Red flags

  • 24 complaints at MahaRERA
  • Completion date moved by 60 months
  • 1 extension taken
  • Rs 50.00 crore secured on the land, in favour of MOONGIPA REALTY PRIVATE LIMITED

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2028Possession promisedmoved 60 months from the original
64 of 99Construction stages doneacross 9 buildings; furthest along: Installation of Lifts, 95%
524 of 1,148Units unsoldnot recorded sold or booked
24Complaints at MahaRERAon this registration
Jump to the 154 documents Report an error

MOONGIPA ARCADE is a Others project by MOONGIPA REALTY PRIVATE LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800007285 on 17 Aug 2017. Possession is promised by 31 Dec 2028. The completion date has moved by 60 months from the original filing. 624 of the 1,148 units on this registration are recorded sold or booked, and 64 of 99 construction stages are filed complete. 24 complaints are on record with the regulator.

At a glance

Project

  • NameMOONGIPA ARCADE
  • TypeOthers
  • Location
    • MUMBAI
    • Andheri
    • Mumbai Suburban
    • 400053
  • Pincode400053
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800007285
  • ReraGenie IDRG-MH-76661

Builder

  • NameMOONGIPA REALTY PRIVATE LIMITED
  • Entity typeCompany
  • GSTIN27AAICA9030H1ZO
  • DirectorsRAJESH BASUDEO AGARWAL, SANJAY BASUDEO AGARWAL
  • Other registrations1 more →
  • No longer live1 lapsed, de-registered or revoked

Key dates

this monthRegisteredAug 2017First promiseDec 2023Revised toDec 2028

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on17 Aug 2017
  • Promised completion31 Dec 2028
  • Revised completionRevised to 31 Dec 2028 (originally 30 Dec 2023)
  • Buildings9 building records
  • Documents filed154 files

Current status

54%624 of 1,148 units booked

Figures as on 20 May 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
ANA161440040
BNA161440133173
CNA161440040
DNA161440124164
ENA161440040
FNA161440146186
G1 AND G2NA171648115163
I 1 AND I 2NA181648113161
HNA171419162181

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building9

As on 20 May 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

64 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Installation of Lifts, at 95%.

A100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
B100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
C100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
D100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
E100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
F100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
G1 AND G20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
I 1 AND I 20%
ActivityProgress
Excavation0%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor0%
Slabs of Super Structure0%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H53%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor90%
Slabs of Super Structure90%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 20 May 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes70%
Storm Water DrainsYes100%
Landscaping & Tree PlantingYes70%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes70%
Solid Waste Management And DisposalYes70%
Water conservation /Rain water harvestingYes70%
Energy managemcntYes70%
Fire protection and fire safety requirementsYes70%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes80%
Open ParkingNoNot applicable

Land and ownership1

MahaRERA does not publish landowner contact details. A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.

Land area10,278 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared present
Charge in favour ofMOONGIPA REALTY PRIVATE LIMITED
Secured amountRs 50.00 crore
CERSAI search filedYes
Declared on27 May 2026
LandownerVillageDistrict
D. N. NAGAR SHREE ASHTAVINAYAK C.H.S.L.AndheriMumbai Suburban

Approvals and building plan

Sanctioning authorityMUNICIPAL CORPORATION OF GREATER MUMBAI
Permissible FSI39994.53
Proposed, not sanctioned24,379 sq m
Buildings approved9
Buildings sanctioned9

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branch1 May Fair Bldg, shop Number 9 and 10, near Sablaise Church Ceaser Road, Amboli, Andheri West, Mumba

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectELLORA PROJECT CONSULTANTS
EngineerSIHAVAT PROJECT CONSULTANTS
Chartered AccountantPMO AND CO
PartnerRole in project
MOONGIPA REALTY PRIVATE LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800017690Dec 2023 → Dec 2028

Reason as filed by the promoterWe are applying for an extension in this project due to lack of difficulties faced during Covid 19, lack of funds, we have got the consent from allottees as per the MahaRERA rules and regulation u/s 7(3) which is more than 51%. Hence we request you to grant us the extension till 31/12/2028.

