Home / Browse projects / Palghar, Maharashtra / ORCHID VILLAS

Registered No litigation declared Residential / Group Housing project

ORCHID VILLAS

By SHARP DEVELOPERS

RG-MH-22839 · RERA P99000024168 · Last updated on MahaRERA portal: 27 Jul 2026

Source: official MahaRERA filing

Red flags

  • 2 complaints at MahaRERA
  • Completion date moved by 43 months
  • 1 extension taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 1 earlier projects delivered on promise

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Palghar registration emailed to you, free during the pilot beta.
Dec 2030Possession promisedmoved 43 months from the original
189 of 209Construction stages doneacross 19 buildings; furthest along: Podiums (if any), 0%
46 of 130Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 187 documents Report an error

ORCHID VILLAS is a Residential / Group Housing project by SHARP DEVELOPERS in Palghar, Maharashtra, registered with MahaRERA as P99000024168 on 23 Jan 2020. Possession is promised by 31 Dec 2030. The completion date has moved by 43 months from the original filing. 84 of the 130 units on this registration are recorded sold or booked, and 189 of 209 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameORCHID VILLAS
  • TypeResidential / Group Housing
  • Location
    • VILL - CHINCHOTI
    • CHINCHOTI
    • Vasai-Virar City (M Corp)
    • Vasai
    • Palghar
    • 401208
  • Pincode401208
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P99000024168
  • ReraGenie IDRG-MH-22839

Builder

  • NameSHARP DEVELOPERS
  • Entity typePartnership
  • PartnersRAAZ ABDUL SAMAD PATHAN, NIYAZ ABDUL SAMAD PATHAN
  • PartnerKADAR KHAJA HUSSAIN KHILLEDAR
  • Declared earlier projects1 →

Key dates

this monthRegisteredJan 2020First promiseMay 2027Revised toDec 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on23 Jan 2020
  • Promised completion31 Dec 2030
  • Revised completionRevised to 31 Dec 2030 (originally 30 May 2027)
  • Buildings19 building records
  • Documents filed187 files

Current status

65%84 of 130 units booked
100.0%Work done, per cost certificate

Figures as on 27 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
CLUSTER - 10NA16013013
CLUSTER - 11NA23020020
CLUSTER - 12NA70404
CLUSTER - 13NA70404
CLUSTER -14NA90606
CLUSTER -15NA50202
CLUSTER -16NA70404
CLUSTER - 17NA70404
CLUSTER -18NA16013013
CLUSTER -19NA70404
CLUSTER 1NA33404
CLUSTER 2NA30404
CLUSTER 3NA30404
CLUSTER 4NA30404
CLUSTER 5NA30404
CLUSTER 6NA30404
CLUSTER 7A-7BNA30606
CLUSTER 8NA3010010
CLUSTER 9NA3016016

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building19

As on 27 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

189 of 209 construction stages are filed complete across 19 buildings. The stage furthest along is Podiums (if any), at 0%.

CLUSTER - 1091%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER - 1191%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER - 1291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER - 1391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER -1491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER -1591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER -1691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER - 1791%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER -1891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER -1991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 182%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 291%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 391%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 491%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 591%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 691%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 7A-7B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 891%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
CLUSTER 991%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 27 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingYes100%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed74

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots74
Closed/Covered74
BuildingClosed/CoveredTotal
CLUSTER - 101313
CLUSTER - 112020
CLUSTER - 1244
CLUSTER - 1344
CLUSTER -1466
CLUSTER -1522
CLUSTER -1644
CLUSTER - 1744
CLUSTER -181313
CLUSTER -1944

Land and ownership4

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area4,154 sq m
Land owned byThe promoter, with other names on the file
Named landowners4
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on4 Oct 2024
LandownerVillageDistrict
DHARMENDRA PRATAP R PALGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban
HIRALAL BHOINDER PAL-Mumbai Suburban
MAYUR HIRALAL PAL-Mumbai Suburban
Manish Hiralal Pal-Mumbai Suburban

Approvals and building plan

Sanctioning authorityvasai virar city muncipal corporation
Permissible FSI9154.07
Proposed, not sanctioned4,154 sq m
Buildings approved19
Buildings sanctioned19

