Home / Browse projects / Mumbai Suburban, Maharashtra / LINKBAY RESIDENCES PHASE II WING B

Registered Litigation declared Residential / Group Housing project

LINKBAY RESIDENCES PHASE II WING B

By Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited

RG-MH-56450 · RERA PR1181012501116 · Last updated on MahaRERA portal: 8 May 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 7 cases
  • Rs 400.00 crore secured on the land, in favour of Tata Captial Housing Finance Limited

Clear

  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • All 12 completed earlier projects delivered on promise

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Jun 2030Possession promisedno revision filed
3 of 11Construction stages donefurthest along: Slabs of Super Structure, 4%
88 of 88Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 77 documents Report an error

LINKBAY RESIDENCES PHASE II WING B is a Residential / Group Housing project by Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited in Mumbai Suburban, Maharashtra, registered with MahaRERA as PR1181012501116 on 9 Oct 2025. Possession is promised by 30 Jun 2030. 0 of the 88 units on this registration are recorded sold or booked, and 3 of 11 construction stages are filed complete.

At a glance

Project

  • NameLINKBAY RESIDENCES PHASE II WING B
  • TypeResidential / Group Housing
  • Location
    • Village Ambivali Link Road
    • Andheri (West)
    • Ambivali
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.PR1181012501116
  • ReraGenie IDRG-MH-56450

Builder

  • NamePortsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited
  • Entity typeCompany
  • CINU45201GJ2021PTC124244
  • GSTIN27AAMCP1471H1Z8
  • DirectorsJackbastian Nazareth, Prithvijeet Rajaram Chavan, Kewal Rajaram Mehta, Anil Rajaram Mattoo
  • Declared earlier projects13 →

Key dates

this monthRegisteredOct 2025PromisedJun 2030

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on9 Oct 2025
  • Promised completion30 Jun 2030
  • Revised completionNone
  • Buildings1 building record
  • Documents filed77 files

Current status

0%0 of 88 units booked
13.6%Work done, per cost certificate

Figures as on 8 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Wing BNA292388088

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 8 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

3 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 4%.

Wing B: 28% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure4%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 8 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNo0%
Water SupplyNo0%
Sewerage (Chamber, Lines, Septic Tank , STP)No0%
Storm Water DrainsNo0%
Landscaping & Tree PlantingNo0%
Street LightingNo0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNo0%
Solid Waste Management And DisposalNo0%
Water conservation /Rain water harvestingNo0%
Energy managemcntNo0%
Fire protection and fire safety requirementsNo0%
Electrical meter room, sub-station, receiving stationNo0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed170

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots170
Podiums / Upper Parking Floor87
Basement79
Stack Parking4

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area10,065 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofTata Captial Housing Finance Limited
Secured amountRs 400.00 crore
CERSAI search filedYes
Declared on4 Oct 2025
LandownerVillageDistrict
Shiv Infra Vision Private LimitedKurlaMumbai Suburban

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI105850.53
Proposed, not sanctioned11,680 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., ICICI Bank Towers, Bandra Kurla Complex, Bandra East, Mumbai.400051, Maharashtra
Estimated costRs 111.76 cr
Cost incurredRs 15.18 cr
Work done13.58%
BuildingWingEstimatedIncurred
Wing BNARs 106.17 crRs 15.18 cr
-NARs 5.59 cr-

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectCreative Consultancy
EngineerMahimtura Consultants Pvt Ltd
EngineerMahimtura Consultants Private L
EngineerMahimtura Consultants Private Limited
EngineerHillel Eliazer Divekar
EngineerGem Engserv Private Limited
Chartered AccountantB R Nagda & Co.
Chartered AccountantKshirsagar & Associates
PartnerRole in project
Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited-

Litigation declared7

CaseCourtStatus
971/2019Bombay High CourtOngoing
15429/2022Bombay High CourtOngoing
21/2024Bombay High CourtOngoing
3159/2024Bombay High CourtOngoing
7696-7697/2025Supreme Court of IndiaOngoing
8709/2025Supreme Court of IndiaOngoing
3896/2024Bombay High CourtOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportNot on the file

    A lawyer's report on who owns the land and what is registered against it.