Complaints filed with MahaRERA24

Case no.ComplainantRespondentFiled
CC006000000181957Shekhar R PrasadMoongippa Realty Pvt Ltd24/12/2019
CC006000000012248Anita Jairaj MirchandaniMOONGIPA REALTY PVT. LTD16/12/2017
CC006000000044420MSS SECURITIES PVT. LTD.MOONGIPA REALITY PRIVATE LIMITED05/05/2018
CC006000000044128Shekhar R.PrasadMoongippa Realty Private Limited16/04/2018
CC006000000079293Fionna DesouzaMoongipa Realty Pvt. Ltd.14/05/2019
CC006000000171864Poonam DesaiMoongipa Realty Private Ltd14/12/2019
CC006000000196984Poonam DesaiMoongipa Realty Private Limited12/05/2021
CC006000000193882YOGESH HARISH BULCHANDANIMOONGIPA REALTY PVT LTD01/09/2020
CC006000000193892YOGESH HARISH BULCHANDANIMOONGIPA REALTY PVT LTD03/09/2020
CC006000000194115Ramjyawan SinghMoongipa Realty Private Limited12/12/2020
CC006000000439627vijay choksiMSS Securities Limited12/03/2024
CC006000000197224Hemant GoyalMoongipa Realty Private Limited16/06/2021
CC006000000197693Mrs. Roopal ChitnisMoongipa Realty Private Limited11/08/2021
CC006000000198045Mahendra TannaAxayraj Buildwell Pvt Ltd30/08/2021
CC006000000198046Mahendra TannaAxayraj Buildwell Pvt Ltd30/08/2021
CC006000000198049Mahendra TannaAxayraj Buildwell Pvt Ltd30/08/2021
CC006000000196806Shazim MachiwalaMoongipa Arcade23/04/2021
CC006000000196870SONIA ADITYAMOONGIPA REALTY PRIVATE LIMITED05/05/2021
CC006000000196878Farhat Jahan M.A.KhopekarMOONGIPA REALTY PRIVATE LIMITED13/05/2021
CC006000000196892Jaya Pratap AdityaMOONGIPA REALTY PRIVATE LIMITED05/05/2021
CC006000000196916BARUN BINOY CHAKRAVARTYMOONIPA11/05/2021
CC006000000272091Mr Darryl NunesMoongipa Realty Pvt Ltd26/07/2022
CC006000000408239Soraiya Vahid KhanMoongipa Realty Private Limited25/11/2023
CC12501893Saira Abdul TurneyMOONGIPA REALTY PRIVATE LIMITED10/06/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 30 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 26 Mar 2025
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 26 Mar 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 Jul 2017Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2028

