Registered Litigation declared Residential / Group Housing project

NYATI EXUBERANCE IV

By NYATI BUILDERS PRIVATE LIMITED

RG-MH-91066 · RERA P52100053576 · Last updated on MahaRERA portal: 27 Sep 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 2 cases
  • 2 complaints at MahaRERA
  • Completion date moved by 16 months
  • 2 extensions taken
  • Rs 60.00 crore secured on the land, in favour of Tata Capital Housing Finance Limited

Clear

  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jul 2027Possession promisedmoved 16 months from the original
14 of 33Construction stages doneacross 3 buildings; furthest along: Staircases, 98%
21 of 312Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 111 documents Report an error

NYATI EXUBERANCE IV is a Residential / Group Housing project by NYATI BUILDERS PRIVATE LIMITED in Pune, Maharashtra, registered with MahaRERA as P52100053576 on 10 Nov 2023. Possession is promised by 31 Jul 2027. The completion date has moved by 16 months from the original filing. 291 of the 312 units on this registration are recorded sold or booked, and 14 of 33 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameNYATI EXUBERANCE IV
  • TypeResidential / Group Housing
  • Location
    • UNDRI
    • Haveli
    • Pune
    • 411060
  • Pincode411060
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100053576
  • ReraGenie IDRG-MH-91066

Builder

  • NameNYATI BUILDERS PRIVATE LIMITED
  • Entity typeCompany
  • CINU45202MH1996PTC102620
  • GSTIN27AAACN6418N1Z4
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • Managing DirectorsNITIN DWARKADAS NYATI, NITIN DWARKADAS NYATI
  • Other registrations20 more →
  • Completed9 of 21
  • No longer live6 lapsed, de-registered or revoked
  • Declared earlier projects18 →

Key dates

this monthRegisteredNov 2023First promiseMar 2026Revised toJul 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on10 Nov 2023
  • Promised completion31 Jul 2027
  • Revised completionRevised to 31 Jul 2027 (originally 31 Mar 2026)
  • Buildings3 building records
  • Documents filed111 files

Current status

93%291 of 312 units booked
86.0%Work done, per cost certificate

Figures as on 27 Sep 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
BLDG C3NA28261040104
BLDG C4NA28261040104
BLDG C5NA28261040104

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 27 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

14 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Staircases, at 98%.

BLDG C387%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Sanitary Fittings within the flats / premises96%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks94%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.89%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.81%
BLDG C487%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises94%
Sanitary Fittings within the flats / premises98%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.88%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.84%
BLDG C552%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure68%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises23%
Sanitary Fittings within the flats / premises14%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks34%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.12%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.21%

Progress on shared amenities15

As on 27 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes10%
Landscaping & Tree PlantingYes30%
Street LightingYes0%
Community BuildingsYes0%
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingYes0%

Parking filed984

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots984
Closed/Covered984
BuildingClosed/CoveredTotal
BLDG C3328328
BLDG C4328328
BLDG C5328328

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area1,400 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofTata Capital Housing Finance Limited
Secured amountRs 60.00 crore
CERSAI search filedYes
Declared on14 Jul 2025

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI26507.51
Proposed, not sanctioned26,508 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch9/2 Kalpataru Gardens, Boat Club Road, Pune 411001
Estimated costRs 67.25 cr
Cost incurredRs 57.80 cr
Work done85.95%
BuildingWingEstimatedIncurred
BLDG C3NARs 22.48 crRs 22.37 cr
BLDG C5NARs 22.48 crRs 13.26 cr
BLDG C4NARs 22.29 crRs 22.18 cr

Certifying professionals and partners9

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectEthique Architects & Associates
ArchitectSHIRISH DASNURKAR and ASSOCIATES
EngineerAMOL SHITOLE
EngineerVishwanath Dhande
EngineerSatish Marathe
EngineerKETAN JAYKAR
Chartered AccountantP N Thombre & Associates
Chartered AccountantMilani & Associates
Chartered AccountantMilani Gattani & Co.
PartnerRole in project
NYATI BUILDERS PRIVATE LIMITED-

Extensions applied for2

A revised date filed with the regulator does not change the possession date in your agreement for sale.

