Haware Sky

By HAWARE SKY LLP

RG-MH-17653 · RERA P51700066480 · Last updated on MahaRERA portal: 31 Jul 2026

Source: official MahaRERA filing

Red flags

  • No red flags in this filing

Clear

  • No litigation declared
  • No complaints on record
  • Completion date never moved
  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form
  • All 2 earlier projects delivered on promise

Nothing adverse is on this record. The buyer report still reads the filed documents themselves, and places this filing against every project registered within 2 km.

See what the report covers Free either way: or have every new Mumbai Suburban registration emailed to you, free during the pilot beta.
Feb 2029Possession promisedno revision filed
6 of 22Construction stages doneacross 2 buildings; furthest along: Slabs of Super Structure, 94%
40 of 128Units unsoldnot recorded sold or booked
0Complaints at MahaRERAon this registration
Jump to the 82 documents Report an error

Haware Sky is a Others project by HAWARE SKY LLP in Mumbai Suburban, Maharashtra, registered with MahaRERA as P51700066480 on 11 Jun 2024. Possession is promised by 10 Feb 2029. 88 of the 128 units on this registration are recorded sold or booked, and 6 of 22 construction stages are filed complete.

At a glance

Project

  • NameHaware Sky
  • TypeOthers
  • Location
    • Subhash Nagar
    • Chembur
    • Kurla
    • Mumbai Suburban
    • 400071
  • Pincode400071
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P51700066480
  • ReraGenie IDRG-MH-17653

Builder

  • NameHAWARE SKY LLP
  • Entity typePartnership
  • GSTIN27AAOFH4796C1Z0
  • PartnersAnil Kumar Singh, Ujjwala Satish Haware
  • Declared earlier projects2 →

Key dates

this monthRegisteredJun 2024PromisedFeb 2029

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on11 Jun 2024
  • Promised completion10 Feb 2029
  • Revised completionNone
  • Buildings2 building records
  • Documents filed82 files

Current status

69%88 of 128 units booked
58.4%Work done, per cost certificate

Figures as on 31 Jul 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
Haware Sky - Wing ANA1153659
Haware Sky - Wing BNA1164569

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building2

As on 31 Jul 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

6 of 22 construction stages are filed complete across 2 buildings. The stage furthest along is Slabs of Super Structure, at 94%.

Haware Sky - Wing A51%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure94%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks76%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.21%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Haware Sky - Wing B51%
ActivityProgress
Excavation100%
Basement (if any)0%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure94%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises60%
Sanitary Fittings within the flats / premises6%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks76%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.21%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Progress on shared amenities15

As on 31 Jul 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsNoNot applicable
Water SupplyYes0%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes0%
Storm Water DrainsYes0%
Landscaping & Tree PlantingYes0%
Street LightingNoNot applicable
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterNoNot applicable
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes0%
Energy managemcntNoNot applicable
Fire protection and fire safety requirementsYes0%
Electrical meter room, sub-station, receiving stationYes0%
Aggregate area of recreational Open SpaceNoNot applicable
Open ParkingNoNot applicable

Parking filed31

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots31
Closed/Covered31
BuildingClosed/CoveredTotal
Haware Sky - Wing A1515
Haware Sky - Wing B1616

Land and ownership1

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area888 sq m
Land owned byThe promoter, with other names on the file
Named landowners1
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on20 May 2026
LandownerVillageDistrict
Nirmal Pragati Co-op Hsg Soc LtdGreater Mumbai (M Corp.) (Part) (802794)Mumbai Suburban

Approvals and building plan

Sanctioning authorityMAHADA
Permissible FSI5930.01
Proposed, not sanctioned5,930 sq m
Buildings approved2
Buildings sanctioned2

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchVashi Branch Mumbai-400705
Estimated costRs 25.94 cr
Cost incurredRs 15.15 cr
Work done58.42%
BuildingWingEstimatedIncurred
Haware Sky - Wing ANARs 12.23 crRs 7.58 cr
Haware Sky - Wing BNARs 12.23 crRs 7.58 cr
-NARs 1.49 cr-

Certifying professionals and partners6

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectMr.Indrajeet Deshmukh (M/s Vastu Creations)
EngineerM/s. Piyushkumar Keshavlal Sura.
EngineerArvind Jaisingh Kadam
EngineerS D ABHYANKAR
Chartered AccountantRISHI SEKHRI
Chartered AccountantMUGHDA BAJAJ
PartnerRole in project
HAWARE SKY LLP-

Complaints filed with MahaRERA

No complaints on record against this registration.

