Gloria Grand

By PARANJAPE SCHEMES (CONSTRUCTION) LTD

RG-MH-07707 · RERA P52100001380 · Last updated on MahaRERA portal: 29 Jun 2026

Source: official MahaRERA filing

Red flags

  • Litigation declared, 1 case
  • 2 complaints at MahaRERA
  • Completion date moved by 45 months
  • 1 extension taken

Clear

  • No encumbrance on the project land
  • Separate project account declared
  • Allotment letter follows the model form

4 conditions are on this record. What each one means for someone buying here, and what the promoter's own filed documents say behind it, is what the buyer report adds.

See what the report covers Free either way: or have every new Pune registration emailed to you, free during the pilot beta.
Dec 2026Possession promisedmoved 45 months from the original
29 of 44Construction stages doneacross 4 buildings; furthest along: Internal walls, 98%
45 of 291Units unsoldnot recorded sold or booked
2Complaints at MahaRERAon this registration
Jump to the 93 documents Report an error

Gloria Grand is a Others project by PARANJAPE SCHEMES (CONSTRUCTION) LTD in Pune, Maharashtra, registered with MahaRERA as P52100001380 on 27 Jul 2017. Possession is promised by 31 Dec 2026. The completion date has moved by 45 months from the original filing. 246 of the 291 units on this registration are recorded sold or booked, and 29 of 44 construction stages are filed complete. 2 complaints are on record with the regulator.

At a glance

Project

  • NameGloria Grand
  • TypeOthers
  • Location
    • Paud Road
    • Bavadhan
    • Bavadhan BK
    • Mulshi
    • Pune
    • 411021
  • Pincode411021
  • MapView location on Google Maps (as filed on RERA)
  • RERA no.P52100001380
  • ReraGenie IDRG-MH-07707

Builder

  • NamePARANJAPE SCHEMES (CONSTRUCTION) LTD
  • Entity typeCompany
  • ChairpersonSHRIKANT PURUSHOTTAM PARANJAPE
  • Managing DirectorSHASHANK PURUSHOTTAM PARANJAPE
  • Other registrations28 more →
  • Completed15 of 29
  • No longer live7 lapsed, de-registered or revoked
  • Declared earlier projects17 →

Key dates

this monthRegisteredJul 2017First promiseMar 2023Revised toDec 2026

Key facts

Registration and timeline

  • StatusRegistered
  • Registered on27 Jul 2017
  • Promised completion31 Dec 2026
  • Revised completionRevised to 31 Dec 2026 (originally 30 Mar 2023)
  • Buildings4 building records
  • Documents filed93 files

Current status

85%246 of 291 units booked
91.7%Work done, per cost certificate

Figures as on 29 Jun 2026, this project's latest MahaRERA filing.

Buildings and wings, as sanctioned

BuildingWingFloors sanctionedHabitable floorsResidential unitsOther unitsTotal
B1NA20201080108
B2NA25251380138
H1NA7702424
H2NA7721021

The full filing

Everything below is from the project's own MahaRERA filing, free to read. The Rs 499 buyer report reads the filed documents themselves and puts the findings in plain language.

Construction progress by building4

As on 29 Jun 2026, the date of the latest filing. The RERA activity checklist for each building, from the promoter's latest quarterly progress filing. These are the promoter's own figures, not an independent inspection.

29 of 44 construction stages are filed complete across 4 buildings. The stage furthest along is Internal walls, at 98%.

B1100%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)100%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
B285%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises98%
Sanitary Fittings within the flats / premises70%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.80%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.90%
H136%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure65%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises10%
Sanitary Fittings within the flats / premises0%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks25%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
H282%
ActivityProgress
Excavation100%
Basement (if any)100%
Podiums (if any)0%
Plinth100%
Stilt Floor0%
Slabs of Super Structure100%
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
Sanitary Fittings within the flats / premises100%
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Progress on shared amenities15

As on 29 Jun 2026, the date of the latest filing. Lifts, roads, water and the other shared works, from the same quarterly filing, and reported by the promoter rather than inspected.

