Red flags

  • Litigation declared, 22 cases
  • 21 complaints at MahaRERA
  • Completion date moved by 75 months
  • 1 extension taken
  • Rs 16.00 crore secured on the land, in favour of APRN Pvt Ltd
  • The declared charge does not appear in the CERSAI report on the filing

Clear

  • Separate project account declared
  • Allotment letter follows the model form

6 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Mar 2028Possession promisedmoved 75 months from the original
62 of 308Construction stages doneacross 28 buildings; furthest along: Basement (if any), 80%
1,160 of 1,582Units unsoldnot recorded sold or booked
21Complaints at MahaRERAon this registration
Jump to the 240 documents Report an error

LIVSMART KURLA is a Others project by D. K. REALTY (INDIA) PVT. LTD. in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800000340 on 15 Jul 2017. Possession is promised by 12 Mar 2028. The completion date has moved by 75 months from the original filing. 422 of the 1,582 units on this registration are recorded sold or booked, and 62 of 308 construction stages are filed complete. 21 complaints are on record with the regulator.

At a glance

Project

  • NameLIVSMART KURLA
  • TypeOthers
  • Location
    • KIROL ROAD
    • KURLA WEST
    • Kurla
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800000340
  • ReraGenie IDRG-MH-09054

Builder

  • NameD. K. REALTY (INDIA) PVT. LTD.
  • Entity typeCompany
  • DirectorsDarshan Milind Kanayalkar, Marshal Christopher Verma

Key dates

this monthRegisteredJul 2017First promiseDec 2021Revised toMar 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on15 Jul 2017
  • Promised completion12 Mar 2028
  • Revised completionRevised to 12 Mar 2028 (originally 30 Dec 2021)
  • Buildings28 building records
  • Documents filed240 files

Current status

27%422 of 1,582 units booked
27.1%Work done, per cost certificate

Figures as on 10 Mar 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING 1NA171455055
WING 2NA171452052
WING 3NA171474074
WING 4NA171452052
WING 5NA171455055
WING 6NA171456056
WING 7NA171452052
WING 8NA171456056
WING 9NA171482082
WING 10NA171452052
WING 11NA171452052
WING 12NA171482082
WING 13NA171452052
WING 14NA171456056
WING 15NA171452052
WING 16NA171482082
WING 17NA171456056
WING 18NA171451051
WING 19NA171454054
WING 20NA171482082
WING 21NA161457259
WING 22NA171452052
WING 23NA171456056
WING 24NA171440040
WING 25NA161444246
WING 26NA161432234
WING 27NA161444145
WING 28NA161443245

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building20

As on 10 Mar 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection. The count above covers all 28 buildings; the table lists the first 20.

62 of 308 construction stages are filed complete across 28 buildings. The stage furthest along is Basement (if any), at 80%.

WING 137%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 237%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 328%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 428%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 528%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 624%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 728%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 828%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 924%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1028%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1128%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1228%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1324%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1428%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1527%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1624%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1724%
ActivityProgress
Excavation100%
Basement (if any)80%
Podiums (if any)0%
Plinth80%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1828%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks3%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 1927%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
WING 2027%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks2%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 10 Mar 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingYes0%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed757

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots757
Closed/Covered757
BuildingClosed/CoveredTotal
WING 11919
WING 22424
WING 33030
WING 42424
WING 51919
WING 62525
WING 73131
WING 82525
WING 93232
WING 103131
WING 113131
WING 123232
WING 132424
WING 141313
WING 152424
WING 163232
WING 173939
WING 181515
WING 193535
WING 204343
WING 212525
WING 223535
WING 233030
WING 242323
WING 252222
WING 262626
WING 272222
WING 282626

Land and ownership

A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area18,564 sq m
Land owned byThe promoter
Named landownersNone
Encumbrance on the landDeclared present
Charge in favour ofAPRN Pvt Ltd
Secured amountRs 16.00 crore
CERSAI search filedYes
Declared on18 Dec 2025

Approvals and building plan

Sanctioning authoritySlum Rehabilitation Authority
Permissible FSI85187.65
Proposed, not sanctioned85,188 sq m
Buildings approved28
Buildings sanctioned28