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 18 May 2024
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 5 Feb 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 27 Dec 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2025Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 10 Feb 2029

Documents filed82

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 82 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: FORM 01 Haware Sky Architect Certificate Q1 FY 2026-27.pdf31 Jul 2026
Withdrawal Update Form 1File: FORM 01 Haware Sky Architect Certificate Q1 FY 2026-27.pdf31 Jul 2026
Withdrawal Update Form 1File: FORM 01 Haware Sky Architect Certificate Q1 FY 2026-27.pdf31 Jul 2026
Withdrawal Update Form 2File: FORM 02 Haware Sky Engineers Certificate Q1 FY 2026 27.pdf31 Jul 2026
Withdrawal Update Form 2File: FORM 02 Haware Sky Engineers Certificate Q1 FY 2026 27.pdf31 Jul 2026
Withdrawal Update Form 2File: FORM 02 Haware Sky Engineers Certificate Q1 FY 2026 27.pdf31 Jul 2026
Withdrawal Update Form 3File: FORM 3 HSLLP Q4 FY 2025 26signed.pdf31 Jul 2026
Withdrawal Update Form 3File: FORM 3 HSLLP Q1 FY 2026 27 signed.pdf31 Jul 2026
Withdrawal Update Form 3File: FORM 3 HSLLP Q1 FY 2026 27 signed.pdf31 Jul 2026
Withdrawal Update Form 1File: Form 1-Architect Certificate-Haware Sky.pdf5 Jun 2026
Withdrawal Update Form 2File: Form 2-Engineer Certificate Haware Sky.pdf5 Jun 2026
Withdrawal Update Form 3File: FORM 3 HSLLP Q4 FY 2025 26signed.pdf5 Jun 2026
Form 2A (FY 2024-2025)File: Form 2A- Quality Assurance-2024-25.pdf4 May 2026
Form 2A (FY 2025-2026)File: Form 2A- Quality Assurance-2025-26.pdf4 May 2026
Form 1File: Architect Form 1.pdf30 Apr 2026
Form 2File: Engineers Certificate Form 2.pdf30 Apr 2026
Form 3File: FORM 3 Haware Sky Q2 24 25.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD - Q2- FY 2024-25_signed.pdf30 Apr 2026
Form 1File: Architect Certificate Bldg No 33 Chembur 24 01 2025.pdf30 Apr 2026
Form 2File: Engineers Certication Bldg No 33 Chembur 24 01 2025.pdf30 Apr 2026
Form 3File: FORM 3 Haware Sky 31 12 24 Signed.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD - Q3- FY 2024-25_signed.pdf30 Apr 2026
Form 1File: Architect Certificate Bldg No 33 Haware Sky.pdf30 Apr 2026
Form 2File: Engineers Certificate Bldg 33 Haware Sky.pdf30 Apr 2026
Form 3File: FORM 3 Haware Sky 31 03 2025 Signed.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD - Q4- FY 2024-25_signed.pdf30 Apr 2026
Form 1File: Haware Sky Architect Certificate.pdf30 Apr 2026
Form 2File: Haware Sky Engineers Certificate Q1.pdf30 Apr 2026
Form 3File: FORM 3 Haware Sky 30 06 25 Sign.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD Q1 FY 2025 26.pdf30 Apr 2026
Form 1File: Architect Certificate Haware Sky 2.pdf30 Apr 2026
Form 2File: Engineers Certificate Haware Sky 2.pdf30 Apr 2026
Form 3File: FORM 3 Haware Sky 30 09 25 Sign.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD Q2 FY 2025 26.pdf30 Apr 2026
Form 1File: Architect Certificate Haware Sky Chembur-.pdf30 Apr 2026
Form 2File: Engineer Certificate Haware Sky Chembur 31122025-.pdf30 Apr 2026
Form 3File: FORM 3 HSLLP Q3 FY 25 26 REVISED.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD Q3 FY 2025 26.pdf30 Apr 2026
Form 1File: Architect Form 1.pdf30 Apr 2026
Form 2File: Engineers Certificate form 2.pdf30 Apr 2026
Form 3File: CA Certificate on Project Cost AND Fund withdrawal Form 3.pdf30 Apr 2026
Disclosure of Sold and Booked InventoryFile: DISCLOSURE OF SOLD - Q1- FY 2024-25_signed.pdf30 Apr 2026
Commencement Certificates / NA Order for plotted developmentFile: COMMENCEMENT CERTIFICATE - CC -MHADA -13788_furthercc_signed.pdf10 Jul 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 4 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf24 Apr 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 4 CA Certificate on Project Cost and Fund withdrawal Form 3.pdf24 Apr 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 4 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf24 Apr 2025
Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFile: 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow20 Feb 2025
Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)File: 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B).p20 Feb 2025
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf6 Feb 2025
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: 3 CA Certificate on Project Cost and Fund withdrawal Form 3.pdf6 Feb 2025
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: 3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf6 Feb 2025
Building plan approvalFile: 02 AMENDED IOA SANCTION DRGS 291024_compressed.pdf27 Dec 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: Architect Form 1.pdf27 Dec 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Haware Sky Q2 24 25.pdf27 Dec 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: Engineers Certificate Form 2.pdf27 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 01 Amended IOA Letter.pdf27 Dec 2024
Commencement Certificates / NA Order for plotted developmentFile: 01Further Commencement Certificate.pdf27 Dec 2024
Building Plan Approval / NA Order for plotted developmentFile: 02 AMENDED IOA SANCTION DRGS 291024_compressed.pdf27 Dec 2024
Proforma of Agreement for saleFile: Agreement for sale.pdf5 Jun 2024
CERSAI detailsFile: Declaration for Cresai revised.pdf30 May 2024
Other - TechnicalFile: Declaration to Annexure A.pdf30 May 2024
Copy of the legal title reportFile: Legal Title Report-compressed.pdf18 May 2024
Building plan approvalFile: 1 Building Plan Approval _ NA Order for plotted development.pdf10 May 2024
Details of encumbrances concerned to FinanceFile: Encumbrances.pdf10 May 2024
Details of encumbrances concerned to LegalFile: Encumbrances.pdf10 May 2024
Building Plan Approval / NA Order for plotted developmentFile: 1 Building Plan Approval _ NA Order for plotted development.pdf10 May 2024
Declaration about Commencement CertificateFile: d Declaration about Commencement Certificate Format-D.pdf10 May 2024
CA Certificate on Project Cost & Fund withdrawal (Form 3)File: FORM 3 Revised.pdf10 May 2024
Deviation Report with respect to model copy of AgreementFile: Deveiation sheet.pdf10 May 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate.pdf29 Apr 2024
Architect’s Certificate of Percentage of Completion of Work (Form 1)File: 10 Architect Form 1.pdf29 Apr 2024
Engineer’s Certificate on Cost Incurred on Project (Form 2)File: (1) Engineers Certificate form 2.pdf8 Apr 2024
Proforma of Allotment letterFile: Allotment Letter.pdf8 Apr 2024
Layout approvalFile: 1 Copy of Layout Approval (in case of layout).pdf5 Feb 2024
PAN CardFile: Haware Sky LLP Pancard.pdf5 Feb 2024
Details of encumbrances concerned to FinanceFile: a Emcumbrance.pdf5 Feb 2024
Details of encumbrances concerned to LegalFile: a Emcumbrance.pdf5 Feb 2024
Copy of Layout Approval (in case of layout)File: 1 Copy of Layout Approval (in case of layout).pdf5 Feb 2024
Declaration in FORM BFile: Form B-Affidavit cum Declaration.pdf5 Feb 2024
Disclosure of Interest in Other Real Estate OrganizationsFile: b Disclosure of Interest in Other Real Estate Organizations.pdf5 Feb 2024

