Home / Browse projects / Pune, Maharashtra / Joyville Hadapsar Annexe Phase 15

Registration lapsed Litigation declared Residential / Group Housing project

Joyville Hadapsar Annexe Phase 15

By Joyville Shapoorji Housing Private Limited

RG-MH-78870 · RERA P52100034911 · Last updated on MahaRERA portal: 20 Jul 2026

Source: official MahaRERA filing

Red flags

  • Registration lapsed
  • Possession 4 months past the filed date
  • Litigation declared, 6 cases
  • Completion date moved by 3 months
  • 1 extension taken

Clear

  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 10 completed earlier projects delivered on promise

5 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Jun 2026Possession promised4 months past this date
10 of 11Construction stages donefurthest along: Podiums (if any), 0%
0 of 132Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 123 documents Report an error

Joyville Hadapsar Annexe Phase 15 is a Residential / Group Housing project by Joyville Shapoorji Housing Private Limited in Pune, Maharashtra, registered with MahaRERA as P52100034911 on 28 Apr 2022. Possession was promised by 30 Jun 2026 and is now 4 months past that date. The completion date has moved by 3 months from the original filing. 132 of the 132 units on this registration are recorded sold or booked, and 10 of 11 construction stages are filed complete.

At a glance

Project

  • NameJoyville Hadapsar Annexe Phase 15
  • TypeResidential / Group Housing
  • Location
    • Off Pune Solapur Highway
    • Shewalewadi
    • Haveli
    • Pune
    • 412307
  • Pincode412307
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100034911
  • ReraGenie IDRG-MH-78870

Builder

  • NameJoyville Shapoorji Housing Private Limited
  • Entity typeCompany
  • CINU70109MH2007PTC166942
  • GSTIN27AACCD9800E1ZV
  • DirectorsRanjana Agarwal, Subrata Dutta Gupta, Sandeep Awasthi, Anuj Puri, Ashish Singh, Anuj Puri, Sandeep Awasthi, Ashish Singh, Anuj Puri, Sandeep Awasthi, Ashish Singh, Anuj Puri and 29 more
  • ChairpersonsVenkatesh Gopalkrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan, Venkatesh Gopalakrishnan and 1 more
  • Managing DirectorsSriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan, Sriram Mahadevan and 1 more
  • Other registrations50 more →
  • Completed23 of 51
  • No longer live11 lapsed, de-registered or revoked
  • Past their filed date1
  • Declared earlier projects14 →

Key dates

4 months past promisethis monthRegisteredApr 2022First promiseMar 2026Revised toJun 2026

Key facts

Registration and timeline

  • StatusRegistration lapsed
  • Registered on28 Apr 2022
  • Promised completion30 Jun 2026
  • Revised completionRevised to 30 Jun 2026 (originally 31 Mar 2026)
  • Buildings1 building record
  • Documents filed123 files

Current status

100%132 of 132 units booked
100.0%Work done, per cost certificate

Figures as on 20 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Tower 15NA24221320132

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 20 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

10 of 11 construction stages are filed complete. The stage furthest along is Podiums (if any), at 0%.

Tower 15: 91% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 20 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes75%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes75%
Storm Water DrainsYes75%
Landscaping & Tree PlantingYes75%
Street LightingYes75%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes95%
Solid Waste Management And DisposalYes90%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes90%
Fire protection and fire safety requirementsYes90%
Electrical meter room, sub-station, receiving stationYes90%
Aggregate area of recreational Open SpaceYes75%
Open ParkingYes75%

Parking filed58

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots58
Closed/Covered58

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area701 sq m
Land owned byNot the promoter
Named landowners1
Encumbrance on the landDeclared none
Declared on28 Jul 2025
LandownerVillageDistrict
Manjri Horse Breeders' Private LimitedMumbai CityMumbai City

Approvals and building plan

Sanctioning authorityPune Metropolitan Region Development Authority
Permissible FSI6342.64
Proposed, not sanctioned6,343 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchICICI Bank Ltd., Bombay Hub, Z Wing, Kamla Mill Compound, Senapati Bapat Marg, Lower Parel, Mumbai.400013, Maharashtra
Estimated costRs 30.25 cr
Cost incurredRs 30.25 cr
Work done100.0%
BuildingWingEstimatedIncurred
Tower 15NARs 22.04 crRs 22.04 cr
-NARs 8.22 crRs 8.22 cr

Certifying professionals and partners8

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMSK Architectsand Associates
EngineerAkshay Lalit Kasar
EngineerG A Bhilare Bhilare
Chartered AccountantBhavesh Nagda
Chartered AccountantM S K C and Associates LLP
Chartered AccountantHarshad Doshi & Co.
Chartered AccountantPooja Rajendrakumar Boob
Chartered AccountantB R Nagda & co
PartnerRole in project
Joyville Shapoorji Housing Private Limited-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA21032620319Mar 2026 → Jun 2026

