RG-MH-18868 · RERA P51800077808 · Last updated on MahaRERA portal: 22 Apr 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Rs 50.00 crore secured on the land, in favour of ADITYA BIRLA HOUSING FINANCE LIMITED
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- All 6 earlier projects delivered on promise
1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
OSTWAL GALA KUNJ is a Residential / Group Housing project by SHREE OSTWAL BUILDERS LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800077808 on 7 Nov 2024. Possession is promised by 31 Dec 2029. 2 of the 114 units on this registration are recorded sold or booked, and 4 of 11 construction stages are filed complete.
At a glance
Project
- NameOSTWAL GALA KUNJ
- TypeResidential / Group Housing
- Location
- DR BABASAHEB AMBEDKAR ROAD
- MULUD (WEST)
- Mulund
- Kurla
- Mumbai Suburban
- 400080
- Pincode400080
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800077808
- ReraGenie IDRG-MH-18868
Builder
- NameSHREE OSTWAL BUILDERS LTD
- Entity typeCompany
- CINU45200MH1989PLC050872
- GSTIN27AAFCS2523N1Z4
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- Managing DirectorUMRAOSINGH PRITHVIRAJ OSTWAL
- DirectorsKULDEEP UMRAOSINGH Ostwal, KULDEEP UMRAOSINGH Ostwal, ASHA UMRAOSINGH OSTWAL, SHAKENDRA VARDHMAN CHHAJED
- Other registrations19 more →
- Completed7 of 20
- Past their filed date1
- Declared earlier projects6 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on7 Nov 2024
- Promised completion31 Dec 2029
- Revised completionNone
- Buildings1 building record
- Documents filed82 files
Current status
Figures as on 22 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| MULUND GALAKUNJ APARTMENT CHSL | NA | 27 | 16 | 99 | 15 | 114 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 22 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
4 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 35%.
MULUND GALAKUNJ APARTMENT CHSL: 40% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 100% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 35% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 22 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | No | Not applicable |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed96
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
| Landowner | Village | District |
|---|---|---|
| MULUND GALA KUNJ APARTMENT CO OP HSG SOC LTD | Mulund | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| MULUND GALAKUNJ APARTMENT CHSL | NA | Rs 54.68 cr | Rs 13.40 cr |
| - | NA | Rs 13.67 cr | Rs 2.05 cr |
Certifying professionals and partners8
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | DESIGN CREST AXIOM |
| Engineer | DESTECH STRUCTURAL CONSULTANT |
| Engineer | BHAVESH BHALCHANDRA TODANKAR |
| Engineer | DESTECH STRUCTURAL CONSULTANTS |
| Chartered Accountant | KHURDIA JAIN & CO |
| Chartered Accountant | ABHISHEK SURANA & CO |
| Chartered Accountant | KHURDIA JAIN & CO. |
| Chartered Accountant | Madhubala Jain & Co |
| Partner | Role in project |
|---|---|
| SHREE OSTWAL BUILDERS LTD | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 10 Oct 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 25 Jun 2024 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 25 Jun 2024 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 25 Jun 2024Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 31 Dec 2029
Documents filed82
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Withdrawal Update Form 1File: Form 1_Ostwal Galakunj_31122025.pdf | 22 Apr 2026 |
| Withdrawal Update Form 2File: FORM-2_GALAKUNJ_31122025.pdf | 22 Apr 2026 |
| Withdrawal Update Form 3File: Form 3_GalaKunj_31122025.pdf | 22 Apr 2026 |
| Withdrawal Update Form 1File: FORM-1_OSTWAL GALAKUNJ_30092025.pdf | 24 Nov 2025 |
| Withdrawal Update Form 2File: FORM-2_OSTWAL GALAKUNJ_30092025.pdf | 24 Nov 2025 |
| Withdrawal Update Form 3File: Form-3_Ostwal Galakunj_30092025.pdf | 24 Nov 2025 |
| Form 5 (FY 2024-2025)File: FORM 5 GALAKUNJ-2024-2025.pdf | 29 Sep 2025 |
| Withdrawal Update Form 1File: FORM 1 _ 30062025.pdf | 26 Sep 2025 |
| Withdrawal Update Form 2File: Form-2_30062025_Gala Kunj.pdf | 26 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 30062025_Galakunj.pdf | 26 Sep 2025 |
