ReraGenieLog inGet a buyer report

Home / Browse projects / Mumbai Suburban, Maharashtra / Horizon Atulya

Registered No litigation declared Residential / Group Housing project

Horizon Atulya

By HORIZON PROMOTERS INDIA LTD

RG-MH-07347 · RERA P51800055546 · Last updated on MahaRERA portal: 24 Jul 2026

Source: official MahaRERA filing

Red flags

  • Completion date moved by 6 months
  • 1 extension taken

Clear

  • No litigation declared
  • No complaints on record
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

2 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 6 months from the original
7 of 11Construction stages donefurthest along: External plumbing and external plaster, 95%
13 of 47Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 72 documents Report an error

Horizon Atulya is a Residential / Group Housing project by HORIZON PROMOTERS INDIA LTD in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51800055546 on 2 Apr 2024. Possession is promised by 31 Dec 2026. The completion date has moved by 6 months from the original filing. 34 of the 47 units on this registration are recorded sold or booked, and 7 of 11 construction stages are filed complete.

At a glance

Project

  • NameHorizon Atulya
  • TypeResidential / Group Housing
  • Location
    • Junction of J N Road And Valji Ladha Road
    • Mulund West
    • Mulund
    • Kurla
    • Mumbai Suburban
    • 400080
  • Pincode400080
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51800055546
  • ReraGenie IDRG-MH-07347

Builder

  • NameHORIZON PROMOTERS INDIA LTD
  • Entity typeCompany
  • CINU45200MH1987PLC244801
  • GSTIN27AAACH5024N1ZI
  • CIN and GSTIN are from this promoter's other MahaRERA registrations. This project's own filing does not repeat them.
  • DirectorsJAY DINESH BHEDA, DINESH SHAMJI BHEDA
  • Other registrations5 more →
  • Completed3 of 6
  • Declared earlier projects6 →

Key dates

this monthRegisteredApr 2024First promiseJun 2026Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on2 Apr 2024
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 21 Jun 2026)
  • Buildings1 building record
  • Documents filed72 files

Current status

72%34 of 47 units booked
102.5%Work done, per cost certificate

Figures as on 24 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Mulund Hansa Villa CHS LtdNA1613311647

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building1

As on 24 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

7 of 11 construction stages are filed complete. The stage furthest along is External plumbing and external plaster, at 95%.

Mulund Hansa Villa CHS Ltd: 87% average across the applicable activities

ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises20%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%

Progress on shared amenities15

As on 24 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes50%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes100%
Storm Water DrainsNoNot applicable
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes75%
Energy managemcntYes0%
Fire protection and fire safety requirementsYes60%
Electrical meter room, sub-station, receiving stationYes100%
Aggregate area of recreational Open SpaceYes100%
Open ParkingYes100%

Parking filed94

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots94
Closed/Covered77
Open Space17

Land and ownership2

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area1,470 sq m
Land owned byThe promoter, with other names on the file
Named landowners2
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on21 Jan 2026
LandownerVillageDistrict
Horizon Promoters India LtdMulundMumbai Suburban
Mulund Hansa Villa CHS LtdMulundMumbai Suburban

Approvals and building plan

Sanctioning authorityMCGM
Permissible FSI4703.19
Proposed, not sanctioned3,201 sq m
Buildings approved1
Buildings sanctioned1

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchSharda Pristine Dr Ambedkar Road Mulund West
Estimated costRs 50.51 cr
Cost incurredRs 51.76 cr
Work done102.49%
BuildingWingEstimatedIncurred
Mulund Hansa Villa CHS LtdNARs 50.51 crRs 51.76 cr

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectGA Design
EngineerSystem Structural Consultants Pvt. Ltd.
EngineerNayan Paresh Raval
Chartered AccountantBID & Associates
Chartered AccountantCHK & Associates
Chartered AccountantYatin Vasant Ruparel
PartnerRole in project
HORIZON PROMOTERS INDIA LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EA15062621371Jun 2026 → Dec 2026

Reason as filed by the promoterThe project has experienced delays on account of delayed approvals resulting from the subsequent imposition of road setback requirements, which necessitated modifications to the project plans and the obtaining of revised approvals from the concerned authorities. Detailed explanatory note is attached with the application.

