Nityanand Nagar Vibhag IV Cooperative Housing Society Limited

By BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED

RG-MH-20286 · RERA P51800012464 · Last updated on MahaRERA portal: 23 Jun 2026

Source: official MahaRERA filing

Red flags

  • 6 complaints at MahaRERA
  • Completion date moved by 72 months
  • 4 extensions taken

Clear

  • No litigation declared
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

3 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2027Possession promisedmoved 72 months from the original
40 of 44Construction stages doneacross 4 buildings; furthest along: Podiums (if any), 0%
181 of 308Units unsoldnot recorded sold or booked
6Complaints at MahaRERAon this registration
Jump to the 172 documents Report an error

Nityanand Nagar Vibhag IV Cooperative Housing Society Limited is a Residential / Group Housing project by BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012464 on 1 Sep 2017. Possession is promised by 30 Jun 2027. The completion date has moved by 72 months from the original filing. 127 of the 308 units on this registration are recorded sold or booked, and 40 of 44 construction stages are filed complete. 6 complaints are on record with the regulator.

At a glance

Project

  • NameNityanand Nagar Vibhag IV Cooperative Housing Society Limited
  • TypeResidential / Group Housing
  • Location
    • Swami Nityanand road
    • Andheri East
    • Andheri
    • Mumbai Suburban
    • 400069
  • Pincode400069
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012464
  • ReraGenie IDRG-MH-20286

Builder

  • NameBAJAJ INTERNATIONAL REALTY PRIVATE LIMITED
  • Entity typeCompany
  • CINU93000MH2010PTC217139
  • GSTIN27AAECB3060C1Z7
  • Managing DirectorBALKISHAN GIRIRAJ MUCHHAL
  • Other registrations1 more →
  • Completed1 of 2

Key dates

this monthRegisteredSep 2017First promiseJun 2021Revised toJun 2027

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on1 Sep 2017
  • Promised completion30 Jun 2027
  • Revised completionRevised to 30 Jun 2027 (originally 30 Jun 2021)
  • Buildings4 building records
  • Documents filed172 files

Current status

41%127 of 308 units booked
97.1%Work done, per cost certificate

Figures as on 23 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing - ANA181483083
Wing - BNA18083083
Wing - CNA18083083
Wing - DNA16059059

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 23 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

40 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Podiums (if any), at 0%.

Wing - A91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - B91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - C91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Wing - D91%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 23 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes100%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes100%
Street LightingNoNot applicable
Community BuildingsYes100%
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes100%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed366

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots366
Closed/Covered349
Open Space17
BuildingClosed/CoveredOpen SpaceTotal
Wing - A77683
Wing - B83891
Wing - C1143117
Wing - D75075

Land and ownership

Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,362 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on1 Aug 2025

Approvals and building plan

Sanctioning authorityMaharashtra Housing And Area Development Authority
Permissible FSI28633.97
Proposed, not sanctioned27,870 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAHURA CENTER GROUND FLOOR MAHAKALI CAVES ROAD ANDHERI EAST MUMBAI 400093
Estimated costRs 152.35 cr
Cost incurredRs 147.95 cr
Work done97.11%
BuildingWingEstimatedIncurred
Wing - ANARs 56.60 crRs 53.52 cr
Wing - BNARs 43.84 crRs 42.74 cr
Wing - DNARs 38.50 crRs 38.49 cr
Wing - CNARs 8.96 crRs 8.75 cr
-NARs 4.44 crRs 4.44 cr

Certifying professionals and partners5

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMiti Designers & Planners
ArchitectUB Architects
EngineerSuman Kuttan
Chartered AccountantAML Agrawal and Company
Chartered AccountantR.S Dani & Co.
PartnerRole in project
BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED-

Extensions applied for4

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800006341Jun 2021 → Jun 2022