Reason as filed by the promoteras on 11 February 2026, a Government Resolution (GR) was issued appointing Pune Municipal Corporation (PMC) as the planning authority for 23 newly merged villages within PMC limits. Following this resolution, PMRDA halted all ongoing files at their current stage and sent a letter to the UDD (Urban Development Department) seeking clarity on the transition. As of now, the clarity on this matter from UDD is pending. Therefore, completion certificate is pending. We kindly request an extension by 30/06/2026 to obtain completion certificate of the project

Litigation declared6

CaseCourtStatus
32/2009Court of Civil Judge Senior Division PuneEvidence Stage
WP No 1311 2019/2019Bombay High CourtPre Admission
RTS Appeal No 704 2021/2021Additional Collector PunePre Admission
Special Civil Suit No. 32 of 2009/2009Court of Civil Judge Senior Division PuneOngoing
WP No. 1311 of 2019/2019Bombay High CourtOngoing
RTS Appeal No. 704/2021/2021Additional Collector, PuneOngoing

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 21 Apr 2022
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 20 Jul 2026
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 21 Apr 2022
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 18 Apr 2022Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot on the file

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

Documents filed123

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 123 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Layout approvalFile: 6 Sanctioned Layout_031024.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15_Updated.pdf20 Jul 2026
Withdrawal Update Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_July 26_Updated.pdf20 Jul 2026
Withdrawal Update Form 3File: CA RERA Certificate Ph 15 - updated.pdf20 Jul 2026
Form 2A (FY 2025-2026)File: Form 2A_Hadapsar_Phase_15.pdf20 Jul 2026
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Apr 2026
Withdrawal Update Form 2File: Form 2_Hadapsar Annex_Phase_15_T15_March 26.pdf20 Apr 2026
Withdrawal Update Form 3File: 202603 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Apr 2026
Form 2A (FY 2024-2025)File: 2a.pdf21 Mar 2026
Withdrawal Update Form 1File: FORM 1_Joyville Hadapsar Annex_Phase_15.pdf24 Jan 2026
Withdrawal Update Form 2File: FORM 2_Hadapsar Annex_Phase_15_T15_December 25.pdf24 Jan 2026
Withdrawal Update Form 3File: FORM 3_CA Certificate Ph 15 Tower 15 - RERA_page-0001.pdf24 Jan 2026
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Oct 2025
Withdrawal Update Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_Sept 25.pdf20 Oct 2025
Withdrawal Update Form 3File: 202509 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Oct 2025
Form 5 (FY 2024-2025)File: Form 5_Hadapsar Phase 15.pdf28 Sep 2025
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf13 Aug 2025
Withdrawal Update Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_June 25.pdf13 Aug 2025
Withdrawal Update Form 3File: 202506 RERA Certificate Ph 15 Tower 15 - RERA.pdf13 Aug 2025
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf1 Aug 2025
Withdrawal Update Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf1 Aug 2025
Withdrawal Update Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_June 25.pdf1 Aug 2025
Withdrawal Update Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_June 25.pdf1 Aug 2025
Withdrawal Update Form 3File: 202506 RERA Certificate Ph 15 Tower 15 - RERA.pdf1 Aug 2025
Withdrawal Update Form 3File: 202506 RERA Certificate Ph 15 Tower 15 - RERA.pdf1 Aug 2025
Form 1File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf17 Jul 2025
Form 2File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_June 25.pdf17 Jul 2025
Form 3File: 202506 RERA Certificate Ph 15 Tower 15 - RERA.pdf17 Jul 2025
Disclosure of Sold and Booked InventoryFile: Joyville Hadapsar Annexe Phase 15 - Tower 15.pdf17 Jul 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202503 RERA Certificate Ph 15 Tower 15 - RERA.pdf21 Apr 2025
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: MahaRERA Regulations_Form 2A_Phase_15.pdf21 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Apr 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Engineer_s Certificate_Hadapsar Annex_Phase_15_T15_March 25.pdf20 Apr 2025
Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 15 - Tower 15.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 15 - Tower 15.pdf20 Jan 2025
Disclosure of sold/ booked inventoryFile: Joyville Hadapsar Annexe Phase 15 - Tower 15.pdf20 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Dec 24.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 15 Tower 15 - RERA.pdf19 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Dec 24.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 15 Tower 15 - RERA.pdf19 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf19 Jan 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202412 RERA Certificate Ph 15 Tower 15 - RERA.pdf19 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Dec 24.pdf19 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Oct 24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Oct 24.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Form 1_Joyville Hadapsar Annex_Phase_15.pdf20 Oct 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202409 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Oct 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Oct 24.pdf20 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_15-_March_24.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_15-_March_24.pdf6 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: Hadapsar_Annexe_Phase_15-_March_24.pdf6 Oct 2024
Form 5 (FY 2023-2024)File: Hadapsar_Annex_Phase_15_Upload.pdf28 Sep 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_15_T15.pdf20 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Dec 23.pdf20 Jul 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)File: Form 2A - Manjri - Phase-15-Tower-15.pdf20 Jul 2024
Disclosure of sold/ booked inventoryFile: Phase15.pdf20 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202406 RERA Certificate Ph 15 Tower 15 - RERA.pdf20 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_15_T15.pdf19 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_March 24.pdf19 Apr 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Manjri - Phase-15-Tower-15.pdf19 Apr 2024
Disclosure of sold/ booked inventoryFile: Phase15.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202403 RERA Certificate Ph 15 Tower 15 - RERA.pdf19 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Joyville Hadapsar Annex, Phase 15-30th June 2022.pdf23 Feb 2024
Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)File: Form 2A - Manjri - Phase-15-Tower-15.pdf16 Jan 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_15_T15.pdf15 Jan 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Dec 23.pdf15 Jan 2024
Disclosure of sold/ booked inventoryFile: Phase15.pdf15 Jan 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202312 RERA Certificate Ph 15 Tower 15 - RERA.pdf15 Jan 2024
Disclosure of sold/ booked inventoryFile: Phase 15.pdf19 Oct 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_15_T15.pdf18 Oct 2023
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer's Certificate_Hadapsar Annex_Phase_15_T15_Sept 23.pdf18 Oct 2023
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 202309 RERA Certificate Ph 15 Tower 15 - RERA.pdf18 Oct 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: Manjri Phase 15.pdf29 Sep 2023
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect's Certificate Hadapsar Annex_Phase_15_T15.pdf19 Jul 2023