Common facilityProposedProgress
Internal Roads & FootpathsYes95%
Water SupplyYes100%
Sewerage (Chamber, Lines, Septic Tank , STP)Yes95%
Storm Water DrainsYes95%
Landscaping & Tree PlantingYes85%
Street LightingYes90%
Community BuildingsNoNot applicable
Treatment And Disposal Of Sewage And Sullage WaterYes0%
Solid Waste Management And DisposalYes0%
Water conservation /Rain water harvestingYes100%
Energy managemcntYes50%
Fire protection and fire safety requirementsYes80%
Electrical meter room, sub-station, receiving stationYes95%
Aggregate area of recreational Open SpaceYes10%
Open ParkingYes0%

Parking filed288

Slots recorded per building wing in the filing. MahaRERA does not publish a two wheeler or four wheeler split, visitor parking, or the sanctioned allotment, so this is provision as filed and not a comparison against the approved plan.

Total parking slots288
Closed/Covered218
Open Space70
BuildingClosed/CoveredOpen SpaceTotal
B110017117
B210017117
H1122436
H261218

Land and ownership11

MahaRERA does not publish landowner contact details. Declared none is the promoter's own declaration to the regulator, not a title search. A search at the sub-registrar is what confirms it.

Land area8,371 sq m
Land owned byThe promoter, with other names on the file
Named landowners11
Encumbrance on the landDeclared none
CERSAI search filedYes
Declared on17 Jul 2025
LandownerVillageDistrict
Suresh Baburao KaranjawaneBavadhan BKPune
Kamal Suresh KaranjawaneBavadhan BKPune
Sailesh Suresh KaranjawaneBavadhan BKPune
Sayali Suresh KaranjawaneBavadhan BKPune
Chandrakant Baburao KaranjawaneBavadhan BKPune
Archana Chandrakant KaranjawaneBavadhan BKPune
Vedanta Chandrakant KaranjawaneBavadhan BKPune
Siddhant Chandrakant KaranjawaneBavadhan BKPune
Rajendra Baburao KaranjawaneBavadhan BKPune
Surekha Raju KaranjawaneBavadhan BKPune
Rohan Raju KaranjawaneBavadhan BKPune

Approvals and building plan

Sanctioning authorityPune Municipal Corporation
Permissible FSI18067.78
Proposed, not sanctioned6,431 sq m
Buildings approved4
Buildings sanctioned4

Project account and cost

70 percent of buyer money must sit in the project account. Account numbers are not published by MahaRERA, so check that your agreement for sale names a designated account for this project and pay into that account only.

Separate project accountDeclared
Bank branchBHANDARKAR ROAD PUNE
Estimated costRs 108.64 cr
Cost incurredRs 99.61 cr
Work done91.68%
BuildingWingEstimatedIncurred
B2NARs 44.91 crRs 43.29 cr
B1NARs 33.07 crRs 31.88 cr
-NARs 22.56 crRs 20.13 cr
H1NARs 5.05 crRs 1.26 cr
H2NARs 3.05 crRs 3.05 cr

Certifying professionals and partners4

Form 1, 2 and 3 certificates from these professionals release the promoter's withdrawals from the 70 percent account.

RoleName
ArchitectAnkur Associates
EngineerChnadrashekhar
Chartered AccountantKapure & Kapure
Chartered AccountantM S K A & Associates
PartnerRole in project
PARANJAPE SCHEMES (CONSTRUCTION) LTD-

Extensions applied for1

A revised date filed with the regulator does not change the possession date in your agreement for sale.

EXT52100011633Mar 2023 → Dec 2026

Reason as filed by the promoterVarious approvals etc have been received quite late. Covid has also caused considerable delay in the execution of the project both in terms of time as well as other resources. A detailed note has been attached herewith explaining to all the reasons for delay and therefore request for extension.

