MAGNACITY - Tower A2
RG-MH-53166 · RERA P52100054476 · Last updated on MahaRERA portal: 29 Sep 2026
Source: official MahaRERA filing
Or get an email each time it changes, with the project watch
Red flags
- Litigation declared, 2 cases
- Completion date moved by 12 months
- 1 extension taken
- Rs 32.00 crore secured on the land, in favour of HDFC Capital Affordable Real Estate Fund
- The declared charge does not appear in the CERSAI report on the filing
Clear
- No complaints on record
- Separate project account declared
- Allotment letter follows the model form
5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.
See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.Saved. When you are ready to decide, the Rs 499 buyer report reads the fine print for you.
MAGNACITY - Tower A2 is a Residential / Group Housing project by Malnad Project (I) Pvt Ltd in Pune, Maharashtra, registered with MahaRERA as P52100054476 on 25 Jan 2024. Possession is promised by 1 Dec 2029. The completion date has moved by 12 months from the original filing. 691 of the 1,080 units on this registration are recorded sold or booked, and 19 of 99 construction stages are filed complete.
At a glance
Project
- NameMAGNACITY - Tower A2
- TypeResidential / Group Housing
- Location
- Solapur Road
- Manjari
- MANJARI Bk
- Haveli
- Pune
- 412307
- Pincode412307
- MapView location on Google Maps (as filed on RERA)
- RERA no.P52100054476
- ReraGenie IDRG-MH-53166
Builder
- NameMalnad Project (I) Pvt Ltd
- Entity typeCompany
- CINU45100PN2017PTC170130
- GSTIN27AAGCK5660F1ZG
- CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
- DirectorsManish Vimalkumar Jain, Yogesh Yeshwant Bhave
- Other registrations2 more →
- Declared earlier projects2 →
Key dates
Key facts
Registration and timeline
- StatusRegistered
- Registered on25 Jan 2024
- Promised completion1 Dec 2029
- Revised completionRevised to 1 Dec 2029 (originally 2 Dec 2028)
- Buildings9 building records
- Documents filed118 files
Current status
Figures as on 29 Sep 2026, this project's latest MahaRERA filing.
Buildings and wings, as sanctioned
| Building | Wing | Floors sanctioned | Habitable floors | Residential units | Other units | Total |
|---|---|---|---|---|---|---|
| A2 - Wing A | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing B | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing C | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing D | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing E | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing F | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing G | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing H | NA | 33 | 30 | 120 | 0 | 120 |
| A2 - Wing J | NA | 33 | 30 | 120 | 0 | 120 |
The full filing
Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.
Construction progress by building9
As on 29 Sep 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.
19 of 99 construction stages are filed complete across 9 buildings. The stage furthest along is Stilt Floor, at 90%.
A2 - Wing A12%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 30% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing B12%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 30% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing C18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing D18%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing E28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 3% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing F28%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 9% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 3% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing G30%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 20% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing H37%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 100% |
| Podiums (if any) | 100% |
| Plinth | 0% |
| Stilt Floor | 90% |
| Slabs of Super Structure | 10% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 5% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
A2 - Wing J9%
| Activity | Progress |
|---|---|
| Excavation | 100% |
| Basement (if any) | 0% |
| Podiums (if any) | 0% |
| Plinth | 0% |
| Stilt Floor | 0% |
| Slabs of Super Structure | 0% |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | 0% |
| Sanitary Fittings within the flats / premises | 0% |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | 0% |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | 0% |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | 0% |
Progress on shared amenities15
As on 29 Sep 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.
| Common facility | Proposed | Progress |
|---|---|---|
| Internal Roads & Footpaths | Yes | 0% |
| Water Supply | Yes | 0% |
| Sewerage (Chamber, Lines, Septic Tank , STP) | Yes | 0% |
| Storm Water Drains | Yes | 0% |
| Landscaping & Tree Planting | Yes | 0% |
| Street Lighting | Yes | 0% |
| Community Buildings | No | Not applicable |
| Treatment And Disposal Of Sewage And Sullage Water | Yes | 0% |
| Solid Waste Management And Disposal | Yes | 0% |
| Water conservation /Rain water harvesting | Yes | 0% |
| Energy managemcnt | Yes | 0% |
| Fire protection and fire safety requirements | Yes | 0% |
| Electrical meter room, sub-station, receiving station | Yes | 0% |
| Aggregate area of recreational Open Space | Yes | 0% |
| Open Parking | Yes | 0% |
Parking filed2484
Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.