Promoter's earlier projects14

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

10 delivered on promise4 under way, not due yet
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Mahindra Citadel Phase 1P52100047656Pimpri, Pune448Nov 2022OngoingJun 2028Not due yet
Mahindra Happinest Tathawade Phase 2P52100045388Tathawade, Pune314May 2022OngoingMay 2027Not due yet
Nest EWSP52100045279Tathawade, Pune89May 2022OngoingJan 2027Not due yet
Happinest Tathawade Phase-1P52100028049Tathawade, Pune-Jan 2021OngoingJan 2027Not due yet
Centralis Tower 2P52100019393Pimpri, Pune-Jan 2019CompletedAug 2023Aug 2023
Centralis Tower 1P52100019406Pimpri, Pune-Jan 2019CompletedAug 2023Jul 2023
Centralis Tower 4P52100019375Pimpri, Pune-Jan 2019CompletedMar 2023Mar 2023
Centralis Tower 3P52100019407Pimpri, Pune-Jan 2019CompletedMar 2023Mar 2023
Centro MHADAP52100030814Pimpri, Pune-Sep 2021CompletedFeb 2023Feb 2023
Antheia A3P52100000171Pimpri, Pune-Jul 2017CompletedDec 2020Dec 2020
Joyville HowrahKWIC Howrah392-CompletedJun 2020Feb 2020
Antheia B4P52100000281Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedJun 2018Jun 2018
Antheia A4P52100000210Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedJun 2018Jun 2018
Antheia C1P52100000217Pimpri Chinchawad (M Corp.), Pune-Jul 2017CompletedMar 2018Mar 2018

How this compares with Pune

100%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 3 months
26%of Pune registrations have lapsed or been cancelledthis one is among them

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Joyville Hadapsar Annexe Phase 15 on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Shewalewadi13,700+ in Pune

2 kmJoyville Hadapsar AnnexeCompleted 49Lapsed / revoked 17Other 44Dot size: filed unitsN

Filed coordinates, straight-line distance. 110 registered projects within 2 km.

Builder: Joyville Shapoorji Housing Private Limited

Joyville Shapoorji Housing Private Limited has 51 registrations on MahaRERA, including Joyville Virar Phase 1 and Joyville Virar Phase 2. Its filings disclose 14 earlier MahaRERA projects: declares 10 of 10 past projects completed on time. Litigation is declared on 30 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What does it mean that Joyville Hadapsar Annexe Phase 15 shows as registration lapsed on MahaRERA?

A registration runs until the completion date the promoter declared. If the project is neither completed nor extended by then it lapses, and a de-registration or revocation ends it by order. In every case the promoter may no longer legally advertise, market or sell in the project, and the Authority can act under section 7 against a defaulting promoter. What it does not do is cancel an agreement for sale you have already signed, or extinguish your section 18 right to delay interest or refund; those run from your agreement, not from the registration. Get the current position from the promoter in writing, verify it on the MahaRERA portal, and take legal advice before paying any further instalment.

What are my rights if Joyville Hadapsar Annexe Phase 15 is delayed beyond 30 Jun 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Joyville Hadapsar Annexe Phase 15?

The registered promoter entity is Joyville Shapoorji Housing Private Limited, a company as per the filing. Its CIN U70109MH2007PTC166942 and GSTIN 27AACCD9800E1ZV can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Joyville Hadapsar Annexe Phase 15?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Joyville Hadapsar Annexe Phase 15?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Joyville Hadapsar Annexe Phase 15?

The professionals named in the filing: Architect: MSK Architectsand Associates; Engineer: Akshay Lalit Kasar; Engineer: G A Bhilare Bhilare; Chartered Accountant: Bhavesh Nagda; Chartered Accountant: M S K C and Associates LLP; Chartered Accountant: Harshad Doshi & Co.. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Joyville Hadapsar Annexe Phase 15?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Joyville Hadapsar Annexe Phase 15. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Joyville Hadapsar Annexe Phase 15 to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.