Litigation declared1

CaseCourtStatus
377/15/2015C J S D PUNEMatter is kept for hearing

Complaints filed with MahaRERA2

Case no.ComplainantRespondentFiled
CC005000000310361SAURABH SANTOSH DAMLEPARANJAPE SCHEMES (CONSTRUCTION) LTD12/02/2024
CC12400666Digvijay Dinkar PatilPARANJAPE SCHEMES (CONSTRUCTION) LTD05/11/2024

The permission chain

The permissions a project needs, in the order they happen, matched to MahaRERA's own document slots. A slot on the file means the promoter uploaded a document there; it is not proof the permission was granted, and the filing carries no issue dates. An empty slot is not proof an approval is missing.

  1. Legal title reportOn the file

    A lawyer's report on who owns the land and what is registered against it.

    uploaded 11 Jul 2017
  2. Layout approvalOn the file

    The planning authority's approval of how the plots and buildings sit on the land.

    uploaded 10 Jul 2024
  3. Building plan approvalOn the file

    Sanction of the building plans themselves, filed as an IOD in Mumbai and as a plan approval elsewhere.

    uploaded 10 Jul 2024
  4. Commencement CertificateOn the file

    Permission to begin construction. On a plotted development the same slot carries the NA order instead.

    uploaded 10 Jul 2024Confirm the Commencement Certificate covers the specific floor you are buying.
  5. Occupancy CertificateNot due yet

    The legal go-ahead to move in. It comes at the end, so its absence on a project still under construction is expected.

    possession is promised for 31 Dec 2026

Documents filed93

As listed on the registration, named by the MahaRERA slot each file was filed under, with the promoter's own file name beneath; the newest 80 of 93 are shown. The files themselves are available at source: open this registration on the MahaRERA portal. We publish what the filing says and never host the promoter's documents in place of it.