Documents filed154

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 154 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Form 1File: Form 1 Architect Cartificate compressed.pdf20 May 2026
Form 2File: Form -2 March 2026.pdf20 May 2026
Form 3File: Signed Form 3.pdf20 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory 31 03 2026.pdf20 May 2026
Form 1File: Form-1-Architect Cartificate_compressed.pdf19 May 2026
Form 2File: FORM-2 JUN-25.pdf19 May 2026
Form 3File: Form 3.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of SoldUnsold Inventory30 06 2025.pdf19 May 2026
Form 1File: Form-1-Architect Cartificate_compressed.pdf19 May 2026
Form 2File: FORM-2 SEP-25.pdf19 May 2026
Form 3File: Form 3 Signed.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-Unsold Inventory 30 09 2025.pdf19 May 2026
Form 1File: Form 1 Architect Cartificate compressed.pdf19 May 2026
Form 2File: FORM 2 DEC 25.pdf19 May 2026
Form 3File: Signed Form 3.pdf19 May 2026
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold Unsold Inventory 31 12 2025.pdf19 May 2026
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf30 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 COMP.pdf30 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 comp.pdf30 Apr 2025
Certificates of CA (Form 3)File: Signed Form 3.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf30 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf30 Apr 2025
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Form 5.pdf30 Apr 2025
Layout approvalFile: Plan wise Approval.pdf26 Mar 2025
Building plan approvalFile: Part OC.pdf26 Mar 2025
Building plan approvalFile: Plan wise Approval.pdf26 Mar 2025
Copy of Layout Approval (in case of layout)File: Plan wise Approval.pdf26 Mar 2025
Building Plan Approval (IOD)File: Part OC.pdf26 Mar 2025
Building Plan Approval (IOD)File: Plan wise Approval.pdf26 Mar 2025
OtherFile: OC Letter.pdf26 Mar 2025
OtherFile: Part OC.pdf26 Mar 2025
Disclosure for secured/unsecured finance availed for the projectFile: Disclosure for Secured Finance.pdf3 Mar 2025
Declaration in FORM BFile: RERA Form B.pdf28 Feb 2025
Certificates of CA (Form 3)File: Signed Form 3.pdf7 Jan 2025
Certificates of CA (Form 3)File: Comp.pdf7 Jan 2025
Certificates of CA (Form 3)File: Compr.pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3.pdf7 Jan 2025
Certificates of CA (Form 3)File: Signed Form 3.pdf7 Jan 2025
Certificates of CA (Form 3)File: Form 3 Signing.pdf7 Jan 2025
Disclosure of sold/ booked inventoryFile: Disc of Inventory.pdf16 Oct 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: FORM 2 A.pdf12 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5.pdf12 Oct 2023
Declaration in FORM BFile: Form B.pdf5 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Final form 1.pdf28 Sep 2023
Certificates of CA (Form 3)File: Form 3.pdf26 Sep 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1.pdf15 Sep 2023
Certificates of CA (Form 3)File: Signed Form 3.pdf15 Sep 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Form 5 FY 18 19 Moongipa Arcade.pdf19 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: Form 5 FY 19 20 Moongipa Arcade.pdf19 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 FY 20 21 Moongipa Arcade.pdf19 Apr 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form 5 FY 21 22 Moongipa Arcade.pdf19 Apr 2023
Disclosure of sold/ booked inventoryFile: Disclosure of Sold and Unsold.pdf13 Apr 2023
Declaration about Commencement CertificateFile: 2 Declaration of CC.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A as on March 20.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A as on March 21.pdf27 Mar 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A as on March 22.pdf27 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 3 Declaration of Interest_Rajesh Agarwal.pdf27 Mar 2023
Disclosure of Interest in Other Real Estate OrganizationsFile: 4 Declaration of Interest_Sanjay Agarwal.pdf27 Mar 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 1 Declaration of Bank Account.pdf27 Mar 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf28 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf28 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Architect Certificate.pdf28 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf1 Feb 2023
Certificates of CA (Form 3)File: Form 3.pdf15 Oct 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf6 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf6 Jul 2022
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2.pdf6 Jul 2022
Certificates of CA (Form 3)File: Form 3.pdf27 Jun 2022
OtherFile: Consent for Change in Plan.pdf3 Mar 2022
Certificates of CA (Form 3)File: Form 3.pdf24 Feb 2022
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Form 1 Architect.pdf20 Dec 2021
Certificates of CA (Form 3)File: Form 3.pdf20 Dec 2021
Certificates of CA (Form 3)File: Form 3.pdf25 Sep 2021
Certificates of CA (Form 3)File: Form 3.pdf20 Aug 2021
Status of Formation of Legal Entity (Society/Co Op etc.)File: Ashtvinayak CHS - Society Registration Certificate.pdf21 Jul 2021

How this compares with Mumbai Suburban

54%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 60 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep MOONGIPA ARCADE on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near MUMBAI6,700+ in Mumbai Suburban

2 kmMOONGIPA ARCADECompleted 107Lapsed / revoked 71Other 133Dot size: filed unitsN

Filed coordinates, straight-line distance. 311 registered projects within 2 km.

Builder: MOONGIPA REALTY PRIVATE LIMITED

MOONGIPA REALTY PRIVATE LIMITED has 2 registrations on MahaRERA, including MOONGIPA LANDMARK and MOONGIPA ARCADE. Its filings disclose no earlier MahaRERA projects. Litigation is declared on 1 of its registrations. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if MOONGIPA ARCADE is delayed beyond 31 Dec 2028?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of MOONGIPA ARCADE?

The registered promoter entity is MOONGIPA REALTY PRIVATE LIMITED, a company as per the filing. Its GSTIN 27AAICA9030H1ZO can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in MOONGIPA ARCADE?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against MOONGIPA ARCADE?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for MOONGIPA ARCADE?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at MOONGIPA ARCADE?

The professionals named in the filing: Architect: ELLORA PROJECT CONSULTANTS; Engineer: SIHAVAT PROJECT CONSULTANTS; Chartered Accountant: PMO AND CO. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in MOONGIPA ARCADE?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About MOONGIPA ARCADE. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save MOONGIPA ARCADE to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.