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAMBADI ROAD VASAI WEST
Estimated costRs 26.00 cr
Cost incurredRs 26.00 cr
Work done100.0%
BuildingWingEstimatedIncurred
CLUSTER - 11NARs 3.82 crRs 3.82 cr
CLUSTER 9NARs 3.00 crRs 3.00 cr
CLUSTER - 10NARs 2.50 crRs 2.50 cr
CLUSTER -18NARs 2.50 crRs 2.50 cr
CLUSTER 8NARs 2.00 crRs 2.00 cr
CLUSTER -14NARs 1.15 crRs 1.15 cr
CLUSTER 7A-7BNARs 1.15 crRs 1.15 cr
-NARs 90.00 lakhRs 90.00 lakh
CLUSTER - 12NARs 78.00 lakhRs 78.00 lakh
CLUSTER - 13NARs 78.00 lakhRs 78.00 lakh
CLUSTER -16NARs 78.00 lakhRs 78.00 lakh
CLUSTER - 17NARs 78.00 lakhRs 78.00 lakh

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectHIMESH GUPTA AND ASSOCIATES
ArchitectMUFFADAL MERCHANT
EngineerMOHAMMED SHOEB BHATI
EngineerMAHENDRA PRABHAKAR MANJREKAR
Chartered AccountantJINESH JOSHI
Chartered AccountantHARESH MEHTA & ASSOCIATES
PartnerRole in project
SHARP DEVELOPERS-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA18082502388May 2027 → Dec 2030

Reason as filed by the promoterThe issuance of the Occupation Certificate is delayed pending clarification on a matter between the VVCMC and the Forest Department. We wish to highlight the following key point: Our Commencement Certificate (CC No. WCMC/TP/CC/VP-5540/23/2019-20) was issued on 22nd May 2019. This predates the relevant Eco-Sensitive Zone (ESZ) Gazette Notification (REGD. NO. D.L. 33004/99), which was published on 11th September 2019. As our CC was granted prior to the gazette notification, a Forest Department NOC should not be applicable. While the WCMC seeks this procedural clarification, we are unable to secu

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC006000000580949RAAZ MOHAMMED ABDUL SAMAD PATHANNITIN SHRAVAN MORE01/07/2024
CC006000000590956RAAZ MOHAMMED ABDUL SAMAD PATHANZAHID HUSAIN KHAN AND TASLIMUNISA ZAHIDHUSAIN KHAN01/07/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 Jan 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 28 Dec 2019
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Dec 2019
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Dec 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2030