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch340, GROUND FLOOR, WARDEN HOUSE, BYCULLA EAST, MUMBAI 400008
Estimated costRs 816.47 cr
Cost incurredRs 221.67 cr
Work done27.15%
BuildingWingEstimatedIncurred
WING 3NARs 38.10 crRs 14.14 cr
WING 16NARs 35.74 crRs 7.82 cr
WING 20NARs 35.74 crRs 9.69 cr
WING 9NARs 35.73 crRs 8.16 cr
WING 12NARs 35.73 crRs 12.58 cr
WING 21NARs 31.40 crRs 6.87 cr
-NARs 29.13 crRs 4.29 cr
WING 28NARs 28.65 crRs 6.27 cr
WING 14NARs 28.33 crRs 9.97 cr
WING 17NARs 27.52 crRs 6.02 cr
WING 7NARs 27.51 crRs 9.42 cr
WING 10NARs 27.48 crRs 9.67 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectBIDCO ENGINEERING DIVISION
ArchitectAakruti Architects and Consultants
EngineerKishor Trikam Das Parmar
Chartered AccountantJ Vipul & Associates
Chartered AccountantDularesh K Jain and Associates
Chartered AccountantChoudhary Tenani and Associates
PartnerRole in project
D. K. REALTY (INDIA) PVT. LTD.-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA24122518954Dec 2021 → Mar 2028

Reason as filed by the promoterD.K. Realty (India) Private Limited (“Promoter”) declares that under a Development Agreement dated 11 December 2015, Housing Development and Infrastructure Limited (HDIL) granted the Promoter exclusive and irrevocable development rights over 85,000 sq. mtrs. of sale FSI on the property at Kurla, Mumbai, including rights to construct, develop, sell, create third-party interests, and obtain SRA lease rights. Based on this, the Promoter obtained revised approvals from the Slum Rehabilitation Authority (SRA) through an Intimation of Approval dated 1 January 2016 for development of a residential-cu

Litigation declared22

CaseCourtStatus
IA No. 5281 of 2025 in CP (IB) No.1170/MB-IV/2021/2025NCLTOngoing
Company Appeal (AT) (Ins.) No. 406 of 2025/2025NCLATOngoing
IA No. 3255 of 2025/2025National Company Law TribunalOngoing
IA No. 3321/ 2025 and IA No. 3322/ 2025/2025National Company Law TribunalOngoing
IA No. 3320 of 2025/2025National Company Law TribunalOngoing
IA No. 3323 of 2025/2025National Company Law TribunalOngoing
IA No. 3349 of 2025/2025National Company Law TribunalOngoing
IA No. 3348 of 2025/2025National Company Law TribunalOngoing
IA No. 3374 of 2025 and IA No. 3398 of 2025/2025National Company Law TribunalOngoing
IA No. 3447 of 2025/2025National Company Law TribunalOngoing
IA No. 3444 of 2025/2025National Company Law TribunalOngoing
IA No. 3446 of 2025/2025National Company Law TribunalOngoing
IA No. 3397 of 2025/2025National Company Law TribunalOngoing
IA No. 3376 of 2025/2025National Company Law TribunalOngoing
IA No. 3377 of 2025/2025National Company Law TribunalOngoing
IA No. 3396 of 2025/2025National Company Law TribunalOngoing
IA No. 5061 of 2025/2025National Company Law TribunalOngoing
IA No. 2707 of 2025/2025National Company Law TribunalOngoing
IA No. 4537 of 2025/2025National Company Law TribunalOngoing
IA No. 4536 of 2025/2025National Company Law TribunalOngoing
IA No. 3978 of 2025/2025National Company Law TribunalOngoing
IA-5916 of 2024 /2024National Company Law TribunalOngoing

Complaints filed with MahaRERA21

Case no.ComplainantRespondentFiled
CC006000000057845Janhavi BhattD K Realty India Pvt Ltd28/01/2019
CC006000000181992Mahendra Kumar ShahD. K. Reality (India) Pvt. Ltd.07/01/2020
CC006000000197382MR. UTTAM SINGHD, K, RELATY (INIDA) PRIVATE LIMITED23/06/2021
CC006000000198249Mohammed Muqeem AnsariD. K.Realty pvt Ltd18/11/2021
CC006000000196366BRG Brothers LLPD. K.Realty (India) Pvt. Ltd.17/03/2021
CC006000000196845Rahul PatilD. K. Realty (India) Pvt. Ltd.27/04/2021
CC006000000210455Shashi Kant BahlDK Realty India Private Limited21/03/2022
CC006000000292382KAUSAR MOSSANIDK REALTY INDIA PVT LTD18/08/2022
CC006000000292612PRAKASH DATTARAM MISALD. K. Realty (India) Pvt. Ltd.11/10/2022
CC006000000344163PRASHANT RAJENDRA KAMBLED.K. REALTY (INDIA) PVT LTD01/02/2023
CC006000000374787Sunil Kumar MehtaD. K. Realty (India) Pvt. Ltd.16/03/2023
CC006000000374795Anjana MehtaD. K. Realty (India) Pvt. Ltd.16/03/2023
CC006000000374798Ayush MehtaD. K. Realty (India) Pvt. Ltd.16/03/2023
CC006000000374872Ayush MehtaD. K. Realty (India) Pvt Ltd28/03/2023
CC006000000374873Ayush MehtaD. K. Realty (India) Pvt. Ltd.28/03/2023
CC006000000374803Kshitij MehtaD. K. Realty (India) Pvt Ltd16/03/2023
CC006000000374807SunilKumar Mehta HUFD. K. Realty (India) Pvt Ltd16/03/2023
CC006000000375319Pradeep Vishnu TendolkarD K Realty (India) Private Limited18/04/2023
CC006000000396725Mr Iqbal Ahmed And Mrs Anjali AhmedD K Realty (India) Pvt. Ltd.18/07/2023
CC006000000429576ANKIT SINGHDK REALTY INDIA PVT LTD09/03/2024
CC12501756Wilson DsaD. K. REALTY (INDIA) PVT. LTD.28/05/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 4 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 16 Jan 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 16 Jan 2026
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 15 May 2019Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 12 Mar 2028

