ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / RAJINFINIA PHASE II WING A WING B WING C

Registration lapsed No litigation declared Residential / Group Housing project

RAJINFINIA PHASE II WING A WING B WING C

By RAJSANKET REALTY LIMITED

RG-MH-49823 · RERA P51800012243 · Last updated on MahaRERA portal: 6 Feb 2025

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 22 months past the filed date
  • 41 complaints at MahaRERA
  • Completion date moved by 12 months
  • 1 extension taken

Clear

  • No litigation declared
  • Separate project account declared
  • Allotment letter follows the model form

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2024Possession promised22 months past this date
15 of 33Construction stages doneacross 3 buildings; furthest along: Slabs of Super Structure, 80%
41Complaints at MahaRERAon this registration
Jump to the 70 documents Report an error

RAJINFINIA PHASE II WING A WING B WING C is a Residential / Group Housing project by RAJSANKET REALTY LIMITED in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800012243 on 1 Sep 2017. Possession was promised by 29 Dec 2024 and is now 22 months past that date. The completion date has moved by 12 months from the original filing. 41 complaints are on record with the regulator.

At a glance

Project

  • NameRAJINFINIA PHASE II WING A WING B WING C
  • TypeResidential / Group Housing
  • Location
    • Ramchandra Lane
    • Malad West
    • Borivali
    • Mumbai Suburban
    • 400064
  • Pincode400064
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800012243
  • ReraGenie IDRG-MH-49823

Builder

  • NameRAJSANKET REALTY LIMITED
  • Entity typeCompany

Key dates

22 months past promisethis monthRegisteredSep 2017First promiseDec 2023Revised toDec 2024

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on1 Sep 2017
  • Promised completion29 Dec 2024
  • Revised completionRevised to 29 Dec 2024 (originally 30 Dec 2023)
  • Buildings3 building records
  • Documents filed70 files

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
WING ANA450000
WING BNA450000
WING CNA450000

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building3

As on 6 Feb 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

15 of 33 construction stages are filed complete across 3 buildings. The stage furthest along is Slabs of Super Structure, at 80%.

WING A64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
WING B64%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises10%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks40%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.5%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%
WING C60%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure80%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises45%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.10%

Progress on shared amenities16

As on 6 Feb 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes20%
Water SupplyYes10%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes50%
Storm Water DrainsYes35%
Landscaping & Tree PlantingYes15%
Street LightingYes20%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes20%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes10%
Energy managemcntYes10%
Fire protection and fire safety requirementsYes10%
Electrical meter room, sub-station, receiving stationYes10%
Aggregate area of recreational Open SpaceYes0%
Open ParkingNoNot applicable
CLUB HOUSE AND ADDITIONAL FACILITIESYes0%

Parking filed498

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots498
Closed/Covered498
BuildingClosed/CoveredTotal
WING A140140
WING B214214
WING C144144

Land and ownership1

MahaRERA does not publish landowner contact details. MahaRERA has published no encumbrance declaration for this project. That is silence on the question, and not a record of clear land.

Land area1,734 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
LandownerVillageDistrict
M/S. ASK CORPORATIONAndheriMumbai Suburban

Approvals and building plan

Permissible FSI50526.98
Proposed, not sanctioned50,527 sq m
Buildings approved3
Buildings sanctioned3

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchACME PLAZA ANDHERI EAST MUMBAI 400093

Certifying professionals and partners1

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectDESIGN CREATIONS & ASSOCIATES
PartnerRole in project
RAJSANKET REALTY LIMITED-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT51800011892Dec 2023 → Dec 2024

Reason as filed by the promoterDue to frequent stopover and resource availability

