Home / Browse projects / Thane, Maharashtra / VASTU LUXURIA

Registered No litigation declared Residential / Group Housing project

VASTU LUXURIA

By LAUKIK DEVELOPMENT CORPORATION

RG-MH-05167 · RERA P51700050802 · Last updated on MahaRERA portal: 24 Apr 2026

Source: official MahaRERA filing

Red flags

  • Rs 30.00 crore secured on the land, in favour of BAJAJ HOUSING FINANCE LIMITED

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

1 condition is on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Thane registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedno revision filed
14 of 33Construction stages doneacross 4 buildings; furthest along: Slabs of Super Structure, 71%
167 of 520Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 148 documents Report an error

VASTU LUXURIA is a Residential / Group Housing project by LAUKIK DEVELOPMENT CORPORATION in Thane, Maharashtra, registered with MahaRERA as P51700050802 on 3 May 2023. Possession is promised by 31 Dec 2028. 353 of the 520 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete.

At a glance

Project

  • NameVASTU LUXURIA
  • TypeResidential / Group Housing
  • Location
    • Nandivali Road
    • PNT Colony
    • DOMBIVLI
    • Kalyan
    • Thane
    • 421201
  • Pincode421201
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700050802
  • ReraGenie IDRG-MH-05167

Builder

  • NameLAUKIK DEVELOPMENT CORPORATION
  • Entity typePartnership
  • PartnersYeleshwaram Sambamoorthy Ravi, Bipinchandra Laddha Patel HUF, Vanita Bipinchandra Patel, Ajit Ramchandra Thatte, Smita Shankar, Mayuresh Shankar, Smit Bipinchandra Patel, Mahendra Valji Velani, Kaushik Mahendra Velani, Satyen Mohanlal Velani, Jagdish Govind Patel, Ketan Ramniklal Patel and 7 more

Key dates

this monthRegisteredMay 2023PromisedDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on3 May 2023
  • Promised completion31 Dec 2028
  • Revised completionNone
  • Buildings4 building records
  • Documents filed148 files

Current status

68%353 of 520 units booked
52.4%Work done, per cost certificate

Figures as on 24 Apr 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA25251508158
WING BNA21211768184
WING CNA26251750175
Wing DNA33303

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 24 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 4 buildings. The stage furthest along is Slabs of Super Structure, at 71%.

WING A36%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING B62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises36%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.11%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING C62%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure71%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises36%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks65%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.11%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Wing DNot stated
ActivityProgress
ExcavationNot applicable
Basement (if any)Not applicable
Podiums (if any)Not applicable
PlinthNot applicable
Stilt FloorNot applicable
Slabs of Super StructureNot applicable
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
Sanitary Fittings within the flats / premisesNot applicable
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Progress on shared amenities15

As on 24 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed405

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots405
Closed/Covered405
BuildingClosed/CoveredTotal
WING A2626
WING B204204
WING C175175

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area7,940 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofBAJAJ HOUSING FINANCE LIMITED
Secured amountRs 30.00 crore
CERSAI search filedYes
Declared on26 Jun 2025

Approvals and building plan

Sanctioning authorityKalyan Dombivli Muncipal Corporation
Permissible FSI30091.53
Proposed, not sanctioned30,092 sq m
Buildings approved4
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank LTD Sai Plaza, Near Tilaknagar Post Office, Dombivli East, 421201
Estimated costRs 131.73 cr
Cost incurredRs 69.05 cr
Work done52.41%
BuildingWingEstimatedIncurred
WING BNARs 48.32 crRs 29.96 cr
WING CNARs 42.85 crRs 25.71 cr
WING ANARs 33.45 crRs 13.38 cr
-NARs 7.12 cr-

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectVinayak Sahasrabhudhe
EngineerS V PATEL & ASSOCIATES
Chartered AccountantJDC & ASSOCIATES LLP
Chartered AccountantPRATIK N PANDYA & CO
PartnerRole in project
LAUKIK DEVELOPMENT CORPORATION-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 16 Mar 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Apr 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Apr 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 12 Apr 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed148