  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 29 Sep 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 29 Sep 2025
  4. Commencement CertificateNot on the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 30 Jun 2030

Documents filed77

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1_LINKBAY PHASE II_Wing B_Dec 25.pdf8 May 2026
Withdrawal Update Form 1File: Form 1_LINKBAY PHASE II_Wing B_MAR 26.pdf8 May 2026
Withdrawal Update Form 2File: Form 2_LINKBAY PHASE II_Wing B_Dec 25.pdf8 May 2026
Withdrawal Update Form 2File: Form 2_LINKBAY PHASE II_Wing B_MAR 26.pdf8 May 2026
Withdrawal Update Form 3File: Form 3_LINKBAY PHASE II_Wing B_Dec 25.pdf8 May 2026
Withdrawal Update Form 3File: Form 3_LINKBAY PHASE II_Wing B_MAR 26.pdf8 May 2026
Declaration and undertaking (Annexure A)File: PBPL- Order 50 Declaration A.pdf30 Sep 2025
Declaration and undertaking (Annexure A)File: SIVPL_Order 50.pdf30 Sep 2025
Layout approvalFile: Amended IOA - 07052025.pdf29 Sep 2025
Building plan approvalFile: Building Plan 01.pdf29 Sep 2025
Building plan approvalFile: Building Plan 02.pdf29 Sep 2025
Building plan approvalFile: Building Plan 03.pdf29 Sep 2025
Building plan approvalFile: Building Plan 04.pdf29 Sep 2025
Building plan approvalFile: Building Plan 05.pdf29 Sep 2025
Building plan approvalFile: Building Plan 06.pdf29 Sep 2025
Building plan approvalFile: Building Plan 07.pdf29 Sep 2025
Building plan approvalFile: Building Plan 08.pdf29 Sep 2025
Building plan approvalFile: Building Plan 09.pdf29 Sep 2025
Building plan approvalFile: Building Plan 10.pdf29 Sep 2025
Building plan approvalFile: Building Plan 11.pdf29 Sep 2025
Building plan approvalFile: Building Plan 12.pdf29 Sep 2025
Building plan approvalFile: Building Plan 13.pdf29 Sep 2025
Building plan approvalFile: Building Plan 14.pdf29 Sep 2025
Building plan approvalFile: Building Plan 15.pdf29 Sep 2025
Building plan approvalFile: Building Plan 16.pdf29 Sep 2025
Building plan approvalFile: Building Plan 17.pdf29 Sep 2025
Building plan approvalFile: Building Plan 18.pdf29 Sep 2025
Building plan approvalFile: Building Plan 19.pdf29 Sep 2025
Building plan approvalFile: Building Plan 20.pdf29 Sep 2025
Building plan approvalFile: Building Plan 21.pdf29 Sep 2025
Building plan approvalFile: Building Plan 22.pdf29 Sep 2025
Building plan approvalFile: Building Plan 23.pdf29 Sep 2025
Building plan approvalFile: Building Plan 24.pdf29 Sep 2025
Building plan approvalFile: Building Plan 25.pdf29 Sep 2025
Building plan approvalFile: Building Plan 26.pdf29 Sep 2025
Building plan approvalFile: Building Plan 27.pdf29 Sep 2025
Building plan approvalFile: Building Plan 28.pdf29 Sep 2025
Building plan approvalFile: Building Plan 29.pdf29 Sep 2025
Building plan approvalFile: Building Plan 30.pdf29 Sep 2025
Building plan approvalFile: Building Plan 31.pdf29 Sep 2025
Building plan approvalFile: Building Plan 32.pdf29 Sep 2025
Building plan approvalFile: Building Plan 33.pdf29 Sep 2025
Building plan approvalFile: Building Plan 34.pdf29 Sep 2025
Building plan approvalFile: Building Plan 35.pdf29 Sep 2025
Building plan approvalFile: Building Plan 36.pdf29 Sep 2025
Building plan approvalFile: Building Plan 37.pdf29 Sep 2025
Building plan approvalFile: Building Plan 38.pdf29 Sep 2025
Building plan approvalFile: Building Plan 39.pdf29 Sep 2025
Building plan approvalFile: Building Plan 40.pdf29 Sep 2025
Building plan approvalFile: Building Plan 41.pdf29 Sep 2025
Building plan approvalFile: Building Plan 42.pdf29 Sep 2025
Building plan approvalFile: Building Plan 43.pdf29 Sep 2025
Building plan approvalFile: Building Plan 44.pdf29 Sep 2025
Building plan approvalFile: Building Plan 45.pdf29 Sep 2025
Building plan approvalFile: Building Plan 46.pdf29 Sep 2025
Building plan approvalFile: Building Plan 48.pdf29 Sep 2025
Building plan approvalFile: Building Plan 49.pdf29 Sep 2025
Building plan approvalFile: Building Plan 47.pdf29 Sep 2025
Building plan approvalFile: Building Plan 50.pdf29 Sep 2025
Building plan approvalFile: Building Plan 51.pdf29 Sep 2025
Building plan approvalFile: Building Plan 52.pdf29 Sep 2025
Building plan approvalFile: Building Plan 53.pdf29 Sep 2025
Building plan approvalFile: Building Plan 54.pdf29 Sep 2025
Building plan approvalFile: Building Plan 55.pdf29 Sep 2025
Building plan approvalFile: Building Plan 56.pdf29 Sep 2025
Building plan approvalFile: Building Plan 57.pdf29 Sep 2025
Building plan approvalFile: Building Plan 58.pdf29 Sep 2025
Building plan approvalFile: Building Plan 59.pdf29 Sep 2025
Building plan approvalFile: Building Plan 60.pdf29 Sep 2025
Building plan approvalFile: Building - Plan 61.pdf29 Sep 2025
Building plan approvalFile: Building Plan 62.pdf29 Sep 2025
Building plan approvalFile: Building Plan 63.pdf29 Sep 2025
Building plan approvalFile: Building Plan 64.pdf29 Sep 2025
Building plan approvalFile: Building Plan 65.pdf29 Sep 2025
Building plan approvalFile: Building Plan 66.pdf29 Sep 2025
Building plan approvalFile: Building Plan 67.pdf29 Sep 2025
Building plan approvalFile: Tower B Identification.pdf29 Sep 2025