| Building | Closed/Covered | Total |
|---|---|---|
| A2 - Wing A | 276 | 276 |
| A2 - Wing B | 276 | 276 |
| A2 - Wing C | 276 | 276 |
| A2 - Wing D | 276 | 276 |
| A2 - Wing E | 276 | 276 |
| A2 - Wing F | 276 | 276 |
| A2 - Wing G | 276 | 276 |
| A2 - Wing H | 276 | 276 |
| A2 - Wing J | 276 | 276 |
Land and ownership
A declared charge means a lender has a claim over the project land. Ask the promoter for a no-objection certificate from the lender named above before you pay any amount.
Approvals and building plan
Project account and cost
70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.
| Building | Wing | Estimated | Incurred |
|---|---|---|---|
| - | NA | Rs 93.40 cr | Rs 29.44 cr |
| A2 - Wing A | NA | Rs 40.61 cr | Rs 2.03 cr |
| A2 - Wing B | NA | Rs 40.61 cr | Rs 2.03 cr |
| A2 - Wing C | NA | Rs 40.61 cr | Rs 3.92 cr |
| A2 - Wing D | NA | Rs 40.61 cr | Rs 2.06 cr |
| A2 - Wing E | NA | Rs 40.61 cr | Rs 6.09 cr |
| A2 - Wing F | NA | Rs 40.61 cr | Rs 7.71 cr |
| A2 - Wing G | NA | Rs 40.61 cr | Rs 10.57 cr |
| A2 - Wing H | NA | Rs 40.61 cr | Rs 9.47 cr |
| A2 - Wing J | NA | Rs 40.61 cr | Rs 1.51 cr |
Certifying professionals and partners6
Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.
| Role | Name |
|---|---|
| Architect | Vishal Deshpande |
| Engineer | Ravindra Kukade |
| Engineer | Suneel Kulkarni |
| Engineer | Amit Nagpure |
| Chartered Accountant | SPAK & Co. |
| Chartered Accountant | GMKS & Co. |
| Partner | Role in project |
|---|---|
| Malnad Project (I) Pvt Ltd | - |
Extensions applied for1
A revised date filed with the regulator does not change the possession date in your agreement for sale.
Reason as filed by the promoterThe project "MAGNACITY - Tower A2" has experienced delays due to unforeseen circumstances beyond the control of the Promoter, including the ongoing geopolitical conflict in West Asia, disruptions in global supply chains, shortages and price escalation of construction materials, the Ready-Mix Concrete (RMC) suppliers' strike, labour shortages caused by elections,disruption in commercial LPG supply, and infrastructure constraints affecting labour welfare and productivity.
Litigation declared2
| Case | Court | Status |
|---|---|---|
| 271/2017 | Civil Judge Senior Division Pune | Pending |
| 271/2017 | Civil Judge Senior | Ongoing |
Complaints filed with MahaRERA
No complaints on record against this registration.
The permission chain
The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.
- Legal title reportOn the file
A lawyer's report on who owns the land and what is registered against it.
uploaded 6 Jan 2024 - Layout approvalOn the file
The planning authority's approval of how the plots and buildings sit on the land.
uploaded 31 Dec 2025 - Building plan approvalOn the file
Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.
uploaded 2 Dec 2025 - Commencement CertificateOn the file
Permission to begin construction. On a plotted development the same slot carries the NA order instead.
uploaded 22 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying. - Occupancy CertificateNot due yet
The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.
possession is promised for 1 Dec 2029
Documents filed118
As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 118 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.