Complaints filed with MahaRERA41

Case no.ComplainantRespondentFiled
CC006000000141031Khyati ShahRajsanket Realty Limited,25/09/2019
CC006000000195868Atull PhullRajsanket Realty Limited03/02/2021
CC006000000054890Mr NeeleshVirendrabhai Ponda & Mrs Vibhuti Neelesh PondaRajsanket Realty Limited12/06/2018
CC006000000057591Sumit MukherjeeRajsanket Realty Limited16/01/2019
CC006000000078277Bagaria and Company Pvt. Ltd.Rajsanket Realty Limited28/02/2019
CC006000000100463ANIL LALERAJSANKET REALTY LIMITED14/08/2019
CC006000000171528Sapna ShuklaSanket International Limited13/11/2019
CC006000000171539Mr. Vijay Ahuja & Mrs. Seema P AhujaRajsanket Realty Limited21/11/2019
CC006000000171613CLAIRE HENRIK BARRETTO AND ANR.RAJSANKET REALTY LIMITED AND ANR.20/11/2019
CC006000000192298Sargun MehtaRajsanket Realty limited13/03/2020
CC006000000192663Mohit R MehtaRajsanket Realty Limited18/02/2020
CC006000000197971ICICI BankMrs. Khyati Shah12/08/2021
CC006000000192756GEETA PAREKHM/S ASK CORPORATION27/02/2020
CC006000000193469RAJESH P MANCHANDAM/S Rajsanket Realty ltd15/07/2020
CC006000000193572SHABBIR M HUSSAINM/S Rajsanket Realty ltd25/07/2020
CC006000000199201Shilpa MittalRajsanket Realty Limited30/11/2021
CC006000000251437RITA AGARWALRAJSANKET REALTY LIMITED14/06/2022
CC006000000251870Graden D'SouzaRajsanket International Limited12/07/2022
CC006000000261968Garmia MishraRajsanket International Limited01/08/2022
CC006000000261964Ravi AgrawalRAJSANKET INTERNATIONAL LIMITED21/07/2022
CC006000000282116Dhansukh Akhai PatelRajsanket Realty Limited27/07/2022
CC006000000282192Sajan Tom ZachariahRAJSANKET INTERNATIONAL LIMITED04/08/2022
CC006000000292284Gyan BarahRajsanket International Limited13/08/2022
CC006000000292353ALAN D'SOUZARajsanket International Limited16/08/2022
CC006000000292354Sanjay VarmaRAJSANKET INTERNATIONAL LIMITED17/08/2022
CC006000000292378DINESH CHANDNANIRAJSANKET INTERNATIONAL LIMITED18/08/2022
CC006000000292548Nishit SinghRAJSANKET INTERNATIONAL LIMITED30/09/2022
CC006000000292574Rupal Rakesh DoshiSANKET INTERNATIONAL LIMITED09/09/2022
CC006000000303615Jacob KuruvillaRAJSANKET INTERNATIONAL LIMITED09/12/2022
CC006000000303647KULIN SHAHRAJSANKET INTERNATIONAL LIMITED15/12/2022
CC006000000344217Hemant RamchandaniRAJSANKET INTERNATIONAL LIMITED07/02/2023
CC006000000397050Sachin AdyanthayaRAJSANKET REALTY LTD12/08/2023
CC006000000397279KAMLESH AILANIRAJSANKET INTERNATIONAL LIMITED29/08/2023
CC006000000398003SHARAD BOTALJERAJSANKET INTERNATIONAL LIMITED01/11/2023
CC006000000408232HILLOO DAMKEVALARAJSANKET REALTY LIMITED29/11/2023
CC006000000428882PARAS JAINRAJSANKET REALTY LIMITED29/01/2024
CC006000000429069PANKAJ KUMAR AGARWALRAJSANKET REALITY LIMITED, DIRECTOR- HARESHKUMAR VALLABH DAS SUTARIA07/02/2024
CC006000000480250Robin DiasRAJSANKET REALTY LTD27/04/2024
CC006000000500617AMIT KOTHARIMS ASK CORPORATION30/05/2024
CC12400922Ravi Mulchand AhujaRAJSANKET REALTY LIMITED28/11/2024
CC12502702Narendra KatudiaRAJSANKET REALTY LIMITED02/08/2025

