Home / Browse projects / Thane, Maharashtra / Om Maitri

Registration lapsed Litigation declared Residential / Group Housing project

Om Maitri

By Oscar Infrastructure Pvt Ltd

RG-MH-30065 · RERA P51700030770 · Last updated on MahaRERA portal: 22 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 1 case
  • 6 complaints at MahaRERA
  • Completion date moved by 12 months
  • 2 extensions taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
7 of 11Construction stages donefurthest along: Installation of Lifts, 95%
27 of 41Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 120 documents Report an error

Om Maitri is a Residential / Group Housing project by Oscar Infrastructure Pvt Ltd in Thane, Maharashtra, registered with MahaRERA as P51700030770 on 13 Sep 2021. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 12 months from the original filing. 14 of the 41 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameOm Maitri
  • TypeResidential / Group Housing
  • Location
    • Tondon Road
    • Ram Nagar
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700030770
  • ReraGenie IDRG-MH-30065

Builder

  • NameOscar Infrastructure Pvt Ltd
  • Entity typeCompany
  • DirectorsRahul Jagannath Joshi, Harmesh Rahul Joshi, Kamesh Rahul Joshi
  • Declared earlier projects2 →

Key dates

4 months past promisethis monthRegisteredSep 2021First promiseJun 2025Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on13 Sep 2021
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 30 Jun 2025)
  • Buildings1 building record
  • Documents filed120 files

Current status

34%14 of 41 units booked
97.8%Work done, per cost certificate

Figures as on 22 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Om MaitriNA1412152641

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 22 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is Installation of Lifts, at 95%.

Om Maitri: 89% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%

Progress on shared amenities15

As on 22 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes100%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes95%
Electrical meter room, sub-station, receiving stationYes85%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed28

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots28
Closed/Covered28

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,498 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on28 Jun 2025
LandownerVillageDistrict
The Dombivli Co-Operative Housing Society LtdKurlaMumbai Suburban

Approvals and building plan

Sanctioning authorityKDMC
Permissible FSI2554.4
Proposed, not sanctioned2,554 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchMarathon Max, LBS Road, Mulund Goregaon Link Road Junction, Mulund West, Mumbai - 400080
Estimated costRs 16.54 cr
Cost incurredRs 16.18 cr
Work done97.82%
BuildingWingEstimatedIncurred
Om MaitriNARs 16.04 crRs 15.72 cr
-NARs 50.00 lakhRs 46.00 lakh

Certifying professionals and partners7

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr Deepak B Patil
ArchitectAr Mugdha M Phansalkar
EngineerMr Adity R Deshmukh
EngineerVishal Raghwani
Chartered AccountantCA KETAN V. LATHIA
Chartered AccountantHimmat Shethia
Chartered AccountantRambhia and Dedhia
PartnerRole in project
Oscar Infrastructure Pvt Ltd-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA28062501839Jun 2025 → Dec 2025

Reason as filed by the promoterDue to earlier litigation at the Kalyan Court, we faced significant difficulties in completing the project, as we were unable to sell the inventory or raise the necessary funds

EA31102518217Jun 2025 → Jun 2026

Reason as filed by the promoterWe, M/s Oscar Infrastructure Pvt. Ltd., promoter of the project “Om Maitri” (Reg. No. P51700030770), request an extension of the project registration beyond 31/12/2025 due to delays caused by the prolonged monsoon affecting external works such as plastering, waterproofing, painting, and related finishing activities. The RCC structure is completed as certified by the Architect on 30/09/2025. We seek an extension up to 30/06/2026 to complete the remaining work and ensure timely possession in full compliance with RERA provisions.

Litigation declared1

CaseCourtStatus
4 /2022District Court at KalyanClosed

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000209844Sagar Ashok MaratheRahul J Joshi28/01/2022
CC006000000292340Dilip B ChaudhariRahul Jagannath Joshi14/08/2022
CC006000000292342Milind P ZambareRahul Jagannath Joshi14/08/2022
CC006000000292343Jayashri D ChaudhariRahul Jagannath Joshi14/08/2022
CC006000000292344Jitendra K AttardeRahul Jagannath Joshi14/08/2022
CC006000000292345Rachana J AttardeRahul Jagannath Joshi14/08/2022

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Aug 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 9 Jun 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 28 Jun 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 28 Jun 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed120