Documents filed187

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 187 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM-1 ORCHID VILLAS.pdf27 Jul 2026
Withdrawal Update Form 2File: FORM-2 ORCHID VILLAS.pdf27 Jul 2026
Withdrawal Update Form 3File: FORM-3 ORCHID VILLA.pdf27 Jul 2026
Withdrawal Update Form 1File: FORM 1- ORCHID VILLA COMPRESS.pdf24 Apr 2026
Withdrawal Update Form 2File: FORM 2- ORCHID VILLA.pdf24 Apr 2026
Withdrawal Update Form 3File: FORM-03 ORCHID VILLA COMPRESS.pdf24 Apr 2026
Withdrawal Update Form 1File: ORCHID FORM 1_compressed.pdf31 Jan 2026
Withdrawal Update Form 2File: ORCHID FORM 2_compressed.pdf31 Jan 2026
Withdrawal Update Form 3File: FORM 3 ORCHID VILLAS_compressed.pdf31 Jan 2026
Withdrawal Update Form 1File: FORM 1 ORCHID VILLA_compressed.pdf3 Jan 2026
Withdrawal Update Form 2File: FORM 2 ORCHID VILLAS_compressed.pdf3 Jan 2026
Withdrawal Update Form 3File: FORM 3 ORCHID VILLAS_compressed.pdf3 Jan 2026
Form 5 (FY 2024-2025)File: FORM 5 ORCHID VILLA-2025.pdf18 Nov 2025
Withdrawal Update Form 1File: FORM 1 ORCHID VILLA_compressed.pdf7 Nov 2025
Withdrawal Update Form 2File: FORM 2 ORCHID VILLAS_compressed.pdf7 Nov 2025
Withdrawal Update Form 3File: FORM 3 ORCHID VILLAS_compressed.pdf7 Nov 2025
Form 5 (FY 2019-2020)File: FORM 5 ORCHID VILAS.pdf4 Nov 2025
Form 5 (FY 2020-2021)File: FORM 5 ORCHID VILLA.pdf4 Nov 2025
Form 5 (FY 2021-2022)File: FORM 5 ORCHID VILLA.pdf4 Nov 2025
Form 5 (FY 2022-2023)File: FORM-5 ORCHID VILLA.pdf4 Nov 2025
Form 5 (FY 2023-2024)File: FORM 5 23-24 SHARP.pdf4 Nov 2025
Form 2A (FY 2025-2026)File: SHARP DEVELOPERS FORM 2A 2025.pdf30 Oct 2025
Form 1File: FORM 1 ORCHID VILLAS.pdf18 Aug 2025
Form 2File: FORM 2 ORCHID VILLAS.pdf18 Aug 2025
Form 3File: FORM 3 ORCHID VILLAS.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q3 2020.pdf18 Aug 2025
Form 1File: FORM 1 ORCHID VILLAS.pdf18 Aug 2025
Form 2File: FORM 2 ORCHID VILLAS.pdf18 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q2 2020.pdf18 Aug 2025
Form 1File: FORM 1 ORCHID VILLAS.pdf18 Aug 2025
Form 2File: FORM 2 ORCHID VILLAS.pdf18 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q1 2020.pdf18 Aug 2025
Form 2File: FORM-2 ORCHID VILLAS.pdf18 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q4 2019.pdf18 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf18 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf18 Aug 2025
Form 1File: FORM 1 Q4 2022.pdf14 Aug 2025
Form 2File: FORM 2 Q4 2022.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q4 2022.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLA.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q3 2022.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLA.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLAS_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q2 2022.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLA.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q1 2022.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLAS.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q4 2021.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLAS.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q3 2021.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLA.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLA.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q2 2021.pdf14 Aug 2025
Form 1File: FORM 1 ORCHID VILLA.pdf14 Aug 2025
Form 2File: FORM 2 ORCHID VILLA_compressed.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLAS_compressed.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q1 2021.pdf14 Aug 2025
Form 1File: FORM-1 ORCHID VILLAS.pdf14 Aug 2025
Form 2File: FORM-2 ORCHID VILLA.pdf14 Aug 2025
Form 3File: FORM 3 ORCHID VILLAS.pdf14 Aug 2025
Disclosure of Sold and Booked InventoryFile: SOLD AND UNSOLD Q4 2020.pdf14 Aug 2025
Withdrawal Update Form 1File: FORM-1 ORCHID VILLA.pdf14 Aug 2025
Withdrawal Update Form 1File: FORM-1 ORCHID VILLA.pdf14 Aug 2025
Withdrawal Update Form 2File: FORM-2 ORCHID VILLA.pdf14 Aug 2025
Withdrawal Update Form 2File: FORM-2 ORCHID VILLA.pdf14 Aug 2025
Withdrawal Update Form 3File: FORM-3 ORCHID VILLA.pdf14 Aug 2025
Withdrawal Update Form 3File: FORM-3 ORCHID VILLA.pdf14 Aug 2025

Promoter's earlier projects1

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
SPRING FIELDP99000020393KAMAN, PalgharApr 2019Certificate SignedFeb 2025Jan 1970

How this compares with Palghar

65%of this project is bookeddistrict median 25%
31%of Palghar projects moved their completion datethis one moved by 43 months
26%of Palghar registrations have lapsed or been cancelledthis one is on the register

Computed across the 3,200+ Palghar projects on ReraGenie, from their own filings.

Free monthly report: Vasai-Virar and Palghar on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep ORCHID VILLAS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near CHINCHOTI3,200+ in Palghar

2 kmORCHID VILLASCompleted 1Lapsed / revoked 2Other 1Dot size: filed unitsN

Filed coordinates, straight-line distance. 4 registered projects within 2 km.

Builder: SHARP DEVELOPERS

SHARP DEVELOPERS has 1 registration on MahaRERA, including ORCHID VILLAS. Its filings disclose 1 earlier MahaRERA project: declares 1 of 1 past projects completed on time. Read the full track record. See more projects on the Palghar district page.

Frequently asked questions

What are my rights if ORCHID VILLAS is delayed beyond 31 Dec 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of ORCHID VILLAS?

The registered promoter entity is SHARP DEVELOPERS, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in ORCHID VILLAS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against ORCHID VILLAS?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for ORCHID VILLAS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at ORCHID VILLAS?

The professionals named in the filing: Architect: HIMESH GUPTA AND ASSOCIATES; Architect: MUFFADAL MERCHANT; Engineer: MOHAMMED SHOEB BHATI; Engineer: MAHENDRA PRABHAKAR MANJREKAR; Chartered Accountant: JINESH JOSHI; Chartered Accountant: HARESH MEHTA & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in ORCHID VILLAS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About ORCHID VILLAS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save ORCHID VILLAS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.