Reason as filed by the promoterThe under-construction project got delayed due to non-availability of construction materials, labour, transportation, etc due to the pandemic. Lockdown Restrictions have disrupted the supply chains, creating a scarcity of raw materials. Also, the migratory labour are still not available for a quick kick-start post unlock, as various Government schemes like MNREGA and PM Gareeb Kalyan Anna Yojana, which provides minimum assured wages and free essential items at the doorstep respectively, will not let them move out to earn a livelihood. Also, we had to halt our construction recently as a few of

EXT51800013820Jun 2021 → Dec 2023

Reason as filed by the promoter1. Our project comprising of wing A, B, C and D have total 177 tenant and flats for sale are 131 out of which 101 flats are sold and 30 are unsold. 2. We had received CC for wing B, C and D in year 2017 with approved plans as on 03.02.2017 3. Thereafter we had sent letter to society to vacate the premises and accordingly the tenants had fully vacated the site but the Post office situated in wing A was not vacated. 4. We had started the construction work for wing B, C and D but could not construct wing A as Post office was not vacated till year 2018 5. Further on April 2019 Post office got vaca

EXT51800025285Jun 2021 → Dec 2025

Reason as filed by the promoterThe primary reason for this extension request is that we have obtained the Occupancy Certificate (OC) for 307 out of 308 flats in the complex. The possession for these flats has been handed over to the original members and sale customers. However, the OC for Flat No. 805, located on the 8th Floor of Wing A, is still pending. This delay is due to the ongoing process of executing the Deed of Supplemental Lease between MHADA and Nityanand Nagar Vibhag IV Cooperative Housing Society Limited (Society). Once the Deed of Supplemental Lease is executed, MHADA will issue the OC for Flat No. 805. It is

EA02052620811Jun 2021 → Jun 2027

Reason as filed by the promoterThe project has received Occupancy Certificate for 307 out of 308 flats. The Occupancy Certificate for Flat No. 805, Wing A (the only pending unit and currently unsold), is awaiting execution of the Deed of Supplemental Lease between MHADA and Nityanand Nagar Vibhag IV Cooperative Housing Society Ltd. This process is entirely beyond the control of the Promoter. Upon execution of the said lease deed, MHADA shall issue the Occupancy Certificate for the pending unit. Since the timeline for completion of this process and issuance of the final Occupancy Certificate remains uncertain, the Promoter i

Complaints filed with MahaRERA6

Case no.ComplainantRespondentFiled
CC006000000000958ADHVIK MAHAJANM/s Bajaj International Realty Pvt Ltd30/09/2017
CC006000000161393Santosh Chandra TandonBajaj International Realty Pvt limited03/11/2019
CC006000000292463Prerna Takshesh ShroffBajaj International Realty Pvt. Ltd.29/08/2022
CC006000000303712BAKUL RAMESHCHANDRA DALALBAJAJ INTERNATIONAL REALTY PVT LTD17/12/2022
CC006000000374815PINA RAJENDRA SHAHBAJAJ INTERNATIONAL REALTY PVT. LTD.16/03/2023
CC12500735AMAR NILKANTH SHUKLABAJAJ INTERNATIONAL REALTY PRIVATE LIMITED04/03/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 26 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Oct 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Oct 2020
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 14 Oct 2021Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 20 Feb 2024