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 120 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - April 26 to June 26.pdf22 Jul 2026
Withdrawal Update Form 2File: Form 2- April 26 to June 26.pdf22 Jul 2026
Withdrawal Update Form 3File: Form 3- April 26 to June 26.pdf22 Jul 2026
Form 2A (FY 2025-2026)File: Rera Form 2 - Om Maitri - March 2026.pdf12 May 2026
Form 5 (FY 2025-2026)File: Form 5 April 25 to Mar 26 Om Maitri signed.pdf12 May 2026
Withdrawal Update Form 1File: OM maitri - Form 1 - jan 26 to march 26.pdf23 Apr 2026
Withdrawal Update Form 2File: Rera Form 2 - Om Maitri - March 2026.pdf23 Apr 2026
Withdrawal Update Form 3File: Form 3 - Om Maitri Mar 26.pdf23 Apr 2026
Withdrawal Update Form 1File: Form-1 Oct-25 to Dec-25.pdf5 Jan 2026
Withdrawal Update Form 2File: Form 2 - Om Maitri Oct 25 to Dec 2025.pdf5 Jan 2026
Withdrawal Update Form 3File: Form 3 - Om Maitri Dec 25.pdf5 Jan 2026
Withdrawal Update Form 1File: Form 1 July 25 to Sept 25.pdf31 Oct 2025
Withdrawal Update Form 2File: Rera Form 2 - Om Maitri - Sep 2025.pdf31 Oct 2025
Withdrawal Update Form 3File: Form 3 - Om Maitri july 25 to sept 25..pdf31 Oct 2025
Withdrawal Update Form 1File: form 1 April 25 to june 25 signed.pdf11 Sep 2025
Withdrawal Update Form 2File: Rera Form 2 - Om Maitri June 2025 final.pdf11 Sep 2025
Withdrawal Update Form 3File: Form 3 - Om Maitri Jun 25.pdf11 Sep 2025
Form 5 (FY 2024-2025)File: Form 5 March 25.pdf2 Jul 2025
Form 5 (FY 2023-2024)File: Form 5 Fy 23-24.pdf2 Jul 2025
Form 5 (FY 2022-2023)File: Form 5 Fy 22-23.pdf2 Jul 2025
Form 5 (FY 2021-2022)File: Form 5 FY 21-22.pdf2 Jul 2025
Form 2A (FY 2022-2023)File: Rera form 2A - Om Maitri - March 2023.pdf1 Jul 2025
Form 2A (FY 2021-2022)1 Jul 2025
Building plan approval or NA orderFile: Commencement Certificates _ NA Order for plotted development.pdf28 Jun 2025
Form 1File: 1) Form 1 - Oct 21 to Dec 21.pdf28 Jun 2025
Form 2File: 2) Form 2 Oct 221 to Dec 21.pdf28 Jun 2025
Form 3File: Form 3 - Om Maitri Dec 21.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries dec 21.pdf28 Jun 2025
OthersFile: 1) initial Form 2 - Sept 21.pdf28 Jun 2025
Form 1File: 1) Form 1 ) Jan 22 to Mar 22.pdf28 Jun 2025
Form 2File: 2) Form 2 Jan 22 to Marc 22.pdf28 Jun 2025
Form 3File: 3) FORM 3 MAR 22 (1).pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Mar 22.pdf28 Jun 2025
Form 1File: 1) Form 1 Apr 22 to Jun 22.pdf28 Jun 2025
Form 2File: 2) Form 2 Apr 22 to june 22.pdf28 Jun 2025
Form 3File: 4) FORM 3 Apr 22 Jun 22.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries June 22.pdf28 Jun 2025
Form 1File: 1)Form 1 July 22 to Sept 22.pdf28 Jun 2025
Form 2File: 2) Form 2 July 22 to Sep 22.pdf28 Jun 2025
Form 3File: 3) form 3 July 22 to Sept 22.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries sept 22.pdf28 Jun 2025
Form 1File: 1) Form 1 Oct 22 to Dec 22.pdf28 Jun 2025
Form 2File: 2) Form 2 Oct 22 o Dec 22.pdf28 Jun 2025
Form 3File: 3) Form 3 - Oct 22 to Dec 22.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Dec 22.pdf28 Jun 2025
Form 1File: 1) Form 1 Jan 23 to Mar 23.pdf28 Jun 2025
Form 2File: 2) Form 2 Jan 23 to Mar 23.pdf28 Jun 2025
Form 3File: 3) Form 3 Jan 23 to Mar 23.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Mar 23.pdf28 Jun 2025
Form 1File: 1) Form 1 Apr 23 to Jun 23.pdf28 Jun 2025
Form 2File: 2) Form 2 - Apr 23 to June 2023.pdf28 Jun 2025
Form 3File: 3) Form 3 - Apr 23 to Jun 23.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries June 23.pdf28 Jun 2025
Form 1File: 1) Form 1 Apr 23 to Jun 23.pdf28 Jun 2025
Form 2File: 2) Form 2 - Apr 23 to June 2023.pdf28 Jun 2025
Form 3File: 3) Form 3 - Apr 23 to Jun 23.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries June 23.pdf28 Jun 2025
Form 1File: 1) Form 1 Oct 23 to Dec 23.pdf28 Jun 2025
Form 2File: 2) Form 2 - Oct 23 to Dec 2023.pdf28 Jun 2025
Form 3File: 3) Form 3 - Om Maitri Dec 23.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Dec 23.pdf28 Jun 2025
Form 1File: 1) Form 1 Jan 24 to March 24.pdf28 Jun 2025
Form 2File: 2) Form 2 Jan 24 to Mar 24.pdf28 Jun 2025
Form 3File: 3) Form 3 - Om Maitri Mar 24.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Mar 24.pdf28 Jun 2025
Form 1File: 1) Form 1 Apr 24 to Jun 24.pdf28 Jun 2025
Form 2File: 2 )Form 2 Apr 24 to June 24.pdf28 Jun 2025
Form 3File: 3) Form 3 - Apr 24 to Jun 24.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries June 24.pdf28 Jun 2025
Form 1File: 1) Form 1 July 24 to Sept 24.pdf28 Jun 2025
Form 2File: 2) Form 2 Apr 24 - Sep 2024.pdf28 Jun 2025
Form 3File: 3) Form 3 - Apr 24 Sep 24.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Sept 24.pdf28 Jun 2025
Form 1File: 1) Form 1 - Sept 224 to Dec 24.pdf28 Jun 2025
Form 2File: Form 2 - Sept 24 to Dec 2024.pdf28 Jun 2025
Form 3File: Form 3 - Sept 24 to Dec 24.pdf28 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold unsold inventries Dec 24.pdf28 Jun 2025
Form 1File: Form 1 Jan 25 to Mar 25.pdf28 Jun 2025
Form 2File: Form 2 Jan 25 to Mar 25.pdf28 Jun 2025
Form 3File: Form 3 - Om Maitri Mar 25.pdf28 Jun 2025

