Home / Browse projects / Mumbai Suburban, Maharashtra / KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd
KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd
RG-MH-05316 · RERA P51800051344 · Last updated on MahaRERA portal: 1 Apr 2026
Source: official MahaRERA filing
Red flags
- No red flags in this filing
Clear
- No litigation declared
- No complaints on record
- Completion date never moved
- Separate project account declared
- Allotment letter follows the model form
- Recorded completed on MahaRERA
Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against the promoter's 7 other registrations and every project registered within 2 km.
See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd is a Residential / Group Housing project by KABRA AND ASSOCIATES in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800051344 on 8 Jun 2023. The registration is recorded completed; possession was promised by 31 Dec 2026. 71 of the 118 units on this registration are recorded sold or booked, and 0 of 11 construction stages are filed complete.
At a glance
Project
- NameKABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd
- TypeResidential / Group Housing
- Location
- Ramchandra Lane
- Off S V Road
- Malad West
- Malad
- Borivali
- Mumbai Suburban
- 400064
- Pincode400064
- MapView location on Google Maps (as filed on RERA)
- RERA no.P51800051344
- ReraGenie IDRG-MH-05316
Builder
- NameKABRA AND ASSOCIATES
- Entity typePartnership
- GSTIN27AAFFK2000F1ZZ
- PartnersSHYAMSUNDER ASHARAM KABRA, RAJESH ASHARAM KABRA, GAUTAM JAIGOPAL KABRA, MANISH KAMALKISHORE KABRA, ABHISHEK KAMALKISHORE KABRA, GOURAV JAIGOPAL KABRA, VINIL SHYAMSUNDER KABRA
- Other registrations7 more →
- Completed7 of 8
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusCompleted
- Registered on8 Jun 2023
- Promised completion31 Dec 2026
- Revised completionNone
- Buildings1 building record
- Documents filed141 files
Current status
Figures as on 1 Apr 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd | NA | 24 | 22 | 118 | 0 | 118 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 1 Apr 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
0 of 11 construction stages are filed complete. The stage furthest along is Excavation, at 95%.
KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd: 58% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 95% |
| Basement (if any) | 90% |
| Podiums (if any) | 90% |
| Plinth | 90% |
| Stilt Floor | 80% |
| Slabs of Super Structure | 85% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 50% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 40% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 15% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 1 Apr 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | No | Not applicable |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | No | Not applicable |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | No | Not applicable |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | No | Not applicable |
| Solid Waste Management And Disposal | No | Not applicable |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | No | Not applicable |
| Fire protection and fire safety requirements | Yes | 10% |
| Electrical meter room, sub-station, receiving station | Yes | 20% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | No | Not applicable |
Parking filed127
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.
| Landowner | Village | District |
|---|---|---|
| JAYVIKAS COOPERATIVE HOUSING SOCIETY LTD. | Malad | Mumbai Suburban |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners5
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | HEMANT TALATY |
| Architect | Arch Rushikesh H. |
| Engineer | Nilesh Paste |
| Chartered Accountant | MEHUL DHRUV |
| Chartered Accountant | NARENDRA CHITLANGIA |
| Partner | Role in project |
|---|---|
| KABRA AND ASSOCIATES | - |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 19 May 2023 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 3 Aug 2023 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 3 Aug 2023 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 29 Mar 2023Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot on the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
Documents filed141