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 29 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 17 Oct 2022
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 17 Oct 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 30 May 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateOn the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    uploaded 6 Feb 2025

Documents filed70

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: 2024 10 23 Malad -SRA Amended Cum Part OC issued for Sale Building No 1 - RajInfinia A B C6 Feb 2025
Architect’s Certificate on Completion of Project (Form 4)File: Form 4 Rajsanket 8-1-25.pdf8 Jan 2025
Disclosure of sold/ booked inventoryFile: Final Sold Unsold Rajinfinia.pdf9 Dec 2024
Disclosure of sold/ booked inventoryFile: Rajinfinia Mar 24- Sold Unsold.pdf12 Apr 2024
Disclosure of sold/ booked inventoryFile: Revised Rajfinia Sold Unsold Dec 23.pdf4 Apr 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rajinfinia_compressed.pdf22 Mar 2024
Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: Rajinfinia_compressed.pdf22 Mar 2024
Disclosure of sold/ booked inventoryFile: Malad DM Sale3.pdf16 Jan 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Rajinfinia Phase II - A B C - Form1 - Sep23.pdf20 Nov 2023
Disclosure of sold/ booked inventoryFile: 3 Disclosure of sold_ booked inventory (1).pdf31 May 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold on Rajsanket Letter head.pdf28 Feb 2023
Disclosure of sold/ booked inventoryFile: Sold-Unsold.pdf27 Feb 2023
Layout approvalFile: New IOD.pdf17 Oct 2022
Copy of Layout Approval (in case of layout)File: New IOD.pdf17 Oct 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: RERA Rajsanket 2019 F5.pdf10 Jun 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: RERA Rajsanket 2019 F5.pdf10 Jun 2022
Declaration about Commencement CertificateFile: CC Dec.pdf9 Jun 2022
Disclosure of sold/ booked inventoryFile: Raj Infinia Sold Unsold RERA 31032022-compressed.pdf9 Jun 2022
CERSAI detailsFile: CERSAI_Acknowledgemnt_Report_200217743638_For_Registration_Of_Security_Interest_29_07_20219 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2020 Rajsanket.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2021 Rajsanket.pdf8 Jun 2022
Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)File: Form 2A 2022 Rajsanket.pdf8 Jun 2022
Commencement Certificates / NA Order for plotted developmentFile: cc compressed.pdf30 May 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)File: RERA Rajsanket 2018 F5.pdf29 Oct 2020
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: RERA Rajsanket 2019 F5.pdf29 Oct 2020
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia sale 201019 EC.pdf30 Dec 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Infinia ARC 250719.pdf25 Sep 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale Bldg Engg Cft.pdf21 Aug 2019
Certificates of CA (Form 3)File: RAJ INFINIA CA CERTIFICATE 30042019.pdf24 Jun 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Infinia RERA ARC 300419.pdf9 May 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale 30_04_2019.pdf9 May 2019
Certificates of CA (Form 3)File: RAJ INFINIA CA CERTIFICATE 15112018.pdf8 May 2019
Certificates of CA (Form 3)File: RAJ INFINA CA CERTIFICATE 05022019.pdf8 May 2019
Certificates of CA (Form 3)File: RAJ INFINIA PHASE 2 CA CERTIFICATE 20082018.pdf4 May 2019
Certificates of CA (Form 3)File: RAJ INFINIA RERA CERTIFCATE 31052018.pdf25 Apr 2019
Certificates of CA (Form 3)File: RAJ INFINIA PHASE 2 28022018.pdf22 Mar 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Infinia ARC 050219.pdf20 Feb 2019
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale 05_02_2019.pdf20 Feb 2019
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Infinia ARCH 310518 COM.pdf17 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Raj Infinia 200818 ARC.pdf17 Dec 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RERA Infinia 15-11-18-20181122133634 COMP.pdf17 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale.pdf4 Dec 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale 20_08_18.pdf22 Nov 2018
Details of encumbrancesFile: Infinia encum 29062018.pdf29 Jun 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Infinia Rera_Certificate.pdf9 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale 05_03_18.pdf9 Apr 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Raj Infinia Dec-17 Architect Com.pdf9 Apr 2018
Certificates of CA (Form 3)File: RAJ INFINIA PHASE 2 - 31 DEC 2017 Compressed.pdf21 Mar 2018
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Infinia Sale 05_01_18.pdf7 Feb 2018
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 02 Raj Infinia 300917.pdf21 Nov 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Raj Infinia.pdf21 Nov 2017
Certificates of CA (Form 3)File: 09 RAJ INFINIA-PHASE 2-RESIDENTIAL 30092017.pdf21 Nov 2017
PAN CardFile: Ask Corpn - pan.pdf31 Jul 2017
PAN CardFile: RajSanket PAN.pdf31 Jul 2017
Details of encumbrancesFile: ASK Corp No Encumbrance Certificate.pdf31 Jul 2017
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: RAJ INFINIA ARCHITECT CERTIFICATE.pdf31 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: RAJ INFINIA ENGG CERTIFICATE PHASE 2 SALE BLDG.pdf31 Jul 2017
Certificates of CA (Form 3)File: RAJ INFINIA RESIDENTIAL PH 1.pdf31 Jul 2017
Proforma of Allotment letterFile: ASK_ Draft_ Agreement for Sale.pdf31 Jul 2017
Proforma of Allotment letterFile: Draft Copy of Allotment Letter.pdf31 Jul 2017
Declaration in FORM BFile: Infinia Phase II.pdf30 Jul 2017
OtherFile: Infinia Additional Declaration.pdf30 Jul 2017
Layout approvalFile: LAYOUT APPROVAL.pdf29 Jul 2017
Building plan approvalFile: IOA.pdf29 Jul 2017
Copy of the legal title reportFile: Raj Infinia - Title Report.pdf29 Jul 2017
Details of encumbrancesFile: Infinia pdf.pdf29 Jul 2017
Copy of Layout Approval (in case of layout)File: LAYOUT APPROVAL.pdf29 Jul 2017
Building Plan Approval (IOD)File: IOA.pdf29 Jul 2017
Commencement Certificates / NA Order for plotted developmentFile: CC.pdf29 Jul 2017
Proforma of Allotment letterFile: Raj Infinia pdf.pdf29 Jul 2017