Documents filed172

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 172 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Bajaj Emerald_ Form 1_Q4 FY 25_26.pdf23 Jun 2026
Withdrawal Update Form 2File: Bajaj Emerald_ Form 2_Q4 FY 25_26.pdf23 Jun 2026
Withdrawal Update Form 3File: Bajaj Emerald_ Form 3_Q4 FY 25_26.pdf23 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A 25_26 Bajaj Emerald_Signed.pdf19 May 2026
Form 2A (FY 2024-2025)File: Form 2A 24_25 Bajaj Emerald_Signed.pdf19 May 2026
Form 5 (FY 2025-2026)File: Form 5 FY 2025 26 Bajaj Emerald.pdf19 May 2026
Withdrawal Update Form 1File: Form 1 Bajaj Emerald as on 30092025.pdf19 Jan 2026
Withdrawal Update Form 2File: Form 2 Q3 25 26 Bajaj Emerald.pdf19 Jan 2026
Withdrawal Update Form 3File: Form 3_Q3 25 26_Bajaj Emerald_compressed.pdf19 Jan 2026
Withdrawal Update Form 1File: Form 1 Bajaj Emerald as on 30092025.pdf13 Nov 2025
Withdrawal Update Form 1File: Form 1 Bajaj Emerald as on 30092025.pdf13 Nov 2025
Withdrawal Update Form 2File: Signed Form 2 BIRPL Q2 FY 25 26.pdf13 Nov 2025
Withdrawal Update Form 2File: Signed Form 2 BIRPL Q2 FY 25 26.pdf13 Nov 2025
Withdrawal Update Form 3File: Emerald form 3 as on 30092025.pdf13 Nov 2025
Withdrawal Update Form 3File: Emerald form 3 as on 30092025.pdf13 Nov 2025
Form 5 (FY 2024-2025)File: Signed Form 5 of BIRPL FY 24-25 Emerald.pdf13 Oct 2025
Withdrawal Update Form 1File: Form 1.pdf7 Aug 2025
Withdrawal Update Form 2File: BAJAJ EMERALD FORM 2 30 06 25.pdf7 Aug 2025
Withdrawal Update Form 3File: SIGNED FORM-3 OF BAJAJ INTERNATIONAL REALTY PVT LTD Q1 FY 25-26.pdf7 Aug 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1_Q4 of FY 24-25.pdf24 Apr 2025
Certificates of CA (Form 3)File: Form 3_Q4 of FY 24-25_compressed.pdf24 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2_Q4 of FY 24-25.pdf24 Apr 2025
Disclosure of sold/ booked inventoryFile: DOS.pdf24 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald_Form 1 Architect Certificate dt 311224.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 311224.pdf22 Jan 2025
Certificates of CA (Form 3)File: BAJAJ EMERALD_FORM 3_CA_Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald_Form 1 Architect Certificate dt 311224.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 311224.pdf22 Jan 2025
Certificates of CA (Form 3)File: BAJAJ EMERALD_FORM 3_CA_Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald_Form 1 Architect Certificate dt 311224.pdf22 Jan 2025
Certificates of CA (Form 3)File: BAJAJ EMERALD_FORM 3_CA_Certificate 31122024_11zon.pdf22 Jan 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 311224.pdf22 Jan 2025
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD - DISCLOSURE OF INVENTORY 300924.pdf17 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 26 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf10 Dec 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 25 Certificates of Engineer (Form 2)(Mandatory for only ongoing project).pdf10 Dec 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: FORM -2A BAJAJ EMERALD FY 2023-24.pdf10 Dec 2024
Declaration in FORM BFile: Form B.pdf2 Dec 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald_Form 1 Architect Certificate dt 300924.pdf29 Nov 2024
Certificates of CA (Form 3)File: Signed Form 3 Rera BIRPL 30062024.pdf29 Nov 2024
Certificates of CA (Form 3)File: Signed Form 3 Rera BIRPL 30092024.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 300924.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Form 2 RERA Shubhada Sep-2024.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Signed Form 2 RERA Shubhada June-2024.pdf29 Nov 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 300624.pdf29 Nov 2024
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY 281124.pdf29 Nov 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - BAJAJ EMERALD FY 2023-24 (SD).pdf7 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5 - BAJAJ EMERALD FY 2023-24 (SD).pdf7 Oct 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf31 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Self-Delaration - BE-NNIV JULY2024.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Self-Delaration - BE-NNIV JULY2024.pdf26 Jul 2024
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DOS Compressed.pdf26 Jul 2024
Certificates of CA (Form 3)File: Self-Delaration - BE-NNIV JULY2024.pdf26 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf26 Apr 2024
Disclosure of sold/ booked inventoryFile: Disclosure Of Inventory.pdf26 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf24 Apr 2024
Certificates of CA (Form 3)File: FORM 3 (4).pdf24 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OCCUPATION CERTIFICATE - 16 FEBRUARY 2024 .pdf20 Feb 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald Form 1 Architect Certificate 31dec23.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 31dec23_compressed.pdf27 Jan 2024
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY 31dec23_compressed.pdf27 Jan 2024
Certificates of CA (Form 3)File: BAJAJ EMERALD_FORM 3_CA_Certificate 31dec23_compressed.pdf27 Jan 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALDFORM 2300923.pdf4 Nov 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: BAJAJ EMERALD FORM 2A - QUALITY ASSURANCE CERT SEPT2023.pdf4 Nov 2023
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY 300923.pdf4 Nov 2023
Certificates of CA (Form 3)File: BAJAJ EMERALDFORM 3CACertificate 30092023.pdf4 Nov 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5 - BAJAJ EMERALD FY 2022-23 (SD).pdf10 Oct 2023
Certificates of CA (Form 3)File: BAJAJ EMERALDFORM 3CACertificate 30062023.pdf8 Aug 2023
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY 300623.pdf7 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald Form 1 Architect Certificate dt 30 06 23.pdf5 Aug 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD FORM 2 30 06 23.pdf5 Aug 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Bajaj Emerald_Form 1 Architect Certificate 31-03-23.pdf22 May 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: BAJAJ EMERALD_FORM 2_ 31-03-23 (Revised).pdf22 May 2023
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY 31-03-23 (3).pdf22 May 2023
Certificates of CA (Form 3)File: BAJAJ EMERALD_FORM 3_CA_Certificate 31-03-2023.pdf22 May 2023
Disclosure of sold/ booked inventoryFile: BAJAJ EMERALD DISCLOSURE OF INVENTORY.pdf1 Feb 2023
PAN CardFile: PAN CARD BIRPL.pdf31 Dec 2022
Details of encumbrances concerned to FinanceFile: NON ENCUMBERANCE CERTIFICATE BAJAJ EMERALD DEC 2022.pdf31 Dec 2022
Details of encumbrances concerned to LegalFile: NON ENCUMBERANCE CERTIFICATE BAJAJ EMERALD DEC 2022.pdf31 Dec 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: BAJAJ EMERALD FORM 2A QUALITY ASSURANCE CERT MAR2020.pdf31 Dec 2022

How this compares with Mumbai Suburban

41%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 72 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Nityanand Nagar Vibhag IV Cooperative Housin on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri East6,700+ in Mumbai Suburban

2 kmNityanand Nagar Vibhag ICompleted 147Lapsed / revoked 85Other 163Dot size: filed unitsN

Filed coordinates, straight-line distance. 395 registered projects within 2 km.

Builder: BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED

BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED has 2 registrations on MahaRERA, including Bajaj Enchante - Panchsheel CHSL and Nityanand Nagar Vibhag IV Cooperative Housing Society Limited. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Nityanand Nagar Vibhag IV Cooperative Housing Society Limited is delayed beyond 30 Jun 2027?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

The registered promoter entity is BAJAJ INTERNATIONAL REALTY PRIVATE LIMITED, a company as per the filing. Its CIN U93000MH2010PTC217139 and GSTIN 27AAECB3060C1Z7 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

The professionals named in the filing: Architect: Miti Designers & Planners; Architect: UB Architects; Engineer: Suman Kuttan; Chartered Accountant: AML Agrawal and Company; Chartered Accountant: R.S Dani & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Nityanand Nagar Vibhag IV Cooperative Housing Society Limited?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Nityanand Nagar Vibhag IV Cooperative Housing Society Limited. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Nityanand Nagar Vibhag IV Cooperative Housin to a free account