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationRegisteredStatusPromisedDelivered
OM Neelkanth DarshanP51800032659Ghatkopar East, Mumbai SuburbanJan 2022CompletedJun 2025Registered original: Dec 2023Mar 2025
OM RESIDENCYP51800026044Mulund west, Mumbai SuburbanAug 2020CompletedJun 2023Mar 2023

How this compares with Thane

34%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one moved by 12 months
23%of Thane registrations have lapsed or been cancelledthis one is among them

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Om Maitri on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Ram Nagar7,600+ in Thane

2 kmOm MaitriCompleted 88Lapsed / revoked 78Other 140Dot size: filed unitsN

Filed coordinates, straight-line distance. 306 registered projects within 2 km.

Builder: Oscar Infrastructure Pvt Ltd

Oscar Infrastructure Pvt Ltd has 1 registration on MahaRERA, including Om Maitri. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What does it mean that Om Maitri shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Om Maitri is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Om Maitri?

The registered promoter entity is Oscar Infrastructure Pvt Ltd, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Om Maitri?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Om Maitri?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Om Maitri?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Om Maitri?

The professionals named in the filing: Architect: Mr Deepak B Patil; Architect: Ar Mugdha M Phansalkar; Engineer: Mr Adity R Deshmukh; Engineer: Vishal Raghwani; Chartered Accountant: CA KETAN V. LATHIA; Chartered Accountant: Himmat Shethia. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Om Maitri?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Om Maitri. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Om Maitri to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.