Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited: RERA track record

CIN U45201GJ2021PTC124244 · GSTIN 27AAMCP1471H1Z8 · Company · attribution by exact filing name, entity resolution in progress

Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited has 1 registration on MahaRERA, including LINKBAY RESIDENCES PHASE II WING B. Its filings disclose 13 earlier MahaRERA projects: declares 12 of 12 past projects completed on time. Litigation is declared on 1 of its registrations.

1RERA registrations
13Past projects disclosed
on timeMedian delivery slip
1Registrations with litigation
Follow this developer. An email when Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited registers a new project on MahaRERA, and when the filings of their existing projects change: new sales, moved possession dates, extensions, complaints. Runs 12 months, no auto-renew. Follow · Rs 999 / 12 months

Projects by this developer

Showing the one project.

Largest first, by the unit count in the filing.

ProjectLocationUnitsBookedRegisteredStatus
LINKBAY RESIDENCES PHASE II WING BPR1181012501116Andheri (West), Mumbai Suburban, 400053880%9 Oct 2025Registered

What this promoter declares as its own experience

Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited declares experience on 13 earlier projects. 5 of them carry a registration number we could match on MahaRERA, and all of them are registered under a different promoter name.

5 of these declarations can be compared with the dates those projects' own registrations hold. On 2, the date given as the original completion date is the REVISED deadline that project carries after an extension rather than its original one. That changes the arithmetic on 2 of the 4 completions recorded here as on time: measured against the original deadline the register itself holds, those were finished after it.

Declared projectRegistered toStatus
INSPIRE BKC PHASE 1 GROUND TO FOURTH FLOORADANI DEVELOPERS PRIVATE LIMITEDCompleted
INSPIRE BKC PHASE 2 SIXTH AND SEVENTH FLOORADANI DEVELOPERS PRIVATE LIMITEDCompleted
WESTERN HEIGHTS - PHASE 1 RESIDENTIALADANI ESTATES PRIVATE LIMITEDCompleted
WESTERN HEIGHTS PHASE 2 COMMERCIAL 1ST AND 2ND FLOORADANI ESTATES PRIVATE LIMITEDCompleted
LINKBAY RESIDENCES PHASE IPORTSMOUTH BUILDCON PRIVATE LIMITEDRegistered

From the promoter experience table each promoter files with MahaRERA, matched to the register by registration number. A declaration naming another promoter's project is a claim of involvement, and involvement takes several shapes: a parent and its project company, one firm re-registering under a second name, or a joint venture between two separate developers. We publish the claim as filed and do not treat it as proof that the entities are one builder.

Past projects, as disclosed in RERA filings

ProjectPromised completionActual completionDelivery
SHOPPERS PLAZA
31 Mar 201731 Mar 2017On time
INSPIRE BKC PHASE 1 GROUND TO FOURTH FLOOR
P51900008813
31 Dec 201716 Oct 2017On time
INSPIRE BKC PHASE 2 SIXTH AND SEVENTH FLOOR
P51900006101
31 Dec 201716 Oct 2017On time
Meadows G,H AND I
31 Dec 201731 Dec 2017On time
Meadows J AND K
31 Dec 201731 Dec 2017On time
WATERLILY PHASE 2
31 Dec 201731 Dec 2017On time
WATERLILY PHASE 3
31 Dec 201731 Dec 2017On time
Meadows A,B AND C
30 Jun 201830 Jun 2018On time
Meadows D,E AND F
30 Jun 201830 Jun 2018On time
WATERLILIY PHASE 4
30 Jun 201830 Jun 2018On time
WESTERN HEIGHTS - PHASE 1 RESIDENTIAL
P51800001290
30 Jun 201915 Dec 2018On time
WESTERN HEIGHTS PHASE 2 COMMERCIAL 1ST AND 2ND FLOOR
P51800002219
30 Jun 201930 Jun 2019On time

Frequently asked questions

How do I verify Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited as a legal entity before signing?

Your agreement for sale must name the exact entity registered for the project, not a group brand. Cross-check its CIN U45201GJ2021PTC124244 and GSTIN 27AAMCP1471H1Z8 on the MCA and GST portals before signing anything. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.

How should I use this delivery record when booking with Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited?

Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.

Does the declared litigation make Portsmouth Buildcon Private Limited and Shiv Infra Vision Private Limited unsafe to buy from?

Not by itself. Litigation on a registration ranges from a boundary dispute to an allottee case about delay; what matters is the case type, which court or forum, and whether it touches the land title of the project you are buying. The case list is in each project's filed documents. Treat litigation as a question to resolve in writing before booking, not as a verdict either way.

Spotted a project attributed to the wrong developer, or something else wrong on this page? Projects are grouped by the promoter name as filed, so a firm that registers under two spellings can split across two pages. Tell us and we will check it against the filings.

Report an errorShare feedback

Data from official MahaRERA filings. How we handle corrections is on the about page.