Home / Browse projects / Pune, Maharashtra / Joyville Hadapsar Annexe Phase 8
Joyville Hadapsar Annexe Phase 8
By Joyville Shapoorji Housing Private Limited
RG-MH-16772 · RERA P52100026785 · Last updated on MahaRERA portal: 28 Sep 2025
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Registration lapsed
- Possession 13 months past the filed date
- Litigation declared, 6 cases
- 1 complaint at MahaRERA
Clear
- Completion date never moved
- No encumbrance on the project land
- Separate project account declared
- Allotment letter follows the model form
- All 10 completed earlier projects delivered on promise
4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
Joyville Hadapsar Annexe Phase 8 is a Residential / Group Housing project by Joyville Shapoorji Housing Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100026785 on 25 Oct 2020. Possession was promised by 30 Sep 2025 and is now 13 months past that date. 1 complaint is on record with the regulator.
At a glance
Project
- NameJoyville Hadapsar Annexe Phase 8
- TypeResidential / Group Housing
- Location
- Off Pune Solapur Highway
- Shewalewadi
- Haveli
- Pune
- 412307
- Pincode412307
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100026785
- ReraGenie IDRG-MH-16772
Builder
- NameJoyville Shapoorji Housing Private Limited
- Entity typeCompany
- CINU70109MH2007PTC166942
- GSTIN27AACCD9800E1ZV
- DirectorsRanjana Agarwal, Subrata Dutta Gupta, Sandeep Awasthi, Anuj Puri, Ashish Singh, Anuj Puri, Sandeep Awasthi, Ashish Singh, Anuj Puri, Sandeep Awasthi, Ashish Singh, Anuj Puri and 29 more
- ChairpersonsVenkatesh Gopalkrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan and 1 more
- Managing DirectorsSriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan and 1 more
- Other registrations50 more →
- Completed23 of 51
- No longer live11 lapsed, de-registered or revoked
- Past their filed date1
- Declared earlier projects14 →
Key dates
Key facts
Registration and timeline
- StatusRegistration lapsed
- Registered on25 Oct 2020
- Promised completion30 Sep 2025
- Revised completionNone
- Buildings1 building record
- Documents filed145 files
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| Tower 5 | NA | 25 | 0 | 0 | 0 | 0 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building1
As on 28 Sep 2025, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
5 of 11 construction stages are filed complete. The stage furthest along is Slabs of Super Structure, at 97%.
Tower 5: 82% average across the applicable activities
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 100% |
| Stilt Floor | 100% |
| Slabs of Super Structure | 97% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 91% |
| Sanitary Fittings within the flats / premises | 100% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 54% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 70% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 89% |
Progress on shared amenities17
As on 28 Sep 2025, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 50% |
| Water Supply | Yes | 90% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 50% |
| Storm Water Drains | Yes | 50% |
| Landscaping & Tree Planting | Yes | 50% |
| Street Lighting | Yes | 50% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 50% |
| Solid Waste Management And Disposal | Yes | 90% |
| Water conservation /Rain water harvesting | Yes | 50% |
| Energy managemcnt | Yes | 90% |
| Fire protection and fire safety requirements | Yes | 90% |
| Electrical meter room, sub-station, receiving station | Yes | 90% |
| Aggregate area of recreational Open Space | Yes | 50% |
| Open Parking | Yes | 50% |
| Covered Parking | Yes | 75% |
| Club House | Yes | 100% |
Parking filed17
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
Land and ownership1
MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.
