Completed |
| SAI SAMRUDDHI B AND C WINGP52000023435 | OPP. ARUN NAGAR, Raigarh, 402302 | - | - | 16 Dec 2019 | Registration lapsed |
| SAI SUMIRAN APARTMENTP50500026906 | RING ROAD PRATAP NAGAR NAGPUR, Nagpur, 440022 | - | - | 3 Nov 2020 | Registration lapsed |
| SKY VISION TOWERP53100030477 | MAHAVIR UDYAAN, Sangli, 416416 | - | - | 25 Aug 2021 | Completed |
What this promoter declares as its own experience
OM SAI CONSTRUCTION declares experience on 13 earlier projects. None of them carries a registration number we could match on MahaRERA, which is usual for work done before the register existed.
From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Sai Ganga | 15 May 2015 | 28 Apr 2017 | +23 months |
| Sai Sapphire | 31 Jul 2015 | 2 Jul 2015 | On time |
| Sai Moksh | 8 Dec 2015 | 19 Jun 2015 | On time |
| Sai Harmony | 31 Jul 2016 | 30 Sep 2016 | +2 months |
| Sai Spring | 1 Aug 2016 | 21 Jul 2016 | On time |
| Sai Crystal | 1 Oct 2016 | 30 Sep 2016 | On time |
| Sai Fortune | 1 Dec 2016 | 21 Nov 2016 | On time |
| SAI DUTTA APARTMENT | 31 Dec 2016 | 31 Dec 2016 | On time |
| Sai Sahil | 1 May 2017 | 28 Apr 2017 | On time |
| Sai Wonder | 1 Jul 2017 | 9 May 2017 | On time |
| Sai Solitaire | 1 Jul 2017 | 21 Jun 2016 | On time |
| Sai Riverdale | 18 Oct 2017 | 3 Jul 2017 | On time |
Frequently asked questions
How do I verify OM SAI CONSTRUCTION as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with OM SAI CONSTRUCTION?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.