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 148 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 4.pdf24 Apr 2026
Withdrawal Update Form 2File: Form 2 4.pdf24 Apr 2026
Withdrawal Update Form 3File: Form 3 4.pdf24 Apr 2026
Withdrawal Update Form 1File: Form 1.pdf5 Feb 2026
Withdrawal Update Form 2File: Form 2.pdf5 Feb 2026
Withdrawal Update Form 3File: Form 3.pdf5 Feb 2026
Withdrawal Update Form 1File: Form 1 2.pdf22 Dec 2025
Withdrawal Update Form 2File: Form 2 2.pdf22 Dec 2025
Withdrawal Update Form 3File: Form 3 2.pdf22 Dec 2025
Form 5 (FY 2024-2025)File: orm 5 Scan Laukik Development Corporation.pdf30 Sep 2025
Layout approvalFile: 01-New.pdf16 Apr 2025
Building plan approvalFile: 01-New.pdf16 Apr 2025
Copy of Layout Approval (in case of layout)File: 01-New.pdf16 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: 01-New.pdf16 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_01.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_02.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_03.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_04.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_05.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_06.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_07.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_08.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_09.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_10.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_11.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_12.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_13.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_14.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_15.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_16.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_17.pdf12 Apr 2025
Building plan approvalFile: Final Passing Plan 19-03-2025_18.pdf12 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf12 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3_compressed.pdf12 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf12 Apr 2025
Commencement Certificates / NA Order for plotted developmentFile: Full CC Letter 19-03-2025_1.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_09.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_18.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_17.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_16.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_15.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_14.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_13.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_12.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_11.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_10.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_08.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_07.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_06.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_05.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_04.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_03.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_02.pdf12 Apr 2025
Building Plan Approval / NA Order for plotted developmentFile: Final Passing Plan 19-03-2025_01.pdf12 Apr 2025
Disclosure of sold/ booked inventoryFile: Disclosure of Sold Booked Inventory mar-25_compressed.pdf12 Apr 2025
Declaration about Commencement CertificateFile: Form D Mar 25.pdf12 Apr 2025
Declaration about Commencement CertificateFile: Form D Mar 25.pdf12 Apr 2025
Details of encumbrances concerned to FinanceFile: laukik bajaj Mortgage Deed 2 P1.pdf8 Apr 2025
Details of encumbrances concerned to FinanceFile: Declaration of Finance Encumbarance.pdf8 Apr 2025
CERSAI detailsFile: Udertaking Cersai Report.pdf8 Apr 2025
Details of encumbrances concerned to LegalFile: laukik bajaj Mortgage Deed 2 P1.pdf8 Apr 2025
Details of encumbrances concerned to LegalFile: Declaration of Finance Encumbarance.pdf8 Apr 2025
Disclosure for secured/unsecured finance availed for the projectFile: Loan Disclousre.pdf8 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf8 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf8 Feb 2025
Disclosure of sold/ booked inventoryFile: Sold Unsold Letter Dec 24 red.pdf8 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 2.pdf22 Oct 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A.pdf22 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 LDCO 2.pdf22 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 1.pdf17 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf15 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf15 Oct 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Letter Sep 24.pdf15 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5 LDCO.pdf10 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf12 Aug 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2.pdf12 Aug 2024
Disclosure of sold/ booked inventoryFile: Sold Unsold Letter Jun 24.pdf12 Aug 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3.pdf12 Aug 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1.pdf3 Jun 2024

How this compares with Thane

68%of this project is bookeddistrict median 26%
24%of Thane projects moved their completion datethis one has not
23%of Thane registrations have lapsed or been cancelledthis one is on the register

Computed across the 7,600+ Thane projects on ReraGenie, from their own filings.

Free monthly report: Thane on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep VASTU LUXURIA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near PNT Colony7,600+ in Thane

2 kmVASTU LUXURIACompleted 63Lapsed / revoked 50Other 113Dot size: filed unitsN

Filed coordinates, straight-line distance. 226 registered projects within 2 km.

Builder: LAUKIK DEVELOPMENT CORPORATION

LAUKIK DEVELOPMENT CORPORATION has 1 registration on MahaRERA, including VASTU LUXURIA. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Thane district page.

Frequently asked questions

What are my rights if VASTU LUXURIA is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of VASTU LUXURIA?

The registered promoter entity is LAUKIK DEVELOPMENT CORPORATION, a partnership as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in VASTU LUXURIA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for VASTU LUXURIA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at VASTU LUXURIA?

The professionals named in the filing: Architect: Vinayak Sahasrabhudhe; Engineer: S V PATEL & ASSOCIATES; Chartered Accountant: JDC & ASSOCIATES LLP; Chartered Accountant: PRATIK N PANDYA & CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in VASTU LUXURIA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About VASTU LUXURIA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save VASTU LUXURIA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.