P52100053576/WarMar 2026 → Jul 2027

Reason as filed by the promoterNA

EA11032620182Mar 2026 → Mar 2027

Reason as filed by the promoterDelay in obtaining the OC (As per Declaration)

Litigation declared2

CaseCourtStatus
1653/2013Civil Judge Senior Division PuneOngoing
1653/2013CIVIL COURTOngoing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
SM12600411Ram GawaliNYATI BUILDERS PRIVATE LIMITED17/06/2026
SM12600420Ram GawaliNYATI BUILDERS PRIVATE LIMITED19/06/2026

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 19 Oct 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 24 Oct 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 24 Oct 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 24 Oct 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Jul 2027

Documents filed111

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 111 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 5 (FY 2025-2026)File: Form 5 Nyati Exuberance IV.pdf27 Sep 2026
Withdrawal Update Form 1File: FORM 1.pdf20 Jul 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Jul 2026
Withdrawal Update Form 3File: FORM 3.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Nyati Exuberance IV Form 2A 2025-2026.pdf23 Apr 2026
Withdrawal Update Form 1File: FORM 1.pdf20 Apr 2026
Withdrawal Update Form 2File: FORM 2.pdf20 Apr 2026
Withdrawal Update Form 3File: FORM 3.pdf20 Apr 2026
Form 2A (FY 2023-2024)File: FORM 2A.pdf25 Mar 2026
Withdrawal Update Form 1File: FORM 1.pdf21 Jan 2026
Withdrawal Update Form 2File: FORM 2.pdf21 Jan 2026
Withdrawal Update Form 3File: FORM 3.pdf21 Jan 2026
Withdrawal Update Form 1File: FORM 1.pdf28 Oct 2025
Withdrawal Update Form 2File: FORM 2.pdf28 Oct 2025
Withdrawal Update Form 3File: FORM 3.pdf28 Oct 2025
Form 2A (FY 2024-2025)File: Nyati Exuberance IV Form 2A 2024-2025.pdf23 Sep 2025
Form 5 (FY 2024-2025)File: Nyati Exuberance IV Form 5.pdf23 Sep 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Nyati Exuberance IV Form 3.pdf17 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf11 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf9 Apr 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf8 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf20 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Exuberance IV CA Certificate.pdf4 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf3 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf3 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Exuberance IV.pdf18 Dec 2024
Disclosure of sold/ booked inventoryFile: 5 Disclosure of sold_ booked inventory.pdf18 Dec 2024
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Format A.pdf3 Dec 2024
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: Format B.pdf3 Dec 2024
Details of encumbrances concerned to FinanceFile: Exuberance Finance Declarartion.pdf25 Nov 2024
Details of encumbrances concerned to LegalFile: Exuberance Finance Declarartion.pdf25 Nov 2024
CERSAI detailsFile: CERSAI Report Exuberance 22082024.pdf23 Nov 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf12 Nov 2024
Layout approvalFile: 1_13 Layout.pdf24 Oct 2024
Building plan approvalFile: 2_13 Parking Layout.pdf24 Oct 2024
Building plan approvalFile: 5_13 C3 Typical Floor.pdf24 Oct 2024
Building plan approvalFile: 6_13 C4 Typical Floor.pdf24 Oct 2024
Building plan approvalFile: 7_13 C5 Typical Floor.pdf24 Oct 2024
Building plan approvalFile: 8_13 C3 C4 C5 Elevation.pdf24 Oct 2024
Building plan approvalFile: 9_13 C3 C4 C5 Section AA.pdf24 Oct 2024
Building plan approvalFile: 10_13 C3 C4 C5 Section CC.pdf24 Oct 2024
Copy of Layout Approval (in case of layout)File: 1_13 Layout.pdf24 Oct 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 7_13 C5 Typical Floor.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 10_13 C3 C4 C5 Section CC.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 9_13 C3 C4 C5 Section AA.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 8_13 C3 C4 C5 Elevation.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 6_13 C4 Typical Floor.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 5_13 C3 Typical Floor.pdf24 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: 2_13 Parking Layout.pdf24 Oct 2024
Declaration about Commencement CertificateFile: Declaration about commencement certificate - Exuberance-IV.pdf24 Oct 2024
Proforma of Agreement for saleFile: EXUBERANCE IV UNIT AGREE 22102024 CLEAN.pdf23 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf22 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf18 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf18 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Nyati Exuberance IV - Form 5.pdf7 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf12 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FPRM 2.pdf12 Jul 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf12 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM 2A.pdf18 May 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf20 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf11 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: NBPL Form 3 - Exuberance IV_11zon.pdf11 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf8 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf8 Apr 2024
Disclosure of sold/ booked inventoryFile: DISCLOSURE OF SOLD UNSOLD INVENTORY.pdf19 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: FORM 1.pdf16 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM 2.pdf16 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3.pdf16 Jan 2024
Details of encumbrances concerned to FinanceFile: Undertaking Exuberance IV.pdf14 Dec 2023
Details of encumbrances concerned to LegalFile: Undertaking Exuberance IV.pdf14 Dec 2023
CERSAI detailsFile: CERSAI REPORT EXUBERANCE.pdf5 Dec 2023
Other - LegalFile: REV DECLARATION ABOUT CC.PDF30 Oct 2023
Other - LegalFile: SELF DECLARATION REGARDING CERSAI.PDF30 Oct 2023
Other - LegalFile: BP SANSTION LAYOUT.PDF30 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Exuburance IV.pdf27 Oct 2023

