NYATI BUILDERS PRIVATE LIMITED: RERA track record
Company ยท attribution by exact filing name, entity resolution in progress
NYATI BUILDERS PRIVATE LIMITED has 21 registrations in this build, including NYATI EVARA I and NYATI UNITREE II. Its filings disclose 18 earlier MahaRERA projects: 14 of 18 past projects completed on time. Litigation is declared on 6 of its registrations.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| NYATI EVARA I | Pune, Maharashtra | - | - | Completed |
| NYATI UNITREE II | Pune, Maharashtra | - | - | Completed |
| NYATI ETHOS I - A1-Part | Pune, Maharashtra | - | - | De-registered |
| NYATI ETHOS I - B3 | Pune, Maharashtra | - | - | De-registered |
| NYATI ENCHANTE I | Maharashtra | - | - | Completed |
| NYATI ERICA | Pune, Maharashtra | - | - | Completed |
| NYATI ENCHANTE III | Maharashtra | - | - | Completed |
| NYATI EVARA II | Pune, Maharashtra | - | - | Completed |
| NYATI ENCHANTE II | Maharashtra | - | - | Completed |
| NYATI EXUBERANCE I | Pune, Maharashtra | - | - | Registration lapsed |
| NYATI EXUBERANCE III | Pune, Maharashtra | - | - | Completed |
| NYATI DEFENCE ENCLAVE I | Pune, Maharashtra | - | - | Registration lapsed |
| NYATI DEFENCE ENCLAVE II | Pune, Maharashtra | - | - | Completed |
| NYATI DEFENCE ENCLAVE III | Pune, Maharashtra | - | - | Registration lapsed |
| NYATI EXUBERANCE II | Pune, Maharashtra | - | - | Registration lapsed |
| NYATI EMERALD I | Pune, Maharashtra | 727 | 81% | Registered |
| NYATI EXUBERANCE IV | Pune, Maharashtra | 312 | 85% | Registered |
| NYATI EMERALD II | Pune, Maharashtra | 160 | 89% | Registered |
| NYATI EMERALD III | Pune, Maharashtra | 290 | 56% | Registered |
| NYATI EVOQUE | Maharashtra | 217 | 19% | Registered |
| NYATI ELENOR | Pune, Maharashtra | 256 | 4% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| Nyati Esplanade | 31 Jan 2013 | 10 Jan 2014 | +11 months |
| Nyati Ethos-I | 30 Dec 2014 | 31 Aug 2015 | +8 months |
| Nyati Ethos-II | 30 Sep 2015 | 10 Mar 2015 | On time |
| Nyati Equatorial-I | 30 Dec 2015 | 20 Jul 2016 | +7 months |
| Nyati Ebony | 31 Mar 2016 | 10 Dec 2015 | On time |
| Nyati Epitome | 30 Dec 2016 | 24 Oct 2016 | On time |
| Nyati Unitree I | 31 Dec 2016 | 3 Oct 2015 | On time |
| Nyati Equatorial-II | 31 Mar 2017 | 29 Apr 2017 | +1 months |
| Nyati Windchimes | 31 Mar 2017 | 30 Jun 2016 | On time |
| Nyati Emporius | 31 Jul 2017 | 30 Mar 2017 | On time |
| Nyati Evita | 31 Jul 2017 | 10 Oct 2016 | On time |
| Nyati Eureka | 31 Jul 2017 | 28 Apr 2017 | On time |
Frequently asked questions
How do I verify NYATI BUILDERS PRIVATE LIMITED as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with NYATI BUILDERS PRIVATE LIMITED?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
Does the declared litigation make NYATI BUILDERS PRIVATE LIMITED unsafe to buy from?
Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.
Data from official MahaRERA filings. Spotted a wrongly attributed project? Report a mismatch.