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 22 Dec 2023
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 11 Jan 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 13 Oct 2025
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Apr 2026Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed72

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Architect Certificate Q1 26-27.pdf24 Jul 2026
Withdrawal Update Form 2File: FORM 2 ENGINEERS CERTIFICATE_HORIZON PROMOTERS INDIA LIMITED_HORIZON ATULYA_(2026-27Q1)_1824 Jul 2026
Withdrawal Update Form 3File: Form 3 Horizon Atulya - June 2026.pdf24 Jul 2026
Withdrawal Update Form 1File: Architect Certificate Q4 Atulya.pdf6 Jun 2026
Withdrawal Update Form 2File: FORM 2_ENGINEERS CERTIFICATE_HORIZON_ATULYA(2025-26Q4).pdf6 Jun 2026
Withdrawal Update Form 3File: Form 3 Horizon Atulya - March 2026.pdf6 Jun 2026
Form 2A (FY 2025-2026)File: Form 2A -FY-25-26.pdf16 May 2026
Withdrawal Update Form 1File: Architect Certificate Q4 Atulya.pdf22 Apr 2026
Withdrawal Update Form 2File: FORM 2_ENGINEERS CERTIFICATE_HORIZON_ATULYA(2025-26Q4).pdf22 Apr 2026
Withdrawal Update Form 3File: Form 3 Horizon Atulya - March 2026.pdf22 Apr 2026
Commencement certificateFile: Full CC - Horizon Atulya.pdf10 Apr 2026
Withdrawal Update Form 1File: Architect Certificate.pdf10 Apr 2026
Withdrawal Update Form 2File: FORM 2_ENGINEERS CERTIFICATE_HORIZON PROMOTERS_ATULYA_(2025-26Q3)_20012026_DS.pdf10 Apr 2026
Withdrawal Update Form 3File: Form 3 Horizon Atulya - Dec 2025 (1).pdf10 Apr 2026
Withdrawal Update Form 1File: Architect Certificate Sept 2025.pdf21 Jan 2026
Withdrawal Update Form 2File: Form 2-Atulya Engineer Certificate-Sept 25.pdf21 Jan 2026
Withdrawal Update Form 3File: Form 3 Horizon Atulya - Sept 2025.pdf21 Jan 2026
Building plan approvalFile: Amended Letter - 01-07-2025.pdf13 Oct 2025
Building plan approvalFile: Amended Plan - 01-07-2025.pdf13 Oct 2025
Form 5 (FY 2024-2025)File: Form 5 Horizon Atulya_FY24-25.pdf4 Oct 2025
Form 1File: Architect Certificate June 2025.pdf18 Jul 2025
Form 2File: Form 2 Engineer Certificate Horizon AtulyaJune 25.pdf18 Jul 2025
Form 3File: Form 3 - June 2025 Hansa Villa.pdf18 Jul 2025
Disclosure of Sold and Booked InventoryFile: Disclosure Of Sold - Unsold Inventory June 2025..pdf18 Jul 2025
Form 3File: Form 3 - Horizon Atulya.pdf11 Jun 2025
Form 1File: Architect Certificate March 2025.pdf11 Jun 2025
Form 2File: Engineer Certificate.pdf11 Jun 2025
Disclosure of Sold and Booked InventoryFile: Disclosure of Sold-unsold inventory.pdf11 Jun 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Horizon Atulya Form 3.pdf31 Jan 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate.pdf31 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate - Horizon Atulya.pdf14 Jan 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Certificate September 2024.pdf14 Nov 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Horizon Atulya.pdf14 Nov 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Cert - Compressed - Sep 2024.pdf14 Nov 2024
Building plan approvalFile: Amended Plan compressed.pdf9 Oct 2024
Building plan approvalFile: Amended Plan Letter.pdf9 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Amended Plan compressed.pdf9 Oct 2024
Building Plan Approval / NA Order for plotted developmentFile: Amended Plan Letter.pdf9 Oct 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate Hansavilla Horizon Atulya Compressed.pdf26 Jul 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Architect certificate.pdf26 Jul 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - Horizon Atulya.pdf26 Jul 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect certificate 31032024.pdf23 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 - March 2024 - Horizon Atulya signed.pdf23 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineer Certificate March 2024.pdf20 Apr 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: Form 3 Horizon Atulya.pdf14 Mar 2024
Declaration in FORM BFile: Declaration in Form B - Hansa Villa CHS Ltd.pdf27 Feb 2024
Other - LegalFile: Index II.pdf16 Feb 2024
Proforma of Agreement for saleFile: Agreement for Sale - Draft revised.pdf2 Feb 2024
Status of ConveyanceFile: Index-II.pdf2 Feb 2024
Status of ConveyanceFile: Deemed Conveyance with Index II.pdf2 Feb 2024
Declaration in FORM BFile: Declaration in Form B - HPIL.pdf25 Jan 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: 2 Disclosure of interest in other Organisations.pdf24 Jan 2024
Details of encumbrances concerned to FinanceFile: Encumbrance Details 2.pdf17 Jan 2024
Details of encumbrances concerned to LegalFile: Encumbrance Details 2.pdf17 Jan 2024
Building plan approvalFile: IOD Plan - Hansa Villa - Highlighted Built up Area.pdf11 Jan 2024
Building plan approvalFile: IOD Plan - Hansa Villa.pdf11 Jan 2024
Layout approvalFile: IOD Plan - Hansa Villa.pdf11 Jan 2024
Copy of Layout Approval (in case of layout)File: IOD Plan - Hansa Villa.pdf11 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Plan - Hansa Villa - Highlighted Built up Area.pdf11 Jan 2024
Building Plan Approval / NA Order for plotted developmentFile: IOD Plan - Hansa Villa.pdf11 Jan 2024
Commencement Certificates / NA Order for plotted developmentFile: 2402713_FirstCC_signed.pdf25 Dec 2023
Declaration about Commencement CertificateFile: Form D - Declaration about CC.pdf25 Dec 2023
Proforma of Allotment letterFile: Allotment Letter - Draft.pdf25 Dec 2023
Deviation Report with respect to Allotment letterFile: Deviation report - Allotment Letter.pdf25 Dec 2023
Deviation Report with respect to model copy of AgreementFile: Deviation Report Agreement for Sale.pdf25 Dec 2023
Building plan approvalFile: IOD Plan - Hansa Villa.pdf22 Dec 2023
PAN CardFile: HPIL Pan Card.pdf22 Dec 2023
Copy of the legal title reportFile: Rera title certificate.pdf22 Dec 2023
Building Plan Approval / NA Order for plotted developmentFile: IOD Plan - Hansa Villa.pdf22 Dec 2023
CERSAI detailsFile: Undertaking-CERSAI.pdf22 Dec 2023
CERSAI detailsFile: CERSAI Details.pdf22 Dec 2023
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: Declaration of separate Bank account.pdf22 Dec 2023