| Withdrawal Update Form 1File: FORM 1 _ 30062025.pdf | 22 Sep 2025 |
| Withdrawal Update Form 2File: Form-2_30062025_Gala Kunj.pdf | 22 Sep 2025 |
| Withdrawal Update Form 3File: Form 3 30062025_Galakunj.pdf | 22 Sep 2025 |
| Declaration and undertaking (Annexure A)File: Annexure A_DEclaration Cum Undertaking.pdf | 19 Jun 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 30092024-GALA KUNJ .pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31122024-GALA KUNJ .pdf | 21 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1 31032025-GALA KUNJ .pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 30092024- GALA KUNJ.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31122024- GALA KUNJ.pdf | 21 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2 31032025- GALA KUNJ.pdf | 21 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Self Certification Form-3 _31032025 _Gala Kunj.pdf | 18 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: Sold Unsold_31032025-Gala Kunj.pdf | 17 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A_March-25_Galakunj.pdf | 16 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD_OSTWAL GALAKUNJ_31122024.pdf | 14 Jan 2025 |
| Other - FinanceFile: SELF CERTIFICATION_OSTWAL GALA KUNJ_31122024.pdf | 14 Jan 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A_OSTWAL GALA KUNJ_31122024.pdf | 14 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 22102024 REVISED.pdf | 29 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 22102024.pdf | 22 Oct 2024 |
| CERSAI detailsFile: CERSAI UNDERTAKING 22102024.pdf | 22 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank Letter Head Format B 22102024.pdf | 22 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 _GALA KUNJ 13082024.pdf | 14 Oct 2024 |
| CERSAI detailsFile: GetUserDocumentFileContent.pdf | 14 Oct 2024 |
| Copy of the legal title reportFile: Title Certificate 18082024.pdf | 10 Oct 2024 |
| Details of encumbrances concerned to FinanceFile: Financial Encrumbrance Certificate New.pdf | 10 Oct 2024 |
| Proforma of Allotment letterFile: Allotment Letter New.pdf | 10 Oct 2024 |
| CERSAI detailsFile: Cersai Undertaking.pdf | 10 Oct 2024 |
| Details of encumbrances concerned to LegalFile: Financial Encrumbrance Certificate New.pdf | 10 Oct 2024 |
| Other - TechnicalFile: Annexure A_DEclaration Cum Undertaking.pdf | 10 Oct 2024 |
| Proforma of Agreement for saleFile: Draft Agreement New.pdf | 10 Oct 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B_from Bank.pdf | 10 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate_11zon.pdf | 13 Aug 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Promoter BANK letterhead_gala kunj.pdf | 13 Aug 2024 |
| Other - TechnicalFile: Order_57_Amenities.pdf | 13 Aug 2024 |
| Other - TechnicalFile: OrdeNo54 .pdf | 13 Aug 2024 |
| Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Bank letter_Galakunj (1).pdf | 13 Aug 2024 |
| Disclosure for secured/unsecured finance availed for the projectFile: Disclosure of Secured Unsecured.pdf | 13 Aug 2024 |
| Building plan approvalFile: Temprary Plan Site Godown.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 8.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 7.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 6.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 5.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 4.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 3.pdf | 25 Jun 2024 |
| Building plan approvalFile: Plan No 2.pdf | 25 Jun 2024 |
| Layout approvalFile: LAYOUT.pdf | 25 Jun 2024 |
| PAN CardFile: SOBL New Pan Card.pdf | 25 Jun 2024 |
| Copy of the legal title reportFile: Title Certificate Dipti Nagda 09 02 2024.pdf | 25 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Financial Encrumbrance Certificate.pdf | 25 Jun 2024 |
| Details of encumbrances concerned to FinanceFile: Legal and Litigation Encrumbrance.pdf | 25 Jun 2024 |
| Copy of Layout Approval (in case of layout)File: LAYOUT.pdf | 25 Jun 2024 |
| Proforma of Allotment letterFile: Allotment Letter.pdf | 25 Jun 2024 |