| Document | Uploaded |
|---|---|
| Form 5 (FY 2025-2026)File: Form 5_MAGNA_A2_Signed.pdf | 29 Sep 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate.pdf | 18 Jul 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 18 Jul 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate.pdf | 18 Jul 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate.pdf | 20 Apr 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 20 Apr 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate (1).pdf | 20 Apr 2026 |
| Form 2A (FY 2025-2026)File: Form 2A_March 2026_signed copy.pdf | 20 Apr 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate signed.pdf | 17 Jan 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 17 Jan 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate.pdf | 17 Jan 2026 |
| Withdrawal Update Form 1File: 1_Ar Certificate.pdf | 15 Jan 2026 |
| Withdrawal Update Form 2File: 2_Engg Certificate.pdf | 15 Jan 2026 |
| Withdrawal Update Form 3File: 3_CA Certificate.pdf | 15 Jan 2026 |
| Layout approvalFile: 1_Layout.pdf | 31 Dec 2025 |
| Building plan approvalFile: 2_250618_A1 & A2_Parking_compressed.pdf | 2 Dec 2025 |
| Building plan approvalFile: 3_250618_A1 & A2_UG Parking_compressed.pdf | 2 Dec 2025 |
| Building plan approvalFile: 4_250618_A1 & A2_LG Parking_compressed.pdf | 2 Dec 2025 |
| Building plan approvalFile: 8_250618_A2_Sec-Ele_compressed.pdf | 2 Dec 2025 |
| Building plan approvalFile: 9_250618_A2_Sec-Ele_compressed.pdf | 2 Dec 2025 |
| Building plan approvalFile: A1 and A2 Parking Plan.pdf | 5 Nov 2025 |
| Building plan approvalFile: A1 and A2UG Parking 8.pdf | 5 Nov 2025 |
| Building plan approvalFile: A1 and A2 LG Parking 9.pdf | 5 Nov 2025 |
| Building plan approvalFile: A2 Bldg refuge fl Plan 12_rotated.pdf | 5 Nov 2025 |
| Building plan approvalFile: A2 Bldg Typ fl Plan 13_rotated.pdf | 5 Nov 2025 |
| Building plan approvalFile: A2 Bldg All fl Plan 14_rotated_compressed 1.pdf | 5 Nov 2025 |
| Building plan approvalFile: A2Sec-Ele 15.pdf | 5 Nov 2025 |
| Building plan approvalFile: 9A2 Sec-Ele 16_rotated.pdf | 5 Nov 2025 |
| Layout approvalFile: Layout magna city (1).pdf | 4 Nov 2025 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA Certificate_Signed.pdf | 31 Oct 2025 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 30 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate_Signed.pdf | 30 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA Certificate_Signed.pdf | 30 Oct 2025 |
| Withdrawal Update Form 1File: 1_Ar Certificate_Signed.pdf | 29 Oct 2025 |
| Withdrawal Update Form 2File: 2_Engg Certificate_Signed.pdf | 29 Oct 2025 |
| Withdrawal Update Form 3File: 3_CA Certificate_Signed.pdf | 29 Oct 2025 |
| Form 5 (FY 2024-2025)File: Form 5_MAGNACITY_A2_Signed.pdf | 22 Sep 2025 |
| Layout approvalFile: 1_250618_Sector 1B_Layout.pdf | 22 Jul 2025 |
| Building plan approvalFile: 6_250618_A2_Bldg Typ fl Plan.pdf | 22 Jul 2025 |
| Building plan approvalFile: 5_250618_A2_Bldg refuge fl Plan.pdf | 22 Jul 2025 |
| Building plan approvalFile: 7_250618_A2_Bldg All fl Plan.pdf | 22 Jul 2025 |
| Commencement certificateFile: 250618 RS 1 _CC.pdf | 22 Jul 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate_compressed.pdf | 19 Apr 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 19 Apr 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 19 Apr 2025 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory_compressed (1).pdf | 19 Apr 2025 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: 5_Form 2A.pdf | 19 Apr 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate_Signed_compressed.pdf | 20 Jan 2025 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 20 Jan 2025 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jan 2025 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold_compressed.pdf | 20 Jan 2025 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Ar Certificate_compressed.pdf | 28 Oct 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate.pdf | 28 Oct 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 28 Oct 2024 |
| Disclosure of sold/ booked inventoryFile: 5_Disclosure of sold inventory_compressed.pdf | 28 Oct 2024 |
| Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: MAGNACITY Tower A2_compressed.pdf | 17 Oct 2024 |
| Proforma of Agreement for saleFile: 240809_A2_AFS_R6.pdf | 12 Aug 2024 |
| Proforma of Agreement for saleFile: 240812_A2_AFS_R7.pdf | 12 Aug 2024 |
| Proforma of Agreement for saleFile: 240812_A2_AFS_R7_1.pdf | 12 Aug 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate_compressed.pdf | 20 Jul 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Jul 2024 |