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 141 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Occupational CertificateFile: Kabra Garnet JayVikas OC signed 2505420.pdf | 1 Apr 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30 06 2023.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30 06 2023.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30 06 2023.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th June 2023.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30 06 2023.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30 09 2023.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30 09 2023.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate_as on 30 09 2023 lv.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th Sept 2023.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30th Sept 2023.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30 12 2023.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30 12 2023.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30 12 2023.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 31st Dec 2023.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 31st Dec 2023.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate As on 31 Mar 2024.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 31 Mar 2024.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30 03 2024.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 31st March 2024.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 31st Mar 2024.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate As on 30 June 2024.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30 June 2024.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30 June 2024 LV.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th June 2024.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30th June 2024.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate 30th Sept 2024.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate 30th Sept 2024.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate 30th Sept 2024 LR.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30th Sept 2024.pdf | 31 Mar 2026 |
| OthersFile: KG 6 Form 5 Annual Report on Statement of Accounts 31st March 2024 .pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30-12-2024 LR.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30-12-2024 LR.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30-12-2024 LR.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 31st March 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 31st Dec 2024.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 31st March 2025.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 31st March 2025.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 31st March 2025.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 31st March 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 31st Mar 2025.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30th June 2025.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30th June 2025.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30 June 2025.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th June 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30th June 2025.pdf | 31 Mar 2026 |
| OthersFile: KG 7 Form 5 Annual CA Certificate 01 April 2024 To 31 March 2025.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 30th Sept 2025.pdf | 31 Mar 2026 |
| OthersFile: KG 6 Form 2A Engineer Certificate for Quality Assurance as on 30th Sept 2025.pdf | 31 Mar 2026 |
| Form 1File: KG 1 Form 1 Architect Certificate as on 31st Dec 2025.pdf | 31 Mar 2026 |
| Form 2File: KG 2 Form 2 Engineer Certificate as on 31st Dec 2025.pdf | 31 Mar 2026 |
| Form 3File: KG 3 Form 3 CA Certificate as on 31st Dec 2025.pdf | 31 Mar 2026 |
| Disclosure of Sold and Booked InventoryFile: KG 4 Disclosure of Sold and Booked Inventory as on 31st Dec 2025.pdf | 31 Mar 2026 |
| Self-declaration of Quarterly ProgressFile: KG 5 Self Declaration for Quaterly progress as on 31st Dec 2025.pdf | 31 Mar 2026 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate as on 31st March 2025.pdf | 6 May 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate as on 31st March 2025.pdf | 28 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KG Form 3 CA Certificate as on 31st March 2025.pdf | 28 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KG Form 2 Engineer Certificate as on 31st March 2025.pdf | 28 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate as on 30-12-2024 LR.pdf | 21 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KG Form 3 CA Certificate as on 30-12-2024 LR.pdf | 21 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KG Form 2 Engineer Certificate as on 30-12-2024 LR.pdf | 21 Jan 2025 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: KG Form 5 Annual Report on Statement of Accounts 31st March 2024 .pdf | 27 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Kabra Garnet Form 1 Architect Certificate 30th Sept 2024.pdf | 8 Nov 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Kabra Garnet Form 3 CA Certificate 30th Sept 2024 LR.pdf | 8 Nov 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Kabra Garnet Form 2 Engineer Certificate 30th Sept 2024.pdf | 8 Nov 2024 |