| Declaration in FORM BFile: Form B SOBL.pdf | 25 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM -1 ARCHITECT CERTIFICATE_Signed.pdf | 25 Jun 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Eng Certificate Gala Kunj.pdf | 25 Jun 2024 |
| Commencement Certificates / NA Order for plotted developmentFile: CC Plinth level 18 12 2023.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 8.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 2.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 3.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 4.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 5.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 6.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Plan No 7.pdf | 25 Jun 2024 |
| Building Plan Approval / NA Order for plotted developmentFile: Temprary Plan Site Godown.pdf | 25 Jun 2024 |
| Declaration about Commencement CertificateFile: Declaration about Commencement Certificate.pdf | 25 Jun 2024 |
| CERSAI detailsFile: CERSAI_Search_Report_200311346910_For_Asset_Based_Search_25_06_2024_14_11_45_946.pdf | 25 Jun 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A_Separate Bank Account.pdf | 25 Jun 2024 |
| Deviation Report with respect to Allotment letterFile: Deviation Report_Allotment Letter.pdf | 25 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Legal and Litigation Encrumbrance.pdf | 25 Jun 2024 |
| Details of encumbrances concerned to LegalFile: Financial Encrumbrance Certificate.pdf | 25 Jun 2024 |
| Deviation Report with respect to model copy of AgreementFile: Deviation Report_Agr for Sale.pdf | 25 Jun 2024 |
Promoter's earlier projects6
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| OSTWAL WOODSP99000019832 | OPP. UNION PARK, Palghar | - | Mar 2019 | Completed | Dec 2024 | Jun 2023 |
| OSTWAL DARSHANP51700004905 | BHAYANDER EAST, Thane | - | Aug 2017 | Completed | Dec 2024Registered original: Dec 2023 | Jun 2024 |
| OSTWAL GARDEN | KANAKIA ROAD MIRA ROAD EAST | 69 | - | Completed | Dec 2015 | Jun 2015 |
| OSTWAL OASIS | MIRA ROAD EAST | 33 | - | Completed | Apr 2015 | Jan 2015 |
| OSTWAL PRIDE I | KANAKIA ROAD MIRA ROAD EAST | 63 | - | Completed | Mar 2015 | Mar 2015 |
| OSTWAL HEIGHT BLDG 1 TO 4 | KANAKIA ROAD MIRA ROAD EAST | 195 | - | Completed | Dec 2013 | Dec 2013 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 1 condition on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 19 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 82 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep OSTWAL GALA KUNJ on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near MULUD (WEST)6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 368 registered projects within 2 km.
Eternia Towers A to D
Oberoi Constructions Limited
Bellanza Phase 1 - Wing A, B, C at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Atmosphere O2
Atmosphere Realty Pvt Ltd
Bellanza Phase 2 - Wing D, E, F at The Prestig
PRESTIGE MULUND REALTY PRIVATE LIMITED
Forest Hills Ph 1 at The Prestige City
PRESTIGE MULUND REALTY PRIVATE LIMITED
Kalpataru Elitus
Arimas Real Estate Private Limited
See every Mumbai Suburban project, with the district possession charts
Builder: SHREE OSTWAL BUILDERS LTD
SHREE OSTWAL BUILDERS LTD has 20 registrations on MahaRERA, including OSTWAL DARSHAN and OSTWAL POINT. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if OSTWAL GALA KUNJ is delayed beyond 31 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of OSTWAL GALA KUNJ?
The registered promoter entity is SHREE OSTWAL BUILDERS LTD, a company as per the filing. Its CIN U45200MH1989PLC050872 and GSTIN 27AAFCS2523N1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in OSTWAL GALA KUNJ?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for OSTWAL GALA KUNJ?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at OSTWAL GALA KUNJ?
The professionals named in the filing: Architect: DESIGN CREST AXIOM; Engineer: DESTECH STRUCTURAL CONSULTANT; Engineer: BHAVESH BHALCHANDRA TODANKAR; Engineer: DESTECH STRUCTURAL CONSULTANTS; Chartered Accountant: KHURDIA JAIN & CO; Chartered Accountant: ABHISHEK SURANA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in OSTWAL GALA KUNJ?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback