CIN U45200MH1989PLC050872 · GSTIN 27AAFCS2523N1Z4 · Company · attribution by exact filing name, entity resolution in progress

SHREE OSTWAL BUILDERS LTD has 20 registrations on MahaRERA, including OSTWAL DARSHAN and OSTWAL POINT. Its filings disclose 6 earlier MahaRERA projects: declares 6 of 6 past projects completed on time. Litigation is declared on 3 of its registrations.

20RERA registrations
6Past projects disclosed
on timeMedian delivery slip
3Registrations with litigation
Follow this developer. An email when SHREE OSTWAL BUILDERS LTD registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing all 20 projects.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
OSTWAL IMPERIALP99000049283PALGHAR, Palghar, 4014043703%7 Feb 2023Registered
OSTWAL HORIZONP51700024492NAVGHAR MIRA ROAD EAST, Thane, 40110726099%18 Feb 2020Registered
OSTWAL PALACEP99000034236TEMBHODE, Palghar, 40140524522%25 Mar 2022Registered
OSTWAL PARADISE BUILDING NO.9 WING A - B - CP51700048041MIRA ROAD EAST, Thane, 40110719471%7 Dec 2022Registered
OSTWAL AKAASHAP51700079129BHAYANDER (EAST), Thane, 40110516020%6 Feb 2025Registered
OSTWAL GALA KUNJP51800077808MULUD (WEST), Mumbai Suburban, 4000801142%7 Nov 2024Registered
OSTWAL MANSIONPM1330002501323BHAYANDER (EAST), Thane, 40110510816%24 Oct 2025Registered
OSTWAL PARAMOUNTP99000078147BOISAR TARAPUR ROAD, Palghar, 4015018127%25 Nov 2024Registered
OSTWAL WOODS IIP99000056093OPP. UNION PARK, Palghar, 4015018151%10 May 2024Registered
OSTWAL WOODS IIIP99000080244OPP. UNION PARK, Palghar, 4015017826%13 May 2025Registered
OSTWAL FERMINOPR1180002502949Eksar, Mumbai Suburban, 400103400%18 Mar 2026Registered
OSTWAL VILLASP99000051610TEMBHODE, Palghar, 4014053636%27 Jun 2023Registered
OSTWAL DARSHANP51700004905BHAYANDER EAST, Thane, 401105--9 Aug 2017Completed
OSTWAL DREAM LANDP99000008545Boisar, Palghar, 401501--19 Aug 2017Completed
OSTWAL DREAM LAND PHASE - IIP99000021182BOISAR, Palghar, 401501--14 Jun 2019Registered
OSTWAL HEIGHT - 5P51700008433Mira-Bhayandar (M Corp.), Thane, 401107--18 Aug 2017Completed
OSTWAL POINTP51700008381Mira-Bhayandar (M Corp.), Thane, 401107--18 Aug 2017Completed
OSTWAL VALLEYP99000006087Katkar (CT), Palghar, 401501--14 Aug 2017Completed
OSTWAL WONDER CITYP99000006909Betegaon, Palghar, 401501--16 Aug 2017Completed
OSTWAL WOODSP99000019832OPP. UNION PARK, Palghar, 401501--5 Mar 2019Completed

What this promoter declares as its own experience

SHREE OSTWAL BUILDERS LTD declares experience on 6 earlier projects. 2 of them carry a registration number we could match on MahaRERA, all under this promoter's own name.

2 of these declarations can be compared with the dates those projects' own registrations hold. On 1, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 1 of the 2 completions recorded here as on time: measured against the original deadline the register itself holds, that one was finished after it.

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
OSTWAL HEIGHT BLDG 1 TO 4
31 Dec 20139 Dec 2013On time
OSTWAL PRIDE I
31 Mar 201531 Mar 2015On time
OSTWAL OASIS
30 Apr 201531 Jan 2015On time
OSTWAL GARDEN
31 Dec 201515 Jun 2015On time
OSTWAL DARSHAN
P51700004905
29 Dec 202426 Jun 2024On time
OSTWAL WOODS
P99000019832
30 Dec 202413 Jun 2023On time

Frequently asked questions

How do I verify SHREE OSTWAL BUILDERS LTD as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45200MH1989PLC050872 and GSTIN 27AAFCS2523N1Z4 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SHREE OSTWAL BUILDERS LTD?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SHREE OSTWAL BUILDERS LTD unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.

Report an error or share feedback

About the SHREE OSTWAL BUILDERS LTD developer page. Projects are grouped by the promoter name as filed, so a wrongly attributed project is the most useful thing to report.

We read every report. We cannot promise a reply to each one.