Promoter's earlier projects13

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

12 delivered on promise1 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
LINKBAY RESIDENCES PHASE IP51800047539Andheri (West), Mumbai Suburban589Nov 2022OngoingOct 2028Not due yet
WESTERN HEIGHTS PHASE 2 COMMERCIAL 1ST AND 2ND FLOORP51800002219DN Nagar, Mumbai Suburban-Jul 2017CompletedJun 2019Registered original: Jun 2018Jun 2019
WESTERN HEIGHTS - PHASE 1 RESIDENTIALP51800001290DN Nagar, Mumbai Suburban-Jul 2017CompletedJun 2019Registered original: Jun 2018Dec 2018
WATERLILIY PHASE 4Shantigram Ahmedabad--CompletedJun 2018Jun 2018
Meadows D,E AND FShantigram, Ahmedabad--CompletedJun 2018Jun 2018
Meadows A,B AND CShantigram, Ahmedabad--CompletedJun 2018Jun 2018
WATERLILY PHASE 3Shantigram Ahmedabad--CompletedDec 2017Dec 2017
WATERLILY PHASE 2Shantigram Ahmedabad--CompletedDec 2017Dec 2017
Meadows J AND KShantigram Ahmedabad--CompletedDec 2017Dec 2017
Meadows G,H AND IShantigram, Ahmedabad--CompletedDec 2017Dec 2017
INSPIRE BKC PHASE 2 SIXTH AND SEVENTH FLOORP51900006101Mumbai City, Mumbai City-Aug 2017CompletedDec 2017Oct 2017
INSPIRE BKC PHASE 1 GROUND TO FOURTH FLOORP51900008813Mumbai City, Mumbai City-Aug 2017CompletedDec 2017Oct 2017
SHOPPERS PLAZAShantigram Ahmedabad--CompletedMar 2017Mar 2017

How this compares with Mumbai Suburban

0%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LINKBAY RESIDENCES PHASE II WING B on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Andheri (West)6,700+ in Mumbai Suburban

2 kmLINKBAY RESIDENCES PHASECompleted 96Lapsed / revoked 74Abeyance 1Other 138Dot size: filed unitsN

Filed coordinates, straight-line distance. 309 registered projects within 2 km.

Builder: Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited

Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited has 1 registration on MahaRERA, including LINKBAY RESIDENCES PHASE II WING B. Its filings disclose 13 earlier MahaRERA projects: declares 12 of 12 past projects completed on time. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if LINKBAY RESIDENCES PHASE II WING B is delayed beyond 30 Jun 2030?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LINKBAY RESIDENCES PHASE II WING B?

The registered promoter entity is Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited, a company as per the filing. Its CIN U45201GJ2021PTC124244 and GSTIN 27AAMCP1471H1Z8 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LINKBAY RESIDENCES PHASE II WING B?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LINKBAY RESIDENCES PHASE II WING B?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LINKBAY RESIDENCES PHASE II WING B?

The professionals named in the filing: Architect: Creative Consultancy; Engineer: Mahimtura Consultants Pvt Ltd; Engineer: Mahimtura Consultants Private L; Engineer: Mahimtura Consultants Private Limited; Engineer: Hillel Eliazer Divekar; Engineer: Gem Engserv Private Limited. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LINKBAY RESIDENCES PHASE II WING B?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LINKBAY RESIDENCES PHASE II WING B. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LINKBAY RESIDENCES PHASE II WING B to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.