| Disclosure of sold/ booked inventoryFile: 6_Disclosure of Sold Inventory_compressed.pdf | 20 Jul 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: rera_008-compressed.pdf | 20 Jul 2024 |
| Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 240605_Declaration of Separate Bank Account.pdf | 7 Jun 2024 |
| Other - FinanceFile: 240605_Annexure A_Declaration cum Undertaking.pdf | 7 Jun 2024 |
| Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 1_Arch Certificate_compressed.pdf | 20 Apr 2024 |
| Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 2_Engg Certificate.pdf | 20 Apr 2024 |
| Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: 5_Form 2A.pdf | 20 Apr 2024 |
| Disclosure of sold/ booked inventoryFile: MAGNACITY - Tower A2.pdf | 20 Apr 2024 |
| CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3_CA Certificate_compressed.pdf | 20 Apr 2024 |
| Home Buyer /Allottee Grievance Redressal CellFile: 240326_Decl about Grievance Redressal Cell.pdf | 26 Mar 2024 |
| Proforma of Agreement for saleFile: 240208_A2_AFS_R4.pdf | 12 Feb 2024 |
| Proforma of Agreement for saleFile: 240123_AFS_R3.pdf | 23 Jan 2024 |
| Building plan approvalFile: 240105_Layout.pdf | 6 Jan 2024 |
| Copy of the legal title reportFile: 240105_Legal Title Report_Pg 1 to 30.pdf | 6 Jan 2024 |
Promoter's earlier projects1
As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.
| Project | Location | Flats | Registered | Status | Promised | Delivered |
|---|---|---|---|---|---|---|
| MAGNACITY - Tower A3P52100052096 | Manjari, Pune | 480 | Jul 2023 | Ongoing | May 2028 | Not due yet |
Comparing a few projects?
You have opened several on ReraGenie. A free account keeps them in one list with their booking and possession figures, and puts two to six of them side by side.
How this compares with Pune
Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.
Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.
Buyer report
Built from this project's filings on the day you order, in plain language.
- 5 conditions on this project's record read and explained, with the clear checks alongside
- Joined against the promoter's 2 other registrations and every project registered within 2 km, which the RERA portal never shows together
- All 118 filed documents as one ZIP, foldered, with a manifest
- The project watch below, included free for 90 days
Project watch
Only want to be told when something changes?
- An email each time this filing moves: new sales, a moved possession date, an extension, a complaint, the occupancy certificate
- Plain words, conditions that have happened marked in red
- A summary of everything that changed when the 90 days end
Keep MAGNACITY - Tower A2 on your shortlist
Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.
Other projects near Manjari13,700+ in Pune
Filed coordinates, straight-line distance. 87 registered projects within 2 km.
Birla Evam Phase 1
Vypak Properties Private Limited
VTP AURELIA PHASE 1
ASOJ REALTY LLP
GODREJ BOULEVARD
Manjari Housing Projects LLP
Godrej Park Springs
Manjari Housing Projects LLP
VTP DOLCE VITA Phase 1
Ashdan Developers Private Limited
VTP EUPHORIA PHASE 3
ASHDAN DEVELOPERS PRIVATE LIMITED
Builder: Malnad Project (I) Pvt Ltd
Malnad Project (I) Pvt Ltd has 3 registrations on MahaRERA, including MAGNACITY - Tower A3 and MAGNACITY - Tower A2. Its filings disclose 2 earlier MahaRERA projects, none completed yet. Litigation is declared on 3 of its registrations. Read the full track record. See more projects on the Pune district page.
Frequently asked questions
What are my rights if MAGNACITY - Tower A2 is delayed beyond 1 Dec 2029?
Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.
How do I verify and contact the developer of MAGNACITY - Tower A2?
The registered promoter entity is Malnad Project (I) Pvt Ltd, a company as per the filing. Its CIN U45100PN2017PTC170130 and GSTIN 27AAGCK5660F1ZG can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.
Is my payment protected in MAGNACITY - Tower A2?
Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.
How current is the construction progress shown for MAGNACITY - Tower A2?
Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.
Who certifies construction progress at MAGNACITY - Tower A2?
The professionals named in the filing: Architect: Vishal Deshpande; Engineer: Ravindra Kukade; Engineer: Suneel Kulkarni; Engineer: Amit Nagpure; Chartered Accountant: SPAK & Co.; Chartered Accountant: GMKS & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.
What should I check before booking in MAGNACITY - Tower A2?
Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.
Get the buyer report · Rs 499 See a real one first
Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.
Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.
Report an error Share feedback