ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / NEW INDIA HEIGHTS

Registration lapsed No litigation declared Others project

NEW INDIA HEIGHTS

By NEW INDIA CONSTRUCTION COMPANY

RG-MH-29735 · RERA P51800029165 · Last updated on MahaRERA portal: 16 May 2023

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 34 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2023Possession promised34 months past this date
0 of 11Construction stages donefurthest along: Excavation, 0%
0Complaints at MahaRERAon this registration
Jump to the 17 documents Report an error

NEW INDIA HEIGHTS is a Others project by NEW INDIA CONSTRUCTION COMPANY in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800029165 on 3 May 2021. Possession was promised by 31 Dec 2023 and is now 34 months past that date.

At a glance

Project

  • NameNEW INDIA HEIGHTS
  • TypeOthers
  • Location
    • OLD POLICE STATION ROAD
    • ANDHER EAST NEAR RAILWAY STATION
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • RERA no.P51800029165
  • ReraGenie IDRG-MH-29735

Builder

  • NameNEW INDIA CONSTRUCTION COMPANY
  • Entity typePartnership
  • GSTIN27AAAFN0287E1ZI
  • GSTIN is from this promoter's other MahaRERA registrations. This project's own filing does not repeat it.
  • PartnersNIRANJAN POPATLAL SHAH, KUNTAL NIRANJAN SHAH, MINESH NIRANJAN SHAH, HETANSHU CHIRAG SHAH, BHAVIK NIRANJAN SHAH
  • Other registrations10 more →
  • Completed2 of 11
  • No longer live4 lapsed, de-registered or revoked
  • Declared earlier projects8 →

Key dates

34 months past promisethis monthRegisteredMay 2021PromisedDec 2023

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on3 May 2021
  • Promised completion31 Dec 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed17 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
NEW INDIA HEIGHTSNA170000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 16 May 2023, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 0%.

NEW INDIA HEIGHTS: 0% average across the applicable activities

ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 16 May 2023, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,255 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI3727.71
Proposed, not sanctioned631 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch116,SAURABH ,ANDHERI EAST MUMBAI-400069

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectKULIN B PATRAWALA
Engineershri dhaval h shah
Chartered AccountantY R GOSWAMI AND CO
PartnerRole in project
NEW INDIA CONSTRUCTION COMPANY-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Apr 2021
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Apr 2021
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Apr 2021
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 29 Apr 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed17

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Proforma of Agreement for saleFile: 2337 RERA Agreement for Sale-19042021.pdf16 May 2023
Building plan approvalFile: IOD.pdf29 Apr 2021
Layout approvalFile: jeevandham plan 1.pdf29 Apr 2021
Building plan approvalFile: jeevandham plan 1.pdf29 Apr 2021
Copy of the legal title reportFile: FormatA Legal Title Report.pdf29 Apr 2021
Details of encumbrancesFile: Search Report.pdf29 Apr 2021
Details of encumbrancesFile: Search Report1.pdf29 Apr 2021
Copy of Layout Approval (in case of layout)File: jeevandham plan 1.pdf29 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: IOD.pdf29 Apr 2021
Building Plan Approval / NA Order for plotted developmentFile: jeevandham plan 1.pdf29 Apr 2021
Commencement Certificates / NA Order for plotted developmentFile: 2273904_FirstCC_signed.pdf29 Apr 2021
Proforma of Allotment letterFile: alloment ment letter.pdf29 Apr 2021
Proforma of Allotment letterFile: 2337 RERA Agreement for Sale-19042021.pdf29 Apr 2021
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Certificate-compressed.pdf15 Apr 2021
Declaration in FORM BFile: FROM B.pdf5 Apr 2021
PAN CardFile: PAN NEW INDIA CONST.pdf3 Apr 2021
Details of encumbrancesFile: 2337 Title Certificate.pdf3 Apr 2021

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

8 not delivered by the promised date
ProjectLocationFlatsRegisteredStatusPromisedDelivered
VISHAKHA HEIGHTS AND VISHAKHA REGENCYP51800046013MULUND EAST, Mumbai Suburban108Jun 2022OngoingDec 2025Not delivered
ASHTAVINAYAK APARTMENTSP51800049920ANDHERI EAST, Mumbai Suburban173Mar 2023OngoingDec 2025Not delivered
AMEY APARTMENTSP51800045221ANDHERI EAST, Mumbai Suburban69May 2022OngoingDec 2025Not delivered
JITEN CHSP51800032184ANDHERI WEST, Mumbai Suburban-Dec 2021Certificate SignedDec 2024Not delivered
ANDHERI SHILPA CHSP51800034461VILLAGE GUNDAVALI, Mumbai Suburban-Apr 2022Certificate SignedDec 2024Not delivered
ASHOK SMRUTIP51800004012Andheri, Mumbai Suburban-Aug 2017Certificate SignedDec 2024Not delivered
TRIUMPH TOWERSP51800027364GOREGAON(W),NEXT TO SARAF COLLEGE, Mumbai Suburban-Dec 2020OngoingMay 2024Registered original: Jun 2023Not delivered
M/S CHIRAG A SHAH PARTNER NEW INDIA CONSTRUCTION COMPANY CA TO KESHAV APARTMENTSP51800046722VILE PARLE WEST, Mumbai Suburban-Sep 2022Certificate SignedMar 2024Not delivered

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep NEW INDIA HEIGHTS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near ANDHER EAST NEAR RAILWAY STATION6,700+ in Mumbai Suburban

Builder: NEW INDIA CONSTRUCTION COMPANY

NEW INDIA CONSTRUCTION COMPANY has 11 registrations on MahaRERA, including ASHOKHEIGHTS and ASHOK SMRUTI. Its filings disclose 8 earlier MahaRERA projects, none completed yet. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that NEW INDIA HEIGHTS shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if NEW INDIA HEIGHTS is delayed beyond 31 Dec 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of NEW INDIA HEIGHTS?

The registered promoter entity is NEW INDIA CONSTRUCTION COMPANY, a partnership as per the filing. Its GSTIN 27AAAFN0287E1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in NEW INDIA HEIGHTS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for NEW INDIA HEIGHTS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at NEW INDIA HEIGHTS?

The professionals named in the filing: Architect: KULIN B PATRAWALA; Engineer: shri dhaval h shah; Chartered Accountant: Y R GOSWAMI AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in NEW INDIA HEIGHTS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About NEW INDIA HEIGHTS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save NEW INDIA HEIGHTS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.