ReraGenieLog inGet a buyer report

Home / Browse projects / Nagpur, Maharashtra / LHS

Completed No litigation declared Commercial project

LHS

By GOLDBRICKS INFRASTRUCTURE PVT LTD

RG-MH-59218 · RERA P50500025598 · Last updated on MahaRERA portal: 13 Nov 2024

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • Separate project account declared
  • Allotment letter follows the model form
  • Recorded completed on MahaRERA

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 5 other registrations and every project registered within 2 km.

See what the report covers Free either way: or have every new Nagpur registration emailed to you, free during the pilot beta.
Jun 2023Possession promisedregistration recorded completed
8 of 11Construction stages donefurthest along: Basement (if any), 0%
0Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

LHS is a Commercial project by GOLDBRICKS INFRASTRUCTURE PVT LTD in Nagpur, Maharashtra, registered with MahaRERA as P50500025598 on 1 Jul 2020. The registration is recorded completed; possession was promised by 30 Jun 2023.

At a glance

Project

  • NameLHS
  • TypeCommercial
  • Location
    • MODEL MILL COMPOUND
    • UMRER ROAD
    • GANESHPETH
    • Nagpur (M Corp.)
    • Nagpur (Urban)
    • Nagpur
    • 440018
  • Pincode440018
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P50500025598
  • ReraGenie IDRG-MH-59218

Builder

  • NameGOLDBRICKS INFRASTRUCTURE PVT LTD
  • Entity typeCompany
  • DirectorsPratik Saraogi, Pratik Saraogi
  • Other registrations5 more →
  • Completed2 of 6
  • Declared earlier projects6 →

Key dates

this monthRegisteredJul 2020PromisedJun 2023Recorded completed

Key facts

Registration and timeline

  • StatusCompleted
  • Registered on1 Jul 2020
  • Promised completion30 Jun 2023
  • Revised completionNone
  • Buildings1 building record
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
LHS BUILDINGNA20000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 13 Nov 2024, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

8 of 11 construction stages are filed complete. The stage furthest along is Basement (if any), at 0%.

LHS BUILDING: 73% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth0%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 13 Nov 2024, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)NoNot applicable
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingNoNot applicable
Street LightingYes0%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalNoNot applicable
Water conservation /Rain water harvestingNoNot applicable
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsNoNot applicable
Electrical meter room, sub-station, receiving stationNoNot applicable
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingYes0%

Parking filed14

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots14
Open Space14

Land and ownership

MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area575 sq m
Land owned byThe promoter
Named landownersNone

Approvals and building plan

Permissible FSI1106.73
Proposed, not sanctioned1,107 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchNAGPUR

Certifying professionals and partners3

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectSANKALP CREATIONS
EngineerARUN UTTARWAR & ASSOCIATES
Chartered AccountantPIYUSH RATHI & ASSOCIATES
PartnerRole in project
GOLDBRICKS INFRASTRUCTURE PVT LTD-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 23 May 2020
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 23 May 2020
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 1 Aug 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 1 Aug 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 18 Feb 2023