DocumentUploaded
Withdrawal Update Form 1File: Form 1.pdf29 Jun 2026
Withdrawal Update Form 1File: FROM1 -Gloria -Sept 2025.pdf29 Jun 2026
Withdrawal Update Form 1File: Form 1 Gloria Grand.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2 Gloria Grand.pdf29 Jun 2026
Withdrawal Update Form 2File: Form 2-Gloria Grand.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 - June 25_compressed.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 - Sep 25-compressed.pdf29 Jun 2026
Withdrawal Update Form 3File: Form 3 Gloria Grand Dec 25-compressed.pdf29 Jun 2026
Form 5 (FY 2024-2025)File: Form 5 Gloria Grand 24-25.pdf8 Nov 2025
Disclosure of sold/ booked inventoryFile: GLORIA - MAHA RERA SOLD,UNSOLD DEC 2024-compressed.pdf5 May 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Glorai Grand-Mar'25-uploaded.pdf18 Apr 2025
Certificates of CA (Form 3)File: FORM 3-Gloria Grand -SEPT'24-uploaded.pdf11 Apr 2025
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2-Gloria Grand-Mar'25-uploaded.pdf11 Apr 2025
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1 GLORIA DEC'2024-uploaded.pdf27 Feb 2025
Certificates of CA (Form 3)File: FORM 3- Gloria Grand B1B2 H1 H2-June'24-uploaded.pdf16 Jan 2025
Disclosure of sold/ booked inventoryFile: Disclosure of inventory -Gloria Grand maharera 30 sep 24-uploaded-.pdf19 Oct 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Gloria Grand-Sept'24-uploaded.pdf17 Oct 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)File: FORM 5-Gloria Grand-FY '23-24-uploaded.pdf7 Oct 2024
Layout approvalFile: Layout-Gloaria-28 June 24-compressed-uploaded.pdf10 Jul 2024
Building plan approvalFile: Building plan approval-GG-JUne'24-compressed-uploaded.pdf10 Jul 2024
Copy of Layout Approval (in case of layout)File: Layout-Gloaria-28 June 24-compressed-uploaded.pdf10 Jul 2024
Building Plan Approval (IOD)File: Building plan approval-GG-JUne'24-compressed-uploaded.pdf10 Jul 2024
Commencement Certificates / NA Order for plotted developmentFile: Commencement Cert -GG-June'24-uploaded.pdf10 Jul 2024
Declaration about Commencement CertificateFile: Format D-GG-Declrn for CC-09July2024-uploaded.pdf10 Jul 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 27 FORM 2-Gloria Grand-June'24-uploaded.pdf9 Jul 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 18 Gloria Grand-FORM 1-June'24-uploaded.pdf4 Jul 2024
Layout approvalFile: H1-GG -Sanctioned Layout-23 0ct23-uploaded-compressed.pdf11 Jun 2024
Copy of Layout Approval (in case of layout)File: H1-GG -Sanctioned Layout-23 0ct23-uploaded-compressed.pdf11 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: A-GG -Commencement- Certifiacte Dated - 30Dec2021.pdf11 Jun 2024
Commencement Certificates / NA Order for plotted developmentFile: A GG -Commencement Certificate-230ct'23-uploaded.pdf11 Jun 2024
Layout approvalFile: Sanctioned layout GG-compressed.pdf30 May 2024
Copy of Layout Approval (in case of layout)File: Sanctioned layout GG-compressed.pdf30 May 2024
Disclosure of sold/ booked inventoryFile: Inventory Report-Gloria Grand- 31st March 2024-uploaded.pdf19 Apr 2024
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: FORM 2-Gloria-Mar'24-uploaded.pdf11 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Gloria-Mar'24-uploaded.pdf10 Apr 2024
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Gloria Grand-Dec'23-uploaded.pdf3 Jan 2024
Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)File: FORM 5-Gloria Grand-FY-22-'23-uploaded11oct23.pdf11 Oct 2023
Disclosure of sold/ booked inventoryFile: Inventory data-Gloria Grand-Sept'23-uploaded.pdf10 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Gloria Grand-Sept'23-uploaded.pdf6 Oct 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Gloria Grand-Mar'23.pdf26 Jul 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: FORM 1-Gloria Grand-June'23.pdf26 Jul 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form-2-Gloria Grand-June23-uploaded.pdf11 Jul 2023
Certificates of CA (Form 3)File: FORM 3-CA certifiacte -Gloria Grand B1 B2 H1 H2.pdf26 Jun 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Form 2 - Gloria Grand-Mar 2023-uplaoded.pdf8 Apr 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gloria Grand-DEC 2019-FORM 1.pdf17 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gloria Grand-DEC 2020-Form 1.pdf17 Feb 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)File: Gloria Grand -FORM 5-F Y 21-22 -uploded 03 Feb 2023.pdf3 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 5Gloria Grand-FORM 1-Dec 2022.pdf1 Feb 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 Form 1 _- Mar 2018.PDF25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 1 GG -FORM1- Sept 18 to Mar 19 Merged -uploaded.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gloria Grand -Form 1--June 2019.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: 2 GG FORM 1- June 20 to Mar 21-Merged.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: GG mar 2022-FORM 1 uplaoded.pdf25 Jan 2023
Certificates of Architect (Form 1)(Mandatory for only ongoing project)File: Gloria Grand -Form 1-Quarter Sept 2022.pdf25 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 5 Gloria Grand -Sep-2017 -March-2018-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 7 Gloria Grand -June-2018_March-2019-FORM2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 4 Gloria Grand -June-2019 to March-2020-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gloria Grand-June-2020 to March-2021-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 6 Gloria Grand-merged files Sept 21 to mar 22-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 1 Gloriya Grand-March 2022-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 2 Gloria Grand -June 2022-FORM2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: 3 Gloria Grand -Sep 2022-FORM 2.pdf23 Jan 2023
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Gloria Grand -FORM 2-Dec-2022.pdf23 Jan 2023
Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)File: Gloria Grand Form 5 FY18-19.pdf6 Jan 2023
Proforma of Agreement for saleFile: 1 7 GLORIA RERA Agt-B1 B2 Residentia 14Nov 2022.pdf14 Nov 2022
Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)File: Form 5 Gloria Grand-min_compressed.pdf25 Oct 2021
Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)File: 12 RERA Gloria Grand compressed.pdf1 Apr 2021
Certificates of CA (Form 5)File: Gloria Grand_Form 5_18-19.pdf7 Oct 2019
Proforma of Allotment letterFile: 3 Proforma-Gloria Grand-MHADA Agreement 24 May2019.pdf24 May 2019
Proforma of Allotment letterFile: Gloria Grand-proforma Agreement and letter-MHADA-05 Apr2019.pdf10 Apr 2019
Certificates of CA (Form 5)File: Gloria Grand - PSCL.pdf3 Oct 2018
Layout approvalFile: Gloria Grand - Revised Layout.pdf25 Jul 2018
Copy of Layout Approval (in case of layout)File: Gloria Grand - Revised Layout.pdf25 Jul 2018
Commencement Certificates / NA Order for plotted developmentFile: Commencement Certificate No 2324-16.pdf25 Jul 2018
Proforma of Allotment letterFile: 2 Proforma Allotment Ltr AND Agreement Gloria Grand.pdf5 Feb 2018
Certificates of CA (Form 3)File: Form 3_CA Certificate_Gloria Grand.pdf20 Jul 2017
Declaration in FORM BFile: Form B - Gloria Grand.pdf19 Jul 2017
Certificates of Engineer (Form 2)(Mandatory for only ongoing project)File: Form 2 Gloria Grand.pdf15 Jul 2017
Proforma of Allotment letterFile: Prof_Allot Ltr and Agrmnt_Apt_Gloria Grand.pdf15 Jul 2017

Promoter's earlier projects8

As disclosed by the promoter in this filing. Where a row names its RERA number, the project links to its own page and the location and registration date are read from that registration.

7 delivered on promise1 delivered late
ProjectLocationFlatsRegisteredStatusPromisedDelivered
127 UPPER EASTP51800000454Andheri, Mumbai Suburban-Jul 2017CompletedJun 2024Registered original: Dec 2019Jan 1970
PRATHAM RESIDENTIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103035-CompletedApr 2016Mar 2016
THE BUSINESS HUBSURVEY NO25 HISSA NO 29 HISSA NO 1 KOTHRUD PUNE 41102986-CompletedJan 2016Nov 2015
MADHUKOSH - IIISNo4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune258-CompletedAug 2015Aug 2015
PRATHAM COMMERCIAL727 SADASHIV PETH KUMTHEKAR ROAD PUNE 41103032-CompletedJun 2015Apr 2015
PUNARVASUPRABHAT ROAD ERANDWANE PUNE 41100410-CompletedDec 2014Late, Jun 2015
MADHUKOSH - IISNo4 HISSA NO 2 SNO 16 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune150-CompletedDec 2013Oct 2013
MADHUKOSH - ISNo 4 HISSA NO 2 SNO 16 AND 17 part Wadgaon khurd Tal Haveli Sinhgad road Pune289-CompletedMar 2012Feb 2012

How this compares with Pune

85%of this project is bookeddistrict median 31%
26%of Pune projects moved their completion datethis one moved by 45 months
26%of Pune registrations have lapsed or been cancelledthis one is on the register

Computed across the 13,700+ Pune projects on ReraGenie, from their own filings.

Free monthly report: Pune on MahaRERA, month by month. What registered each month, this city against the other six, the possession pipeline and the pincode micro-markets, from these same filings.

Keep Gloria Grand on your shortlist

Saving puts this project on your dashboard with its booking and possession figures, ready to place side by side with up to five others. A free account also gets our weekly market digest by email.

How alerts work

Other projects near Bavadhan13,700+ in Pune

2 kmGloria GrandCompleted 58Lapsed / revoked 36Other 61Dot size: filed unitsN

Filed coordinates, straight-line distance. 155 registered projects within 2 km.

Builder: PARANJAPE SCHEMES (CONSTRUCTION) LTD

PARANJAPE SCHEMES (CONSTRUCTION) LTD has 29 registrations on MahaRERA, including SWAPNASAMRAT and Blue Ridge Project C Land T18 and T19. Its filings disclose 17 earlier MahaRERA projects: declares 9 of 17 past projects completed on time. Litigation is declared on 6 of its registrations. Read the full track record. See more projects on the Pune district page.

Frequently asked questions

What are my rights if Gloria Grand is delayed beyond 31 Dec 2026?