Documents filed240

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 240 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1 - 1-1-2026.pdf10 Mar 2026
Withdrawal Update Form 1File: Form 1 - 1-1-2026.pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2- 1-1-2026.pdf10 Mar 2026
Withdrawal Update Form 2File: Form 2- 1-1-2026.pdf10 Mar 2026
Withdrawal Update Form 3File: Form 3_Rera_Signed_Dec25.pdf10 Mar 2026
Withdrawal Update Form 3File: Form 3_Rera_Signed_Dec25.pdf10 Mar 2026
Layout approvalFile: Layout Plan Highlighted Bldg 2.pdf16 Jan 2026
Building plan approvalFile: Typical floor plan with highlighted wings.pdf16 Jan 2026
Withdrawal Update Form 1File: Form 1 Annexure 01-07-2025.pdf16 Jan 2026
Withdrawal Update Form 1File: Form 1 Annexure A 01-10-2025.pdf16 Jan 2026
Withdrawal Update Form 1File: Form 1 Annexure A 01-10-2025.pdf16 Jan 2026
Withdrawal Update Form 2File: Form 2 Annexure B 01-07-2025.pdf16 Jan 2026
Withdrawal Update Form 2File: Form 2 Annexure B_01-10-2025.pdf16 Jan 2026
Withdrawal Update Form 2File: Form 2 Annexure B_01-10-2025.pdf16 Jan 2026
Withdrawal Update Form 3File: CA Certificate Form 3.pdf16 Jan 2026
Withdrawal Update Form 3File: CA Certificate Form 3.pdf16 Jan 2026
Withdrawal Update Form 3File: CA Certificate Form 3.pdf16 Jan 2026
Form 2A (FY 2024-2025)File: Form 2A.pdf16 Jan 2026
Form 1File: Form 1.pdf13 Jan 2026
Form 2File: Form 2.pdf13 Jan 2026
Form 3File: CA Certificate Form 3.pdf13 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf13 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf13 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026
Form 3File: CA Certificate Form 3.pdf10 Jan 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold and Unsold Inventory.pdf10 Jan 2026
Self-declaration of Quarterly ProgressFile: Declaration.pdf10 Jan 2026
Form 1File: Form 1.pdf10 Jan 2026
Form 2File: Form 2.pdf10 Jan 2026

How this compares with Mumbai Suburban

27%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 75 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LIVSMART KURLA on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near KURLA WEST6,700+ in Mumbai Suburban

2 kmLIVSMART KURLACompleted 128Lapsed / revoked 104Other 145Dot size: filed unitsN

Filed coordinates, straight-line distance. 377 registered projects within 2 km.

Builder: D. K. REALTY (INDIA) PVT. LTD.

D. K. REALTY (INDIA) PVT. LTD. has 1 registration on MahaRERA, including LIVSMART KURLA. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if LIVSMART KURLA is delayed beyond 12 Mar 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LIVSMART KURLA?

The registered promoter entity is D. K. REALTY (INDIA) PVT. LTD., a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LIVSMART KURLA?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against LIVSMART KURLA?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for LIVSMART KURLA?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LIVSMART KURLA?

The professionals named in the filing: Architect: BIDCO ENGINEERING DIVISION; Architect: Aakruti Architects and Consultants; Engineer: Kishor Trikam Das Parmar; Chartered Accountant: J Vipul & Associates; Chartered Accountant: Dularesh K Jain and Associates; Chartered Accountant: Choudhary Tenani and Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LIVSMART KURLA?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LIVSMART KURLA. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LIVSMART KURLA to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.