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Architech certificate.PDF13 Nov 2024
Disclosure of sold/ booked inventoryFile: LHS Sold Unsold 31-03-2023.PDF22 Jul 2023
Disclosure of sold/ booked inventoryFile: LHS Sold Unsold 30-06-2023.PDF22 Jul 2023
CERSAI detailsFile: CERSAI_Search_Report_200263377430_For_Asset_Based_Search_17_03_2023_22_21_04_908.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_SEPT-20.pdf17 Mar 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_DEC-20.pdf17 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_June-21--1.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_Sept-21--2.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_Dec-21--3.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_Mar-22--4.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_June-22--5.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_Sept-22--6.PDF15 Mar 2023
Disclosure of sold/ booked inventoryFile: LHS_Dec-22--7.PDF15 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_SEPT-20 - 1.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_DEC-20- 2.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_MAR-21- 3.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_JUNE-21- 4.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_SEPT-21- 5.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_DEC-21- 6.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_MAR-22- 7.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_SEPT-22- 9.pdf3 Mar 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: LHS_FORM-1_DEC-22- 10.pdf3 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June-22.pdf1 Mar 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep-20.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec-20.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March-21.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 June-21.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep-21.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec-21.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 March-22.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Sep-22.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Form 2 Dec-2022.pdf24 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A March-21.pdf24 Feb 2023
Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A March-22.pdf24 Feb 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: FORM-2_LHS.pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form-3_LHS_MAR-21_.pdf18 Feb 2023
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Occupancy Certificate (1).pdf18 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_JUNE-21.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_SEP-21.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_DEC-21.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_MAR-22.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_JUNE-22.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_SEP-22.pdf17 Feb 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM-3_LHS_DEC-22.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form-5_LHS_20-21.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Form-5_LHS_21-22.pdf17 Feb 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architech Certificate of LHS.PDF10 Aug 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Engineer Certificate of LHS.PDF10 Aug 2022
CERSAI detailsFile: CERSAI_Search_Report_200244064740_For_Asset_Based_Search_05_08_2022_15_03_54_361.pdf5 Aug 2022
Building plan approvalFile: 1st and 2nd floor.pdf1 Aug 2022
Building plan approvalFile: 3rd floor and Elevation.pdf1 Aug 2022
Building plan approvalFile: Ground floor.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 1st and 2nd floor.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: 3rd floor and Elevation.pdf1 Aug 2022
Building Plan Approval / NA Order for plotted developmentFile: Ground floor.pdf1 Aug 2022
Commencement Certificates / NA Order for plotted developmentFile: 1st and 2nd floor.pdf1 Aug 2022
PAN CardFile: Pan Card - GIPL.pdf19 Jun 2020
Declaration in FORM BFile: Form B- Notarised.PDF19 Jun 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: CA Certificate - Digitally Signed.pdf19 Jun 2020
OtherFile: Credai Certificate.PDF19 Jun 2020
Layout approvalFile: Final Layout Approval.PDF23 May 2020
Building plan approvalFile: BP Commencement Certificate.pdf23 May 2020
Copy of the legal title reportFile: Title Search Report_compressed.pdf23 May 2020
Details of encumbrancesFile: Non Encumbrance Certificate.pdf23 May 2020
Copy of Layout Approval (in case of layout)File: Final Layout Approval.PDF23 May 2020
Building Plan Approval / NA Order for plotted developmentFile: BP Commencement Certificate.pdf23 May 2020
Commencement Certificates / NA Order for plotted developmentFile: BP Commencement Certificate.pdf23 May 2020
Declaration in FORM BFile: Signed Form B.PDF23 May 2020
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Signed Engg Certificate.PDF23 May 2020
Proforma of Allotment letterFile: Allotment Letter- LHS RERA.pdf23 May 2020

Promoter's earlier projects5

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

1 delivered on promise1 not delivered by the promised date3 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
ANANDAM WORLD CITY-TOWER G AND NP50500045835GANESHPETH, Nagpur-Jun 2022OngoingMar 2030Not due yet
ANANDAM WORLD CENTREP50500033711GANESHPETH, Nagpur397Mar 2022OngoingJun 2027Not due yet
ANANDAM WORLD CITY VILLAP50500009151GANESHPETH, Nagpur-Aug 2017OngoingDec 2026Not due yet
RHSP50500047576GANESHPETH, Nagpur44Nov 2022OngoingMar 2026Registered original: Mar 2025Not delivered
ANANDAM WORLD CITY PART OF TOWER A B AND DP50500004568Nagpur (M Corp.), Nagpur-Aug 2017CompletedAug 2024Dec 2019

How this compares with Nagpur

13%of Nagpur projects moved their completion datethis one has not
22%of Nagpur registrations have lapsed or been cancelledthis one is completed

Computed across the 2,800+ Nagpur projects on ReraGenie, from their own filings.

Free monthly report: Nagpur on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep LHS on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near GANESHPETH2,800+ in Nagpur

2 kmLHSCompleted 38Lapsed / revoked 18Other 42Dot size: filed unitsN

Filed coordinates, straight-line distance. 98 registered projects within 2 km.

Builder: GOLDBRICKS INFRASTRUCTURE PVT LTD

GOLDBRICKS INFRASTRUCTURE PVT LTD has 6 registrations on MahaRERA, including ANANDAM WORLD CITY PART OF TOWER A B AND D and ANANDAM WORLD CITY VILLA. Its filings disclose 6 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Nagpur district page.

Frequently asked questions

What are my rights if LHS is delayed beyond 30 Jun 2023?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of LHS?

The registered promoter entity is GOLDBRICKS INFRASTRUCTURE PVT LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in LHS?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for LHS?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at LHS?

The professionals named in the filing: Architect: SANKALP CREATIONS; Engineer: ARUN UTTARWAR & ASSOCIATES; Chartered Accountant: PIYUSH RATHI & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in LHS?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About LHS. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save LHS to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.