Promoter's earlier projects18

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

14 delivered on promise4 delivered late
ProjectLocationFlatsStatusPromisedDelivered
Nyati Enchante IIIVadgaonsheri Pune50CompletedMar 2021Mar 2021
Nyati Enchante IIVadgaonsheri Pune65CompletedMar 2021Mar 2021
Nyati Evara IIUndri Pune96CompletedSep 2020Sep 2020
Nyati Enchante IVadgaonsheri Pune50CompletedSep 2020Sep 2020
Nyati Evara IUndri Pune240CompletedJun 2019Jun 2019
Nyati Meadows - B8, B9vadgaonsheri Pune76CompletedJul 2017Apr 2017
Nyati EvitaLohegaon Pune240CompletedJul 2017Oct 2016
Nyati EurekaKharadi Pune38CompletedJul 2017Apr 2017
Nyati EmporiusBaner Pune98CompletedJul 2017Mar 2017
Nyati WindchimesUndri Pune200CompletedMar 2017Jun 2016
Nyati Equatorial-IIBavdhan Bk Pune312CompletedMar 2017Late, Apr 2017
Nyati Unitree ICTS No 1995 1996B Pune nagar Road Yerwada Pune142CompletedDec 2016Oct 2015
Nyati EpitomeMohammedwadi Pune112CompletedDec 2016Oct 2016
Nyati EbonyUndri Pune188CompletedMar 2016Dec 2015
Nyati Equatorial-IBavdhan bk pune264CompletedDec 2015Late, Jul 2016
Nyati Ethos-IIUndri Pune152CompletedSep 2015Mar 2015
Nyati Ethos-IUndri Pune165CompletedDec 2014Late, Aug 2015
Nyati EsplanadeBavdhan Bk Pune253CompletedJan 2013Late, Jan 2014

How this compares with Pune

93%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 16 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NYATI EXUBERANCE IV on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near UNDRI13,700+ in Pune

2 kmNYATI EXUBERANCE IVCompleted 85Lapsed / revoked 28Other 89Dot size: filed unitsN

Filed coordinates, straight-line distance. 202 registered projects within 2 km.

Builder: NYATI BUILDERS PRIVATE LIMITED

NYATI BUILDERS PRIVATE LIMITED has 21 registrations on MahaRERA, including NYATI EVARA I and NYATI UNITREE II. Its filings disclose 18 earlier MahaRERA projects: declares 14 of 18 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if NYATI EXUBERANCE IV is delayed beyond 31 Jul 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NYATI EXUBERANCE IV?

The registered promoter entity is NYATI BUILDERS PRIVATE LIMITED, a company as per the filing. Its CIN U45202MH1996PTC102620 and GSTIN 27AAACN6418N1Z4 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NYATI EXUBERANCE IV?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against NYATI EXUBERANCE IV?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for NYATI EXUBERANCE IV?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NYATI EXUBERANCE IV?

The professionals named in the filing: Architect: Ethique Architects & Associates; Architect: SHIRISH DASNURKAR and ASSOCIATES; Engineer: AMOL SHITOLE; Engineer: Vishwanath Dhande; Engineer: Satish Marathe; Engineer: KETAN JAYKAR. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NYATI EXUBERANCE IV?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NYATI EXUBERANCE IV. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NYATI EXUBERANCE IV to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.