| Landowner | Village | District |
|---|---|---|
| Manjri Horse Breeders' Farm Private Limited | Mumbai City | Mumbai City |
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | MSK Arch and Associates |
| Engineer | Akshay Lalit Kasar Kasar |
| Chartered Accountant | M S K C and Associates LLP |
| Chartered Accountant | Harshad Doshi & Co. |
| Chartered Accountant | B R Nagda & Co |
| Chartered Accountant | Harshad Doshi |
| Partner | Role in project |
|---|---|
| Joyville Shapoorji Housing Private Limited | - |
Litigation declared6
| Case | Court | Status |
|---|---|---|
| 32/2009 | Court of Civil Judge Senior Division Pune | Evidence Stage |
| WP No 1311 2019/2019 | Bombay High Court | Pre Admission |
| RTS Appeal No 704 2021/2021 | Additional Collector Pune | Pre Admission |
| Special Civil Suit No. 32 of 2009/2009 | Court of Civil Judge Senior Division Pune | Ongoing |
| WP No. 1311 of 2019/2019 | Bombay High Court | Ongoing |
| RTS Appeal No. 704/2021/2021 | Additional Collector, Pune | Ongoing |
Complaints filed with MahaRERA1
| Case no. | Complainant | Respondent | Filed |
|---|---|---|---|
| CC005000000137154 | Sagar Tapare | Joyville Shapoorji Housing Pvt Ltd | 05/06/2022 |
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 21 Oct 2020 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 21 Oct 2020 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 21 Oct 2020 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 21 Oct 2020Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateOn the file
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
uploaded 30 Dec 2024
Documents filed145
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 145 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2024-2025)File: Form 5_Hadapsar Phase 8.pdf | 28 Sep 2025 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Dec 24.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 19 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Dec 24.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 19 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 19 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 19 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Dec 24.pdf | 19 Jan 2025 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 30 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy Bldg 4 5 17 18.pdf | 30 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 30 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy Bldg 4 5 17 18.pdf | 30 Dec 2024 |
| Architect’s Certificate on Completion of Project (Form 4)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 30 Dec 2024 |
| Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFile: OC Copy Bldg 4 5 17 18.pdf | 30 Dec 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Oct 24.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Oct 24.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Oct 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_8.pdf | 20 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 20 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Oct 24.pdf | 20 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 8 - Tower 5.pdf | 20 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_8-_March_24.pdf | 6 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_8-_March_24.pdf | 6 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_8-_March_24.pdf | 6 Oct 2024 |
| Form 5 (FY 2023-2024)File: JHA_Phase_8_Upload.pdf | 27 Sep 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Dec 23.pdf | 20 Jul 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Manjri - Phase-8-Tower-5.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: Phase8.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202406 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 20 Jul 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_March 24.pdf | 19 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Manjri - Phase-8-Tower-5.pdf | 19 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: Phase8.pdf | 19 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202403 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 19 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5__March 23.pdf | 5 Mar 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5_03.pdf | 19 Feb 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase 8_ Tower 5_03.pdf | 19 Feb 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202312 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 17 Jan 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Manjri - Phase-8-Tower-5.pdf | 16 Jan 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 15 Jan 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Dec 23.pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Phase8.pdf | 15 Jan 2024 |
| Disclosure of sold/ booked inventoryFile: Phase 8.pdf | 19 Oct 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 17 Oct 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_Sept 23.pdf | 17 Oct 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202309 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 17 Oct 2023 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Manjri Phase 8.pdf | 29 Sep 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 19 Jul 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5_June 23.pdf | 19 Jul 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202306 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 19 Jul 2023 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)File: Form 2A - Manjri - Phase-8-Tower-5.pdf | 16 May 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 17 Apr 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Phase8.pdf | 17 Apr 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202303 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 17 Apr 2023 |