Promoter's earlier projects2

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

2 delivered on promise
ProjectLocationFlatsRegisteredStatusPromisedDelivered
HAWARE AMARAP51800049029Vikhroli East, Mumbai Suburban157Jan 2023Certificate SignedJan 2028Jun 2025
Haware AlturaP51800029411Vikhroli East, Mumbai Suburban-May 2021Certificate SignedApr 2026Mar 2024

How this compares with Mumbai Suburban

69%of this project is bookeddistrict median 30%
33%of Mumbai Suburban projects moved their completion datethis one has not
21%of Mumbai Suburban registrations have lapsed or been cancelledthis one is on the register

Computed across the 6,700+ Mumbai Suburban projects on ReraGenie, from their own filings.

Free monthly report: Mumbai on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Haware Sky on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Chembur6,700+ in Mumbai Suburban

2 kmHaware SkyCompleted 156Lapsed / revoked 117Other 129Dot size: filed unitsN

Filed coordinates, straight-line distance. 402 registered projects within 2 km.

Builder: HAWARE SKY LLP

HAWARE SKY LLP has 1 registration on MahaRERA, including Haware Sky. Its filings disclose 2 earlier MahaRERA projects: declares 2 of 2 past projects completed on time. Read the full track record. See more projects on the Mumbai Suburban district page.

Frequently asked questions

What are my rights if Haware Sky is delayed beyond 10 Feb 2029?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Haware Sky?

The registered promoter entity is HAWARE SKY LLP, a partnership as per the filing. Its GSTIN 27AAOFH4796C1Z0 can be cross-checked on the MCA and GST portals. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Haware Sky?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How current is the construction progress shown for Haware Sky?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Haware Sky?

The professionals named in the filing: Architect: Mr.Indrajeet Deshmukh (M/s Vastu Creations); Engineer: M/s. Piyushkumar Keshavlal Sura.; Engineer: Arvind Jaisingh Kadam; Engineer: S D ABHYANKAR; Chartered Accountant: RISHI SEKHRI; Chartered Accountant: MUGHDA BAJAJ. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Haware Sky?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; the promoter's record on their other projects, not just this one; whether construction progress keeps pace with sales in the coming quarters. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Haware Sky. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Haware Sky to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.