Home / Developers / Oscar Infrastructure Pvt Ltd
Oscar Infrastructure Pvt Ltd: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
Oscar Infrastructure Pvt Ltd has 1 registration in this build, including Om Maitri. Its filings disclose 2 earlier MahaRERA projects: 2 of 2 past projects completed on time. Litigation is declared on 1 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| Om Maitri | Thane, Maharashtra | 41 | 34% | Registration lapsed |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| OM RESIDENCY P51800026044 | 30 Jun 2023 | 23 Mar 2023 | On time |
| OM Neelkanth Darshan P51800032659 | 30 Jun 2025 | 18 Mar 2025 | On time |
Frequently asked questions
How do I verify Oscar Infrastructure Pvt Ltd as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with Oscar Infrastructure Pvt Ltd?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make Oscar Infrastructure Pvt Ltd unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.