Promoter's earlier projects6

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

3 delivered on promise3 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
Horizon GiridarshanP51800049813Mulund West, Mumbai Suburban-Feb 2023CompletedJun 2025Oct 2024
HORIZON SHLOKAP51800029955MULUND WEST, Mumbai Suburban-Jul 2021CompletedMay 2023Late, Feb 2024
HORIZON SAMYAKP51800005791MULUND WEST, Mumbai Suburban-Aug 2017CompletedMar 2019Late, Jul 2023
HORIZON SPANDANR.H.B.ROAD MULUND WEST MUMBAI 40008028-CompletedDec 2017Apr 2017
HORIZON PEARLPLOT NO 18B OFF G.G.ROAD MULUND WEST MUMBAI 40008019-CompletedMar 2015Late, Sep 2015
HORIZON FLORAKASTURBA ROAD MULUND WEST MUMBAI 40008035-CompletedOct 2014Aug 2014

How this compares with Mumbai Suburban

72%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one moved by 6 months
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Horizon Atulya on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Mulund West6,700+ in Mumbai Suburban

2 kmHorizon AtulyaCompleted 123Lapsed / revoked 99Other 150Dot size: filed unitsN

Filed coordinates, straight-line distance. 372 registered projects within 2 km.

Builder: HORIZON PROMOTERS INDIA LTD

HORIZON PROMOTERS INDIA LTD has 6 registrations on MahaRERA, including HORIZON SAMYAK and HORIZON SHLOKA. Its filings disclose 6 earlier MahaRERA projects: declares 3 of 6 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Horizon Atulya is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Horizon Atulya?

The registered promoter entity is HORIZON PROMOTERS INDIA LTD, a company as per the filing. Its CIN U45200MH1987PLC244801 and GSTIN 27AAACH5024N1ZI can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Horizon Atulya?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Horizon Atulya?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Horizon Atulya?

The professionals named in the filing: Architect: GA Design; Engineer: System Structural Consultants Pvt. Ltd.; Engineer: Nayan Paresh Raval; Chartered Accountant: BID & Associates; Chartered Accountant: CHK & Associates; Chartered Accountant: Yatin Vasant Ruparel. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Horizon Atulya?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Horizon Atulya. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Horizon Atulya to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.