ReraGenieLog inGet a buyer report

Home / Browse projects / MODERN ENCLAVE

Registration lapsed No litigation declared Residential / Group Housing project

MODERN ENCLAVE

By VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED

RG-MH-64596 · RERA P51900012720 · Last updated on MahaRERA portal: 4 Aug 2017

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 82 months past the filed date

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: .
Dec 2019Possession promised82 months past this date
4 of 11Construction stages donefurthest along: Stilt Floor, 95%
0Complaints at MahaRERAon this registration
Jump to the 42 documents Report an error

MODERN ENCLAVE is a Residential / Group Housing project by VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED in 400011, registered with MahaRERA as P51900012720 on 7 Sep 2017. Possession was promised by 31 Dec 2019 and is now 82 months past that date.

At a glance

Project

  • NameMODERN ENCLAVE
  • TypeResidential / Group Housing
  • Location
    • 400011
  • Pincode400011
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51900012720
  • ReraGenie IDRG-MH-64596

Builder

  • NameVIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED
  • Entity typeCompany
  • Managing DirectorSANTUSH PANDURANG MANE
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

82 months past promisethis monthRegisteredSep 2017PromisedDec 2019

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on7 Sep 2017
  • Promised completion31 Dec 2019
  • Revised completionNone
  • Buildings1 building record
  • Documents filed42 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
MODERN ENCLAVENA200000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 4 Aug 2017, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

4 of 11 construction stages are filed complete. The stage furthest along is Stilt Floor, at 95%.

MODERN ENCLAVE: 77% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor95%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises95%
Sanitary Fittings within the flats / premises50%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.20%

Progress on shared amenities16

As on 4 Aug 2017, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes85%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsYes80%
Landscaping & Tree PlantingYes100%
Street LightingYes50%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes100%
Solid Waste Management And DisposalYes95%
Water conservation /Rain water harvestingYes50%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes100%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes90%
Open ParkingNoNot applicable
LOBBIES AND CARRIDORSYes95%

Parking filed1

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots1
Closed/Covered1

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,510 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
MAHANAGAR CONSTRUCTION PVT LTDAndheriMumbai Suburban

Approvals and building plan

Permissible FSI5109.62
Proposed, not sanctioned5,110 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchAGAR BAZAR, DADAR WEST, MUMBAI 400028

Certifying professionals and partners2

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMHATRE AND ASSOCIATES
EngineerVIKAS GOKHALE ASSOCIATE CONSULTANTS
PartnerRole in project
VIGNAHARTA BUILDERS AND PROJECTS PRIVATE LIMITED-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 3 Aug 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 3 Aug 2017
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 3 Aug 2017
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed42

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Certificates of CA (Form 3)File: FORM-3 C A CARTIFICATE R.pdf4 Aug 2017
Proforma of Allotment letterFile: Draft of Agreement AGRIPADA.pdf4 Aug 2017
Layout approvalFile: Layout As Per Approval (4).pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p02.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p03.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p04.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p05.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p06.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p07.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p08.pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p09.pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (1).pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (2).pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (3).pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (4).pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (5).pdf3 Aug 2017
Building plan approvalFile: APPROVED PLAN (6).pdf3 Aug 2017
Building plan approvalFile: IOD AGRIPADA - p01.pdf3 Aug 2017
PAN CardFile: PAN CARD COMPANY.PDF3 Aug 2017
Copy of the legal title reportFile: TITLE REPORT AGREEPADA.PDF3 Aug 2017
Details of encumbrancesFile: Encumbrances.pdf3 Aug 2017
Copy of Layout Approval (in case of layout)File: Layout As Per Approval (4).pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p01.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p02.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p03.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p04.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p05.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p06.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p07.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p08.pdf3 Aug 2017
Building Plan Approval (IOD)File: IOD AGRIPADA - p09.pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (1).pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (2).pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (3).pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (4).pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (5).pdf3 Aug 2017
Building Plan Approval (IOD)File: APPROVED PLAN (6).pdf3 Aug 2017
Declaration in FORM BFile: FORM B AGREEPADA ANSARI.PDF3 Aug 2017
Declaration in FORM BFile: FORM B AFFIDAVIT0001.PDF3 Aug 2017
Declaration in FORM BFile: FORM B AFFIDAVIT.PDF3 Aug 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 - ARCHITECT CERTIFICATE.PDF3 Aug 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2 - ENGINEER CERTIFICATE R.PDF3 Aug 2017

Keep MODERN ENCLAVE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near this project

2 kmMODERN ENCLAVECompleted 9Lapsed / revoked 15Other 19Dot size: filed unitsN

Filed coordinates, straight-line distance. 43 registered projects within 2 km.

Builder: VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED

VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED has 2 registrations on MahaRERA, including VIJAYA HEIGHTS and MODERN ENCLAVE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record.

Frequently asked questions

What does it mean that MODERN ENCLAVE shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if MODERN ENCLAVE is delayed beyond 31 Dec 2019?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MODERN ENCLAVE?

The registered promoter entity is VIGHNAHATRA BUILDERS AND PROJECTS PRIVATE LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MODERN ENCLAVE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for MODERN ENCLAVE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MODERN ENCLAVE?

The professionals named in the filing: Architect: MHATRE AND ASSOCIATES; Engineer: VIKAS GOKHALE ASSOCIATE CONSULTANTS. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MODERN ENCLAVE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MODERN ENCLAVE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MODERN ENCLAVE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.