How this compares with Mumbai Suburban

33%of Mumbai Suburban projects moved their completion datethis one moved by 12 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is among them

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep RAJINFINIA PHASE II WING A WING B WING C on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Malad West6,700+ in Mumbai Suburban

2 kmRAJINFINIA PHASE II WINGCompleted 108Lapsed / revoked 65Other 137Dot size: filed unitsN

Filed coordinates, straight-line distance. 310 registered projects within 2 km.

Builder: RAJSANKET REALTY LIMITED

RAJSANKET REALTY LIMITED has 1 registration on MahaRERA, including RAJINFINIA PHASE II WING A WING B WING C. Its filings disclose no earlier MahaRERA projects. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What does it mean that RAJINFINIA PHASE II WING A WING B WING C shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if RAJINFINIA PHASE II WING A WING B WING C is delayed beyond 29 Dec 2024?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of RAJINFINIA PHASE II WING A WING B WING C?

The registered promoter entity is RAJSANKET REALTY LIMITED, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in RAJINFINIA PHASE II WING A WING B WING C?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against RAJINFINIA PHASE II WING A WING B WING C?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for RAJINFINIA PHASE II WING A WING B WING C?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at RAJINFINIA PHASE II WING A WING B WING C?

The professionals named in the filing: Architect: DESIGN CREATIONS & ASSOCIATES. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in RAJINFINIA PHASE II WING A WING B WING C?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About RAJINFINIA PHASE II WING A WING B WING C. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save RAJINFINIA PHASE II WING A WING B WING C to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.