ReraGenieLog inGet a buyer report

Home / Developers / SHREE OSTWAL BUILDERS LTD

SHREE OSTWAL BUILDERS LTD: RERA track record

Company ยท attribution by exact filing name, entity resolution in progress

SHREE OSTWAL BUILDERS LTD has 20 registrations in this build, including OSTWAL DARSHAN and OSTWAL POINT. Its filings disclose 6 earlier MahaRERA projects: 6 of 6 past projects completed on time. Litigation is declared on 3 of its registrations.

20Registrations in this build
6Past projects disclosed
on timeMedian delivery slip
3Registrations with litigation

Projects in this build

ProjectLocationUnits BookedStatus
OSTWAL DARSHANThane, Maharashtra--Completed
OSTWAL POINTThane, Maharashtra--Completed
OSTWAL HEIGHT - 5Thane, Maharashtra--Completed
OSTWAL VALLEYPalghar, Maharashtra--Completed
OSTWAL WONDER CITYPalghar, Maharashtra--Completed
OSTWAL DREAM LANDPalghar, Maharashtra--Completed
OSTWAL DREAM LAND PHASE - IIPalghar, Maharashtra--Registered
OSTWAL WOODSPalghar, Maharashtra--Completed
OSTWAL HORIZONThane, Maharashtra26099%Registered
OSTWAL PALACEPalghar, Maharashtra24522%Registered
OSTWAL PARADISE BUILDING NO.9 WING A - B - CThane, Maharashtra19471%Registered
OSTWAL IMPERIALPalghar, Maharashtra3703%Registered
OSTWAL VILLASPalghar, Maharashtra3636%Registered
OSTWAL WOODS IIPalghar, Maharashtra8151%Registered
OSTWAL GALA KUNJMumbai Suburban, Maharashtra1142%Registered
OSTWAL PARAMOUNTPalghar, Maharashtra8127%Registered
OSTWAL AKAASHAThane, Maharashtra16011%Registered
OSTWAL WOODS IIIPalghar, Maharashtra7826%Registered
OSTWAL MANSIONThane, Maharashtra10816%Registered
OSTWAL FERMINOMumbai Suburban, Maharashtra400%Registered

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
OSTWAL HEIGHT BLDG 1 TO 4
31 Dec 20139 Dec 2013On time
OSTWAL PRIDE I
31 Mar 201531 Mar 2015On time
OSTWAL OASIS
30 Apr 201531 Jan 2015On time
OSTWAL GARDEN
31 Dec 201515 Jun 2015On time
OSTWAL DARSHAN
P51700004905
29 Dec 202426 Jun 2024On time
OSTWAL WOODS
P99000019832
30 Dec 202413 Jun 2023On time

Frequently asked questions

How do I verify SHREE OSTWAL BUILDERS LTD as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with SHREE OSTWAL BUILDERS LTD?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make SHREE OSTWAL BUILDERS LTD unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.