| Disclosure of sold/ booked inventoryFile: Kabra Garnet Sold Unsold Inventory 30th Sept 2024.pdf | 8 Nov 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate As on 30 June 2024.pdf | 8 Aug 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KG Form 3 CA Certificate as on 30 June 2024 LV.pdf | 8 Aug 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KG Form 2 Engineer Certificate as on 30 June 2024.pdf | 29 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: KG Form 3 CA Certificate as on 30 03 2024.pdf | 6 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate As on 31 Mar 2024.pdf | 1 May 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KG Form 2 Engineer Certificate as on 31 Mar 2024.pdf | 1 May 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: KG Form 1 Architect Certificate as on 30 12 2023.pdf | 20 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: KG Form 2 Engineer Certificate as on 30 12 2023.pdf | 20 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: KG Sold UnSold Inventory as on 30 12 2023.pdf | 20 Jan 2024 |
Promoter's earlier projects14
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| KABRA DIAMANTEP51800030391 | BELWALKAR WADI GOREGAON WEST, Mumbai Suburban | - | Aug 2021 | Completed | Dec 2025 | Jun 2024 |
| KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSLP51800001067 | Between 4 & 7 Bungalow, Opp. Bonbon, Mumbai Suburban | - | Jul 2017 | Completed | Dec 2022 | Feb 2020 |
| KABRA CENTROID A Redevelopment of GOP CHSLP51800000307 | Andheri, Mumbai Suburban | - | Jul 2017 | Completed | Dec 2021 | Oct 2019 |
| KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society LtdP51800002483 | Andheri, Mumbai Suburban | - | Aug 2017 | Completed | Dec 2021 | Apr 2018 |
| KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSLP51800005550 | Andheri, Mumbai Suburban | - | Aug 2017 | Completed | Dec 2019 | Jan 2019 |
| TILAK Revelopment Project of TILAK APARTMENT CHSLP51800007990 | Andheri, Mumbai Suburban | - | Aug 2017 | Completed | Dec 2017 | Jul 2017 |
| NATRAJ | Corner of Prem Nagar & Sodawala Lane Opp. Prabhodhan Thackarey Hall Borivali West Mumbai 400092 MAHARASHTRA | 93 | - | Completed | Jun 2017 | May 2017 |
| RAGESHREE | Sodawala Lane Opp. Pandya Hospital Borivali West Mumbai - 400 092 MAHARASHTRA | 69 | - | Completed | Jun 2016 | Late, May 2017 |
| KABRA ARGENTUM - UNNAT NAGAR - 43/44 | Plot No. 43 - 44 Unnat Nagar II Off S V Road, Opp Patkar College, Goregaon West Mumbai - 400 104 MAHARASHTRA | 79 | - | Completed | Sep 2015 | Late, Jan 2016 |
| NEW VINAY | Sunder Nagar Near Mumbai University Kalina Santacruz East Mumbai 400 098 MAHARASHTRA | 70 | - | Completed | May 2015 | Late, Dec 2015 |
| CHRISTINA | Shree Nagar Estate Vidyaniketan Marg Off M G Road Goregaon West Mumbai - 400 104 MAHARASHTRA | 51 | - | Completed | May 2015 | Sep 2014 |
| VIHANG | Building No. 16 Siddharth Nagar IV Opp. Vivek College Goregaon West Mumbai - 400 104 MAHARASHTRA | 41 | - | Completed | Mar 2015 | Late, Jun 2017 |
| NANDANWADI | Plot No.257 Jawahar Nagar, Next to Mount Mary High School, Goregaon West Mumbai - 400104 MAHARASHTRA | 21 | - | Completed | Jun 2014 | May 2014 |
| ALYA GARNET | Brahmand Azad Nagar Behind Universal School Brahmand Thane West - 400607 MAHARASHTRA | 107 | - | Completed | Mar 2014 | Dec 2012 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Mumbai Suburban
Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.
Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Useful on a completed registration when you are buying resale, or checking what was promised against what was delivered.
- Red flags and clear checks, the possession story, sanctions and sales, land and title, who you are dealing with
- Joined against the promoter's 7 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 141 filed documents as one ZIP, foldered, with a manifest
Keep KABRA GARNET - Redevelopment of Jayvikas Pre on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Malad West6,700+ in Mumbai Suburban
Filed coordinates, straight-line distance. 327 registered projects within 2 km.
Ruparel Stardom
AMI MODISPACES LLP
Chandak Treesourus
CHANDAK REALTORS PRIVATE LIMITED
ANCHORPOINT AVIARA
YUKTI INFRAPROJECTS LLP
AURIS ILARIA TOWER A
TRANSCON-SHETH CREATORS PRIVATE LIMITED
ADHRIT
MUNDARA DEVELOPERS
IRENE WING B PHASE 1
Sheth Creators and Sunvision Private Limit
See every Mumbai Suburban project, with the district possession charts
Builder: KABRA AND ASSOCIATES
KABRA AND ASSOCIATES has 8 registrations on MahaRERA, including KABRA CENTROID A Redevelopment of GOP CHSL and KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSL. Its filings disclose 14 earlier MahaRERA projects: declares 10 of 14 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.
Frequently asked questions
What are my rights if KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd is delayed beyond 31 Dec 2026?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd?
The registered promoter entity is KABRA AND ASSOCIATES, a partnership as per the filing. Its GSTIN 27AAFFK2000F1ZZ can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd?
The professionals named in the filing: Architect: HEMANT TALATY; Architect: Arch Rushikesh H.; Engineer: Nilesh Paste; Chartered Accountant: MEHUL DHRUV; Chartered Accountant: NARENDRA CHITLANGIA. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback