KABRA AND ASSOCIATES: RERA track record
Partnership ยท attribution by exact filing name, entity resolution in progress
KABRA AND ASSOCIATES has 8 registrations in this build, including KABRA CENTROID A Redevelopment of GOP CHSL and KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSL. Its filings disclose 14 earlier MahaRERA projects: 10 of 14 past projects completed on time.
Projects in this build
| Project | Location | Units | Booked | Status |
|---|---|---|---|---|
| KABRA CENTROID A Redevelopment of GOP CHSL | Mumbai Suburban, Maharashtra | - | - | Completed |
| KABRA METRO ONE WING A AND B A Redevelopment Project of PRATAP CHSL | Mumbai Suburban, Maharashtra | - | - | Completed |
| KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society Ltd | Mumbai Suburban, Maharashtra | - | - | Completed |
| TILAK Revelopment Project of TILAK APARTMENT CHSL | Mumbai Suburban, Maharashtra | - | - | Completed |
| KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSL | Mumbai Suburban, Maharashtra | - | - | Completed |
| KABRA DIAMANTE | Mumbai Suburban, Maharashtra | - | - | Completed |
| KABRA GARNET - Redevelopment of Jayvikas Premises Co-Op Hsg Soc Ltd | Mumbai Suburban, Maharashtra | 118 | 60% | Completed |
| KABRA TIARA - Redevelopment of Dindoshi Darshan CHSL | Mumbai Suburban, Maharashtra | 127 | 61% | Registered |
Past projects, as disclosed in RERA filings
| Project | Promised completion | Actual completion | Delivery |
|---|---|---|---|
| ALYA GARNET | 29 Mar 2014 | 12 Dec 2012 | On time |
| NANDANWADI | 30 Jun 2014 | 9 May 2014 | On time |
| VIHANG | 31 Mar 2015 | 10 Jun 2017 | +26 months |
| CHRISTINA | 1 May 2015 | 16 Sep 2014 | On time |
| NEW VINAY | 31 May 2015 | 31 Dec 2015 | +7 months |
| KABRA ARGENTUM - UNNAT NAGAR - 43/44 | 30 Sep 2015 | 20 Jan 2016 | +4 months |
| RAGESHREE | 30 Jun 2016 | 9 May 2017 | +10 months |
| NATRAJ | 30 Jun 2017 | 30 May 2017 | On time |
| TILAK Revelopment Project of TILAK APARTMENT CHSL P51800007990 | 31 Dec 2017 | 18 Jul 2017 | On time |
| KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSL P51800005550 | 31 Dec 2019 | 15 Jan 2019 | On time |
| KABRA CENTROID A Redevelopment of GOP CHSL P51800000307 | 30 Dec 2021 | 16 Oct 2019 | On time |
| KABRA AJANTA Redevelopment of Santacruz Ajanta Premises Co Operative Society Ltd P51800002483 | 30 Dec 2021 | 12 Apr 2018 | On time |
Frequently asked questions
How do I verify KABRA AND ASSOCIATES as a legal entity before signing?
Your agreement for sale must name the exact entity registered for the project, not a group brand. The registration certificate on each project's MahaRERA page names the exact legal entity; ask for it if the sales office only uses a brand name. Large builders commonly register one company or LLP per project, which is normal; the entity on the registration certificate is the one legally accountable to you.
How should I use this delivery record when booking with KABRA AND ASSOCIATES?
Their completed projects have landed on time so far, but apply the same test to the specific project: promised date, current progress, and sales pace. If possession then slips past your agreement date, section 18 entitles you to interest at SBI's highest MCLR plus 2 percent (currently 10.90% per annum) for every month of delay, or an exit with a full refund with interest.
The record above looks clean. What should I still check?
A clean filing history is a good sign, not a guarantee. Filings only show what promoters must disclose: they do not show build quality, the state of approvals still pending, or whether the agreement they offer follows MahaRERA's model clauses. Check the specific project's certificates and agreement deviations, and confirm sales pace is matched by construction pace quarter on quarter.