Under section 18 of the RERA Act you may stay in the project and claim interest for every month of delay, or exit and claim a full refund with interest. In Maharashtra the rate is SBI's highest MCLR plus 2 percent, currently 10.90% per annum (June 2026). The free delay interest calculator on ReraGenie puts a rupee figure on any delay. Claims are filed as MahaRERA complaints with a Rs 5,000 fee.

How do I verify and contact the developer of Gloria Grand?

The registered promoter entity is PARANJAPE SCHEMES (CONSTRUCTION) LTD, a company as per the filing. Neither this filing nor this promoter's other MahaRERA registrations disclose a CIN, LLPIN or GSTIN for this entity. Your agreement for sale must name this exact entity, not a group brand name. The promoter's registered address and contact details are on the project's MahaRERA listing (scan the QR code on any advertisement) and in its filed documents. The Rs 499 buyer report includes all of them as a single ZIP, foldered by type.

Is my payment protected in Gloria Grand?

Partly, by law. 70 percent of every buyer payment must go into the project's designated bank account, withdrawable only against architect, engineer and CA certificates as construction progresses; since July 2024 MahaRERA requires a three-account structure for collections. Separately, a promoter cannot take more than 10 percent of the price before signing a registered agreement for sale (section 13). Neither rule guarantees completion; they limit how far your money can travel from the project.

How do I read the complaint cases filed against Gloria Grand?

Each case number above is a complaint MahaRERA hears in public. On the MahaRERA website, open Complaint Details and search the CC number: the order PDFs, hearing dates and disposal status are free to download. Orders bind the promoter. Before booking, check whether past orders were complied with, not just whether complaints exist; an ignored order is a stronger warning than the complaint itself.

How current is the construction progress shown for Gloria Grand?

Promoters must file a quarterly progress report within 20 days of each quarter end, certified by the architect (Form 1), engineer (Form 2) and chartered accountant (Form 3). The figures above come from the latest filing, so they can trail the site by up to a quarter. A promoter who stops filing QPRs altogether invites penalties under section 61, and a stale filing date is itself a warning sign worth checking on the portal.

Who certifies construction progress at Gloria Grand?

The professionals named in the filing: Architect: Ankur Associates; Engineer: Chnadrashekhar; Chartered Accountant: Kapure & Kapure; Chartered Accountant: M S K A & Associates. Their Form 1 (architect), Form 2 (engineer) and Form 3 (chartered accountant) certificates are what unlock the promoter's withdrawals from the 70 percent account, so their names on record are part of the project's accountability chain.

What should I check before booking in Gloria Grand?

Four things this page cannot decide for you: that the carpet area in your agreement matches the filed carpet area (the model agreement allows only a 3 percent variation, with a refund right below that); that the agreement follows MahaRERA's model clauses with deviations highlighted; how the declared litigation on this registration affects your risk; why the completion date was revised and what the new timeline depends on. The Rs 499 buyer report works through all of them from the filings.

Read the whole filing and still not sure? That is what the Rs 499 buyer report is for: the conditions on this record read one by one, the progress against the promise, this promoter's other registrations, what the filed documents themselves say, and a ZIP of every document on the filing. It carries the Rs 299 project watch free for 90 days.

Get the buyer report · Rs 499 See a real one first

Studying this micro-market rather than buying a flat? The developer project analysis, Rs 2,999, maps every registration within 5 km from filed coordinates, reads what this market absorbs, prices the parcel and takes the promoter's whole book apart. See a complete sample.

Spotted something wrong on this page, or want to tell us what would make it more useful? Every page here is built from what the promoter filed on MahaRERA, and we read every report.

Report an error Share feedback

Report an error or share feedback

About Gloria Grand. Everything on this page comes from what the promoter filed on MahaRERA, so if a fact looks wrong it helps to say which one.

We read every report. We cannot promise a reply to each one.

Save Gloria Grand to a free account

It takes a minute, there is no card, and everything on this page stays free to read either way.

Create a free accountI already have one

We will save this project for you as soon as you are in.