| Disclosure of sold/ booked inventoryFile: Hadapsar Phase 8.pdf | 14 Jan 2023 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202212 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 14 Jan 2023 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 7 Jan 2023 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5__December 22.pdf | 7 Jan 2023 |
| Disclosure of sold/ booked inventoryFile: Phase 8.pdf | 17 Oct 2022 |
| Disclosure of sold/ booked inventoryFile: Phase 8.pdf | 15 Oct 2022 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202209 RERA Certificate Ph 8 Tower 05 - RERA.pdf | 15 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5__September 22_R1.pdf | 10 Oct 2022 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_8_T5.pdf | 4 Oct 2022 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_8_T5__September 22.pdf | 4 Oct 2022 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)File: Form 2A - Manjri - Phase-8-Tower-5.pdf | 4 Oct 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Phase 8 Certificate Signed.pdf | 30 Sep 2022 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Phase 8 Certificate Signed.pdf | 29 Sep 2022 |
| Disclosure of sold/ booked inventoryFile: Joyville hadapsar Phase 8.pdf | 14 Sep 2022 |
Promoter's earlier projects14
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| Mahindra Citadel Phase 1P52100047656 | Pimpri, Pune | 448 | Nov 2022 | Ongoing | Jun 2028 | Not due yet |
| Mahindra Happinest Tathawade Phase 2P52100045388 | Tathawade, Pune | 314 | May 2022 | Ongoing | May 2027 | Not due yet |
| Nest EWSP52100045279 | Tathawade, Pune | 89 | May 2022 | Ongoing | Jan 2027 | Not due yet |
| Happinest Tathawade Phase-1P52100028049 | Tathawade, Pune | - | Jan 2021 | Ongoing | Jan 2027 | Not due yet |
| Centralis Tower 2P52100019393 | Pimpri, Pune | - | Jan 2019 | Completed | Aug 2023 | Aug 2023 |
| Centralis Tower 1P52100019406 | Pimpri, Pune | - | Jan 2019 | Completed | Aug 2023 | Jul 2023 |
| Centralis Tower 4P52100019375 | Pimpri, Pune | - | Jan 2019 | Completed | Mar 2023 | Mar 2023 |
| Centralis Tower 3P52100019407 | Pimpri, Pune | - | Jan 2019 | Completed | Mar 2023 | Mar 2023 |
| Centro MHADAP52100030814 | Pimpri, Pune | - | Sep 2021 | Completed | Feb 2023 | Feb 2023 |
| Antheia A3P52100000171 | Pimpri, Pune | - | Jul 2017 | Completed | Dec 2020 | Dec 2020 |
| Joyville Howrah | KWIC Howrah | 392 | - | Completed | Jun 2020 | Feb 2020 |
| Antheia B4P52100000281 | Pimpri Chinchawad (M Corp.), Pune | - | Jul 2017 | Completed | Jun 2018 | Jun 2018 |
| Antheia A4P52100000210 | Pimpri Chinchawad (M Corp.), Pune | - | Jul 2017 | Completed | Jun 2018 | Jun 2018 |
| Antheia C1P52100000217 | Pimpri Chinchawad (M Corp.), Pune | - | Jul 2017 | Completed | Mar 2018 | Mar 2018 |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 4 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 50 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 145 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
- A watch tells you the moment that changes, including if the registration lapses or a complaint is filed
- But on this project's record so far, expect it to be quiet. You can also save this project free and keep it on your shortlist
Keep Joyville Hadapsar Annexe Phase 8 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Shewalewadi13,700+ in Pune
Filed coordinates, straight-line distance. 106 registered projects within 2 km.
MAGNACITY - Tower A2
Malnad Project (I) Pvt Ltd
Birla Evam Phase 1
Vypak Properties Private Limited
VTP AURELIA PHASE 1
ASOJ REALTY LLP
GODREJ BOULEVARD
Manjari Housing Projects LLP
Godrej Park Springs
Manjari Housing Projects LLP
VTP DOLCE VITA Phase 1
Ashdan Developers Private Limited
Builder: Joyville Shapoorji Housing Private Limited
Joyville Shapoorji Housing Private Limited has 51 registrations on MahaRERA, including Joyville Virar Phase 1 and Joyville Virar Phase 2. Its filings disclose 14 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 30 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What does it mean that Joyville Hadapsar Annexe Phase 8 shows as registration lapsed on MahaRERA?
A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.
What are my rights if Joyville Hadapsar Annexe Phase 8 is delayed beyond 30 Sep 2025?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of Joyville Hadapsar Annexe Phase 8?
The registered promoter entity is Joyville Shapoorji Housing Private Limited, a company as per the filing. Its CIN U70109MH2007PTC166942 and GSTIN 27AACCD9800E1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in Joyville Hadapsar Annexe Phase 8?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How do I read the complaint cases filed against Joyville Hadapsar Annexe Phase 8?
Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.
How current is the construction progress shown for Joyville Hadapsar Annexe Phase 8?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at Joyville Hadapsar Annexe Phase 8?
The professionals named in the filing: Architect: MSK Arch and Associates; Engineer: Akshay Lalit Kasar Kasar; Chartered Accountant: M S K C and Associates LLP; Chartered Accountant: Harshad Doshi & Co.; Chartered Accountant: B R Nagda & Co; Chartered Accountant: Harshad Doshi. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in Joyville Hadapsar Annexe Phase 8?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback